Grenfell Tower Inquiry: Phase 2 Report, Volume 1 · 2024

Chapter 2: Executive summary

Chapter 2: Executive summary

2.1 This chapter contains an overview of the contents of our report. Our terms of reference were broad and we have followed many lines of inquiry, sometimes with unexpected results. The report is therefore inevitably lengthy and detailed. It is not possible to summarise the whole of its contents in a few pages and we have not tried to do so. The purpose of this chapter is to describe in broad terms the contents of the report and the main conclusions we have reached about the events that culminated in the tragedy at Grenfell Tower. We hope that it will assist readers in understanding the scope of the report and directing their attention to the parts of greatest interest to them. However, there is no substitute for reading the report itself.

2.2 For ease of reference we have referred to the contents of the report under headings that correspond to those of its various Parts.

Part 2 The path to disaster (Chapters 3 – 14)

2.3 In this Part of the report we describe the course of events leading up to the fire, beginning with the regulatory regime and its development in relation to the external walls of high-rise buildings. We describe the part played by the government in the form of the then Department for Communities and Local Government in the development of the statutory guidance and the investigation into the fire at Lakanal House, Southwark in 2009. We also describe the parts played by other influential bodies in creating the circumstances in which refurbishment of Grenfell Tower took place.

2.4 We conclude that the fire at Grenfell Tower was the culmination of decades of failure by central government and other bodies in positions of responsibility in the construction industry to look carefully into the danger of incorporating combustible materials into the external walls of high-rise residential buildings and to act on the information available to them.

The government

2.5 In the years between the fire at Knowsley Heights in 1991 and the fire at Grenfell Tower in 2017 there were many opportunities for the government to identify the risks posed by the use of combustible cladding panels and insulation, particularly to high-rise buildings, and to take action in relation to them. Indeed, by 2016 the department was well aware of those risks, but failed to act on what it knew. In particular, it failed to heed the warning of the Environment and Transport Select Committee in December 1999 that it should not take a serious fire in which people were killed before steps were taken to minimise the risks posed by some external cladding systems. It also failed to implement or keep under review the committee's recommendation that the large-scale test that had recently been developed should be substituted in Approved Document B for previous requirements relating to the fire safety of external cladding systems (thereby abandoning Class 0).

10

2.6 The department also failed to pay due regard to the striking results of a large-scale test in 2001 involving aluminium composite panels with unmodified polyethylene cores, which burned violently, or to take any steps either to ascertain the extent to which panels of that kind were in use or to warn the construction industry about the risks they posed. It failed even to publish the results of the test.

2.7 On many subsequent occasions the department was made aware that national Class 0 was an inappropriate standard by which to determine the suitability of external wall panels but allowed it to remain as part of the statutory guidance until after the Grenfell Tower fire. It could and should have been removed years earlier.

2.8 The review of Approved Document B carried out by the department between 2005 and 2006 provided an opportunity to clarify the guidance on compliance with functional requirement B4(1), but the language used was vague and ill-considered words were added at a late stage in the process without proper consultation.

2.9 Between 2012 and 2017 the department received numerous warnings about the risks involved in using polymeric insulation and aluminium composite panels with unmodified polyethylene cores. It also became aware of several major cladding fires abroad involving products of those kinds. By 2013 at the latest, it knew that Approved Document B was unclear and not properly understood by a significant proportion of those working in the construction industry and by February 2016 it had become aware that some in the industry were worried that combustible insulation and aluminium composite material (ACM) panels with unmodified polyethylene cores were routinely being used on high-rise buildings in breach of functional requirement B4. However, despite what it knew, and the warnings it received from some quarters, the department failed to amend or clarify the guidance in Approved Document B on the construction of external walls.

2.10 The department itself was poorly run, in as much as the official with day-to-day responsibility for the Building Regulations and Approved Document B was allowed too much freedom of action without adequate oversight. He failed to bring to the attention of more senior officials the serious risks of which he had become aware, and they in turn failed to supervise him properly or to satisfy themselves that his response to matters affecting the safety of people's lives was appropriate. It was a serious failure to allow such an important area of activity to remain in the hands of one relatively junior official.

2.11 The Building Research Establishment (originally known as the Fire Research Station) had been established in 1921 as a government body to carry out research into and testing of construction methods and products. After it was privatised in 1997 the department limited the scope of the advice it was asked to provide on fire safety matters. As a result, the department deprived itself of the full benefit of BRE's advice and experience. On occasions it deliberately curtailed investigations before any proper conclusion had been reached.

2.12 The department displayed a complacent and at times defensive attitude to matters affecting fire safety. Following the fire at Lakanal House the coroner recommended that Approved Document B be reviewed, but her recommendations were not treated with any sense of urgency and officials did not explain clearly to the Secretary of State what steps were required to comply with them. Similarly, legitimate concerns about the fire risks of cladding raised by the All-Party Parliamentary Group on Fire Safety were repeatedly met with a defensive and dismissive attitude by officials and some ministers.

11

2.13 In the years that followed the Lakanal House fire the government's deregulatory agenda, enthusiastically supported by some junior ministers and the Secretary of State, dominated the department's thinking to such an extent that even matters affecting the safety of life were ignored, delayed or disregarded.

2.14 During that period the government determinedly resisted calls from across the fire sector to regulate fire risk assessors and to amend the Fire Safety Order to make it clear that it applied to the exterior walls of buildings containing more than one set of domestic premises. Although it commissioned a review of the advice in the Local Government Association Guide Fire safety in purpose-built blocks of flats relating to the evacuation of vulnerable people, it failed to consult those who represented their interests.

The Building Research Establishment

2.15 BRE held a trusted position within the construction industry and was recognised both nationally and internationally as a leader in fire safety. However, from 1991 much of the work it carried out in relation to testing the fire safety of external walls was marred by unprofessional conduct, inadequate practices, a lack of effective oversight, poor reporting and a lack of scientific rigour.

2.16 Although BRE recognised from as early as 1991, following the fire at Knowsley Heights, that small-scale testing of the kind that provided the basis for national Class 0 did not enable a proper assessment to be made of the way in which an external wall system would react to fire, it did not draw that to the government's attention, formally or informally. Similarly, following its large-scale test of a system incorporating aluminium composite panels with unmodified polyethylene cores in 2001, BRE failed to draw the department's attention in clear terms to the way in which the material had behaved and the dangers it presented.

2.17 BRE's reports into the major fires at Knowsley Heights (1991), Garnock Court (1999) and The Edge (2005) were far from comprehensive and in each case failed to identify or assess important contributory factors. The reports of fires it provided to the department were characterised by superficiality and a lack of analysis, with the result that they gave the department the false impression that the regulations and guidance were working effectively.

2.18 There were weaknesses in the way BRE carried out tests in accordance with BS 8414 and in its record-keeping, which exposed it to the risk of manipulation by unscrupulous product manufacturers, as happened in the case of the second test carried out for Celotex, the manufacturer of the insulation specified for use on Grenfell Tower. Senior BRE staff gave advice to customers such as Kingspan and Celotex on the best way to satisfy the criteria for a system to be considered safe, thereby compromising its integrity and independence. In some cases we saw evidence of a desire to accommodate existing customers and to retain its status within the industry at the expense of maintaining the rigour of its processes and considerations of public safety. The unprofessional behaviour of some of BRE's staff was in part the result of a failure to provide them with adequate training in their responsibilities.

12

Part 3: The testing and marketing of products (Chapters 15 – 29)

2.19 One very significant reason why Grenfell Tower came to be clad in combustible materials was systematic dishonesty on the part of those who made and sold the rainscreen cladding panels and insulation products. They engaged in deliberate and sustained strategies to manipulate the testing processes, misrepresent test data and mislead the market. In the case of the principal insulation product used on Grenfell Tower, Celotex RS5000, the Building Research Establishment (BRE) was complicit in that strategy.

2.20 Those strategies succeeded partly because the certification bodies that provided assurance to the market of the quality and characteristics of the products, the British Board of Agrément (BBA) and Local Authority Building Control (LABC), failed to ensure that the statements in their product certificates were accurate and based on test evidence. UKAS, the body charged with oversight of the certification bodies, failed to apply proper standards of monitoring and supervision.

Arconic Architectural Products

2.21 Arconic Architectural Products manufactured and sold the Reynobond 55 PE rainscreen panels used in the external wall of Grenfell Tower. They were an ACM product made of two thin sheets of aluminium with a polyethylene core to provide stiffening. The material was manufactured and sold in flat sheets designed to be cut to size and attached to a metal sub-frame, either as flat panels by rivets or as three-dimensional structures, known as cassettes, by slots, making use of the force of gravity. Polyethylene burns fiercely and when used in cassette form Reynobond 55 PE was extremely dangerous.4 See in particular Part 11 chapter 109. From 2005 until after the Grenfell Tower fire Arconic deliberately concealed from the market the true extent of the danger of using Reynobond 55 PE in cassette form, particularly on high-rise buildings.5 See Part 3 Chapters 16 to 21.

2.22 The product in its riveted form had been classed under the European classification system B-s2, d0, but from early 2005 Arconic had been in possession of test data showing that in its cassette form the product reacted to fire in a very dangerous way and could not be classified in accordance with European standards. Nonetheless, Arconic persisted in telling the market that the panels had been classed B-s2, d0 without drawing any distinction between the cassette and riveted forms.

2.23 By late 2007 Arconic had become aware that there was serious concern in the construction industry about the safety of ACM panels and had itself recognised the danger they posed. By the summer of 2011 it was well aware that Reynobond 55 PE in cassette form performed much worse in a fire and was considerably more dangerous than in riveted form. Nonetheless, it was determined to exploit what it saw as weak regulatory regimes in certain countries (including the UK) to sell Reynobond 55 PE in cassette form, including for use on residential buildings.

2.24 Despite the knowledge gained from cladding fires in Dubai in 2012 and 2013, Arconic did not consider withdrawing Reynobond 55 PE in favour of the fire-resistant version then available. Instead, it allowed customers in the UK to continue buying the unmodified product, giving them to understand that it would tell them if it was unsuitable for the use to which they intended to put it, although without any intention of doing so.

13

2.25 Following further testing in 2013, Arconic decided that Reynobond 55 PE would be certified as Class E only, whether used in riveted or cassette form. However, it did not pass that information to its customers in the UK or to the BBA. That was not an oversight. It reflected a deliberate strategy to continue selling Reynobond 55 PE in the UK based on a statement about its fire performance that it knew to be false.

2.26 In December 2014 the French testing house Centre Scientifique et Technique du Bâtiment (CSTB) classified the panels in riveted form as Class C and the panels in cassette form as Class E. However, Arconic failed to inform the BBA of those revised classifications.

2.27 Although Reynobond 55 PE required some degree of fabrication and could not be used in the form in which it left the factory, Arconic persuaded the BBA to issue a certificate that drew no distinction between the different forms of fixing. It concealed important information from the BBA, in particular the test data relating to the product in cassette form, that showed that it performed much worse than in riveted form. It caused the BBA to make statements in the certificate that Arconic knew to be false and misleading.

Celotex

2.28 Celotex manufactured RS5000, a combustible polyisocyanurate foam insulation. In an attempt to break into the market for insulation suitable for use on high-rise buildings, created and then dominated by Kingspan K15, Celotex embarked on a dishonest scheme to mislead its customers and the wider market.6 See Part 3 Chapters 24 and 25.

2.29 With the complicity of BRE, in May 2014 Celotex tested in accordance with BS 8414 a system incorporating RS5000 that contained two sets of fire-resistant magnesium oxide boards placed in critical positions to ensure that it passed. It then obtained from BRE a test report that omitted any reference to the magnesium oxide boards, thereby rendering it materially incomplete and misleading.

2.30 Celotex then marketed RS5000 as "the first PIR board to successfully test to BS 8414", and as "acceptable for use in buildings above 18 metres in height". However, the test on which Celotex relied in support of that claim had been manipulated as we have described above, a fact that Celotex did not disclose in its marketing literature. Moreover, BS 8414 is a system test and does not involve the testing or classification of individual products. Celotex deliberately tucked that information away in the small print of its marketing literature.

2.31 RS5000 had previously been marketed as FR5000. From 2011 it had been sold as having Class 0 fire performance "throughout", a claim which was false and misleading. Celotex presented RS5000 to Harley as suitable and safe for use on Grenfell Tower, although it knew that was not the case.

Kingspan

2.32 From 2005 until after this Inquiry had begun, Kingspan knowingly created a false market in insulation for use on buildings over 18 metres in height by claiming that K15 had been part of a system successfully tested under BS 8414 and could therefore be used in the external wall of any building over 18 metres in height regardless of its design or other components. That was a false claim, as it well knew, because BS 8414 is a method for testing complete wall systems and its results apply only to the particular system tested. As Kingspan knew, K15 could not honestly be sold as suitable for use in the external walls of buildings over 18 metres in height generally, but that is what it had succeeded in doing for many years.7 See Part 3 Chapters 22 and 23.

14

2.33 In marketing K15 Kingspan relied on the results of a single BS 8414-1 test performed in 2005 on a system whose components were not representative of a typical external wall and it continued to rely on that test without disclosing that it had changed the composition of the product in 2006. Tests performed in 2007 and 2008 on systems incorporating the then current form of K15 were disastrous, but Kingspan did not withdraw the product from the market, despite its own concerns about its fire performance.

2.34 Kingspan concealed from the BBA the fact that the product it was selling, to which the certificate issued in 2008 referred, differed from the product that had been incorporated into the system tested in 2005. Moreover, the BBA certificate contained three important statements about the fire performance of K15 that were untrue. It used a form of words suggested by Kingspan and drawn from its own marketing literature.

2.35 In 2009 Kingspan succeeded in obtaining from the LABC a certificate that contained false statements about K15 and supported its use generally on buildings over 18 metres in height. Kingspan relied on that certificate for many years to sell the product. It made a calculated decision to use the LABC certificate to mask, or distract from, the absence of supporting test evidence.

2.36 When the BBA certificate was re-issued in 2013, Kingspan persuaded the BBA to include a statement that K15 complied with paragraph 12.7 of Approved Document B, which wrongly implied that it was a product of limited combustibility.

2.37 When it did return to carrying out tests on systems incorporating K15, Kingspan did not use the product currently on the market but used modified or trial versions. It dishonestly relied on the results of those tests to support the sale of K15 for use on buildings over 18 metres in height and continued to do so until October 2020.

2.38 Kingspan's claim that K15 met the requirements for Class 0 was based on a test of the foil facer alone and was disingenuous.

2.39 Kingspan cynically exploited the industry's lack of detailed knowledge about BS 8414 and BR 135 and relied on the fact that an unsuspecting market was very likely to rely on its own claims about the product, not least because the BBA certificate directed the buyer to consult Kingspan in relation to its use on buildings over 18 metres in height.

Siderise

2.40 Siderise manufactured the Lamatherm cavity barriers used in the refurbishment. Although there is no evidence of any dishonesty on its part, some aspects of its marketing materials gave cause for concern. It also supplied cavity barriers for use in voids larger than those for which they had been tested.

The British Board of Agrément

2.41 The British Board of Agrément (BBA) is a commercial organisation that certifies the compliance of products with the requirements of legislation. It issued certificates of compliance in respect of one of the insulation products used on Grenfell Tower, Kingspan K15, and the Reynobond 55 PE panels used as the rainscreen. Its certificates were accepted in the industry largely without question but its procedures were neither wholly independent nor rigorous and were not always rigorously applied.

15

2.42 The dishonest strategies of Arconic and Kingspan succeeded in a large measure due to the incompetence of the BBA, its failure to adhere robustly to the system of checks it had put in place, and an ingrained willingness to accommodate customers instead of insisting on high standards and adherence to a contract that was intended to maintain them. As a result of systemic shortcomings and inadequate levels of competence and technical expertise among its staff, its scrutiny of the fire performance of K15 and Reynobond 55 PE was seriously deficient and the certificates it produced for those products were misleading.

2.43 The underlying problem was that the BBA failed to manage the conflict between the need to act as a commercial organisation in order to attract and retain customers and the need to exercise a high degree of rigour and independence in its investigations in order to satisfy those who might consider relying on its certificates. It accepted for inclusion in certificates forms of wording proposed by manufacturers that were wrong and misleading. Its lack of robust processes and reluctance to enforce the terms of its contracts enabled it to become the victim of dishonest behaviour on the part of unscrupulous manufacturers.

2.44 So far as Reynobond 55 PE was concerned, the certificate issued by the BBA in 2008 contained false statements, including that the product "may be regarded as having a Class 0 surface". The BBA accepted the results of tests carried out on a different product. It failed to take advice from BRE when drafting the certificate. It completed and approved periodic reviews and re-issued the certificate without having received any new information, despite having asked Arconic repeatedly to provide it. It failed to suspend or withdraw the certificate in response to Arconic's failure to co-operate.

2.45 Until December 2013 the BBA effectively allowed the contents of the certificates relating to Kingspan K15 to be dictated by Kingspan itself, including the requirement to seek advice from Kingspan in relation to the use of the product on buildings over 18 metres in height. The BBA did not assess any aspect of the product's manufacture, testing or fire performance before it issued the certificate. It did not obtain any test data relating to K15 before it issued a certificate containing a statement that the product had been classified as national Class 0, since none existed. It ought to have known that the statement in the revised certificate issued in July 2013 implying that K15 was a material of limited combustibility was false because K15 was a phenolic foam product.

Local Authority Building Control

2.46 Local Authority Building Control (LABC) is a body formed by local authority building control departments in 2005 to provide support with training and technical matters and to provide centralised marketing and business development services for members. Following an initial assessment by a local authority building control surveyor and a second stage review by a group of experts, it issued certificates verifying the compliance of construction products and systems with the Building Regulations and Approved Documents.

2.47 The LABC must take its share of the blame for the acceptance by the market of Celotex RS5000 and Kingspan K15 for use on buildings over 18 metres in height. There was a complete failure on the part of the LABC over a number of years to take basic steps to ensure that the certificates it issued in respect of them were technically accurate.

2.48 The LABC was vulnerable to manipulation because its processes were not implemented rigorously enough. The task of producing an initial assessment should not have been given to building control officers, who did not have the degree of knowledge and experience necessary to make an informed assessment of the product in question, and those who carried out the second stage review were not always competent to do so and in some cases did not take the necessary degree of care.

16

2.49 Over a period of some years the LABC's certificates relating to Kingspan K15 and Celotex RS5000 contained misleading statements about their fire performance and about the suitability of both products for use in the external walls of buildings over 18 metres in height. Despite warnings from various quarters, the LABC failed to scrutinise properly the claims made for the products by the manufacturers and instead adopted uncritically the language they suggested. In short, it was willing to accommodate the customer at the expense of those who relied on the certificates. As a result, the LABC was also the victim of dishonest behaviour on the part of unscrupulous manufacturers.

The National House Building Council

2.50 The National House Building Council (NHBC) employed a large number of Approved Inspectors through whom it provided building control services to a large part of the housing construction industry. It also wielded considerable influence on the industry through its membership of the Building Control Alliance, a body established in 2008 to promote the role of building control bodies, and its publication of guidance notes. However, it failed to ensure that its building control function remained essentially regulatory and free of commercial pressures. It was unwilling to upset its own customers and the wider construction industry by revealing the scale of the use of combustible insulation in the external walls of high-rise buildings, contrary to the statutory guidance. We have concluded that the conflict between the regulatory function of building control and the pressures of commercial interests prevents a system of that kind from effectively serving the public interest.

The Building Research Establishment

2.51 BRE played an important part in enabling Celotex and Kingspan to market their products for use in the external walls of buildings over 18 metres in height. BRE's systems were not robust enough to ensure complete independence and the necessary degree of technical rigour at all times. As a result, it sacrificed rigorous application of principle to its commercial interests. From 2004 it had engaged in discussions with Kingspan about the steps it might take to ensure that a system incorporating K15 met the performance requirements, and during the test of a system incorporating K15 in March 2014 it gave advice on its performance, including how the results of the test might be interpreted. It accepted the inclusion of magnesium oxide boards in the system incorporating RS5000 tested for Celotex in May 2014.

United Kingdom Accreditation Service

2.52 UKAS did not always follow its own policies and its assessment processes were lacking in rigour and comprehensiveness. Even when failings were identified they were not properly explored and opportunities to improve were not always taken. The process relied too much on the candour and co-operation of the organisations being assessed and too much was left to trust. UKAS should have taken a more searching, even sceptical, attitude to the organisations it accredited. Its powers to take action were surprisingly limited, with no powers of enforcement. The most it could do in response to unsatisfactory conduct was to suspend or withdraw accreditation.

17

Part 4: The Tenant Management Organisation (Chapters 30 – 33)

2.53 The relationship between the TMO and its residents had been a troubled one for many years before the refurbishment of Grenfell Tower. Two independent reports in 2009 had drawn attention to numerous serious flaws in that relationship. The second of those reports identified governance, customer service, staff attitudes and a poor repairs service as constant themes of the investigation. It also found that the residents' lack of trust in the TMO lay at the heart of the problems. The reports made some 34 recommendations for change.

2.54 Despite those penetrating reports and the recommendations they contained, eight years later the TMO had shown little sign of any change and appeared to have learnt nothing about how to treat, or relate to, its residents.

2.55 We have concluded from all the evidence that from 2011 to 2017 relations between the TMO and many of the residents of Grenfell Tower were increasingly characterised by distrust, dislike, personal antagonism and anger. Some, perhaps many, occupants of the tower regarded the TMO as an uncaring and bullying overlord that belittled and marginalised them, regarded them as a nuisance, or worse, and failed to take their concerns seriously. For its part, the TMO regarded some of the residents as militant troublemakers led on by a handful of vocal activists, principally Edward Daffarn, whose style they found offensive. The result was a toxic atmosphere fuelled by mistrust on both sides.

2.56 In the end, however, responsibility for the maintenance of the relationship between the TMO and the Grenfell community fell not on the members of that community, who had a right to be treated with respect, but on the TMO as a public body exercising control over the building which contained their homes. The TMO lost sight of the fact that the residents were people who depended on it for a safe and decent home and the privacy and dignity that a home should provide. That dependence created an unequal relationship and a corresponding need for the TMO to ensure that, whatever the difficulties, the residents were treated with understanding and respect. We have concluded that the TMO failed to recognise that need and therefore failed to take the steps necessary to ensure that it was met.

2.57 However irritating and inconvenient it may at times have found the complaints and demands of some of the residents of Grenfell Tower, for the TMO to have allowed the relationship to deteriorate to such an extent reflects a serious failure on its part to observe its basic responsibilities.

18

Part 5: The management of fire safety at Grenfell Tower (Chapters 34 – 46)

2.58 RBKC and the TMO were jointly responsible for the management of fire safety at Grenfell Tower. The years between 2009 and 2017 were marked by a persistent indifference to fire safety, particularly the safety of vulnerable people. We have examined in detail a wide variety of matters that have led us to that conclusion, the most prominent of which we set out here.

2.59 RBKC was responsible for overseeing the TMO's activities, not monitoring its operations on a day-to-day basis, but its oversight of the TMO's performance was weak and fire safety was not subject to any key performance indicator. The absence of any independent or rigorous scrutiny by RBKC of the TMO's performance of its health and safety obligations, and in particular its management of fire safety, was a particular weakness. RBKC took little or no account of an independent and highly critical review of fire safety carried out for the TMO in 2009. It did not even know about a further independent and highly critical report produced in 2013 because the TMO had failed to disclose it to RBKC.8 See Part 5 Chapter 37.

2.60 The TMO's performance of its own functions and the effectiveness of RBKC's oversight depended on full and candid reporting by the TMO's senior management to its board. Although there was a satisfactory system for senior management to report to the board and to RBKC, it did not operate effectively because of an entrenched reluctance on the part of the TMO's chief executive, Robert Black, to inform the board and RBKC's scrutiny committees of matters that affected fire safety. That failure was all the more serious because there were chronic and systemic failings in the TMO's management of fire safety of which the board should have been made aware. Robert Black consistently failed to tell either the board or RBKC of the LFB's concerns about the TMO's compliance with the Fire Safety Order or the steps taken to enforce it.

2.61 First, although in 2009 an independent fire safety consultant had recommended that a fire safety strategy be prepared, nothing was done until November 2013 and a strategy had still not been finally approved by the time of the Grenfell Tower fire.

2.62 Secondly, the TMO's only fire assessor for its entire estate, Carl Stokes, was allowed to drift into that role without any formal selection or procurement process. He had misrepresented his experience and qualifications (some of which he had invented) and was ill-qualified to carry out fire risk assessments on buildings of the size and complexity of Grenfell Tower, let alone to hold the entire TMO portfolio. As a result there was a danger that fire risk assessments would not meet the required standard.

2.63 Thirdly, although Mr Stokes' methods for carrying out fire risk assessments generally reflected the Health and Safety Executive's five steps for managing risks, the LGA Guide and PAS 79, they suffered from serious shortcomings. He often failed to check whether the TMO had taken action in response to risks he had identified in previous assessments. Despite the concerns expressed by the LFB about his competence, the TMO continued to rely uncritically on him, a situation which made the danger more acute in the absence of any arrangements for assessing the quality of his work.

19

2.64 Fourthly, there was no adequate system for ensuring that defects identified in fire risk assessments were remedied effectively and in good time. The TMO developed a huge backlog of remedial work that it never managed to clear, a situation that was aggravated by the failure of its senior management to treat defects with the seriousness they deserved. Indeed, on one occasion senior management intervened to reduce the importance attached to the implementation of remedial measures. The demands of managing fire safety were viewed by the TMO as an inconvenience rather than an essential aspect of its duty to manage its property carefully.

2.65 Certain important features of the fire prevention measures at Grenfell Tower were not of an appropriate standard. For example, the new front doors installed by the TMO in 2011 and 2012 did not meet the fire resistance standards suggested by Approved Document B because the TMO had failed to specify the correct fire safety standard when ordering them.

2.66 Inspection and maintenance regimes affecting fire prevention systems did not reflect best practice and were inconsistently followed. Many self-closing devices on the front doors of flats in Grenfell Tower failed to work effectively and some were missing entirely. The TMO did not institute an effective inspection and maintenance programme for self-closing devices on entrance doors despite an Enforcement Notice issued by the LFB in late 2015 relating to ineffective door closers in another high-rise residential building it managed, Adair Tower, and a Deficiency Notice issued in 2016 in relation to Grenfell Tower itself on the same grounds.

2.67 Although the TMO had no obligation to produce a general evacuation plan, its Emergency Plan for Grenfell Tower was out of date and incomplete and did not reflect the changes brought about by the refurbishment. The TMO was well aware of that fact following a fire at Adair Tower in October 2015, but failed to address it. The absence of fire action notices in the tower was a prominent subject of complaints by residents and led to the issue of a Deficiency Notice in November 2016.

2.68 The Grenfell Tower fire revealed the importance of ensuring that the responsible person under the Fire Safety Order collects sufficient information about any vulnerable occupants to enable PEEPs to be prepared, when appropriate, and, in the event of a fire, appropriate measures to be taken to assist their escape. The TMO did take some steps to gather information of that kind, both before and during the refurbishment, but its data systems were not properly co-ordinated. Such information as was collected was not always used to revise its records, with the result that the spreadsheet available on the night of the fire was incomplete. The TMO's failure to collect such information amounted to a basic neglect of its obligations in relation to fire safety.

20

Part 6: The refurbishment of Grenfell Tower (Chapters 47– 67)

2.69 In this Part we trace the origins of the refurbishment project and its relationship to the Kensington Aldridge Academy and Leisure Centre (KALC) projects. We describe the persons and organisations principally involved in the project and the legislative background against which the refurbishment was carried out. We also identify two significant problems relating to Approved Document B that in our view call for urgent attention. The first is the assumption that compliance with functional requirements B3 and B4 will provide a high degree of compartmentation, thus rendering evacuation of the building unnecessary. The second is the tension between functional requirements of the Building Regulations and the prescriptive language of the guidance and the propensity of many in the industry to treat the guidance as definitive.

2.70 We explain how the KALC project influenced the appointment of Studio E as architect and describe the way in which the TMO manipulated the procurement process to avoid having to put the contract for architectural services out to public tender. Artelia was appointed by the TMO as a consultant, having acted as employer's agent and quantity surveyor for the KALC project.

2.71 The initial plans for the refurbishment ran into difficulties because the estimated cost of the project produced by the principal contractor on the KALC project exceeded the budget by a significant margin. However, in about May 2013 the TMO's former emphasis on maintaining the momentum of the project changed to one of saving cost. That led in turn to a recommendation, reluctantly supported by Artelia, that a principal contractor should be appointed through a formal procurement process. Such a process was then implemented.

2.72 Although Rydon's tender was judged to be the most competitive, it still exceeded the TMO's budget. As a result, although the TMO had received advice from its lawyers that it would be improper to do so, it entered into discussions with Rydon before the procurement process had been completed leading to an agreement that, if Rydon were awarded the contract, it would reduce its price to an acceptable level.

2.73 Although Studio E had wanted to use zinc rainscreen panels, cost became an increasingly important consideration for the TMO and eventually an aluminium composite material (ACM), Reynobond 55 PE, was chosen, largely on the grounds of cost. Rydon was able to offer a substantial saving through the use of ACM panels as a result of its relationship with its intended cladding sub-contractor, Harley.

2.74 The choice of combustible materials for the cladding of Grenfell Tower resulted from a series of errors caused by the incompetence of the organisations and individuals involved in the refurbishment. Studio E, Rydon and Harley all took a casual approach to contractual relations. They did not properly understand the nature and scope of the obligations they had undertaken, or, if they did, paid scant attention to them. They failed to identify their own responsibilities for important aspects of the design and in each case assumed that someone else was responsible for matters affecting fire safety. Everyone involved in the choice of the materials to be used in the external wall thought that responsibility for their suitability and safety lay with someone else.

21

2.75 None of those involved in the design of the external wall or the choice of materials acted in accordance with the standards of a reasonably competent person in their position. They were not familiar with or did not understand the relevant provisions of the Building Regulations, Approved Document B or industry guidance. Studio E demonstrated a cavalier attitude to the regulations affecting fire safety and Rydon and Harley relied on their previous experience rather than on any technical analysis or expertise. The risks of using combustible materials in the external walls of high-rise buildings were well known and they should have been aware of them.

2.76 RBKC building control did not properly scrutinise the design or choice of materials and failed to satisfy itself that on completion of the work the building would comply with the requirements of the Building Regulations.

2.77 Exova was instructed by Studio E on behalf of the TMO to prepare a fire safety strategy for the building in its refurbished form. A draft was prepared but never completed. In particular, it did not include an analysis of the external wall or its compliance with functional requirement B4(1) of the Building Regulations.

2.78 Although our criticisms are directed principally towards Studio E, Exova, Rydon, Harley and RBKC building control, the TMO must also bear a share of the blame for the disaster because it failed to ensure that the position of Exova was clarified after Rydon had been appointed and that the fire safety strategy was completed.

2.79 As architect Studio E was responsible for the design of the external wall and for the choice of the materials used in its construction.9 See generally Part 6 Chapter 63. Although the TMO as the client wanted to reduce the cost by using ACM rainscreen panels, it was the responsibility of Studio E to determine whether the use of such material would enable the building to comply with functional requirement B4(1) of the Building Regulations and advise the TMO accordingly. Its failure to recognise that ACM was dangerous and to warn the TMO against its use represented a failure to act in accordance with the standard of a reasonably competent architect. It also failed to recognise that Celotex insulation was combustible and not suitable for use on a building over 18 metres in height in accordance with the statutory guidance. Studio E therefore bears a very significant degree of responsibility for the disaster.

2.80 We have identified many other respects in which Studio E failed to meet the standards of a reasonably competent architect, of which the following are the most significant. It failed to ensure that Exova completed the fire safety strategy for the refurbished building or advise Rydon and the TMO that it should be required to do so. It failed to understand that it was responsible for design work carried out by sub-contractors and so did not check Harley's designs to ensure that on completion the building would comply with the Building Regulations. It did not devise a proper cavity barrier strategy or check Harley's designs for the cavity barriers and it failed to produce detailed drawings of the window reveals or to notice that the materials specified for the window infill panels were unsuitable.

2.81 Exova also bears considerable responsibility for the fact that Grenfell Tower was in a dangerous condition on completion of the refurbishment.10 See generally Part 6 Chapter 54. Our most serious criticism is that it failed to produce a final version of the fire safety strategy for the refurbished building and that it failed either to draw that fact to the attention of the design team or to warn it about the potential consequences. None of those responsible for drafting the fire safety strategy visited Grenfell Tower; the only site visit by a member of Exova's staff took place at a preliminary stage. Exova's attitude was wholly inconsistent with the careful approach to matters affecting the safety of life to be expected of a reasonably competent fire engineer.

22

2.82 We consider that the principal contractor, Rydon, also bears considerable responsibility for the fire.11 See generally Part 6 Chapter 64. It gave inadequate thought to fire safety, to which it displayed a casual attitude throughout the project and its systems for managing the design work did not ensure that its sub-contractors and consultants properly understood their different responsibilities. Rydon itself did not understand where responsibility for individual decisions lay and as a result it failed to co-ordinate the design work properly.

2.83 Rydon had an inexperienced team on the refurbishment that did not have sufficient knowledge of the Building Regulations or Approved Document B. It relied entirely on its cladding sub-contractor, Harley, to draw its attention to any errors in the design, but it did not specifically ask Harley to assess Studio E's work. It failed to take proper steps to investigate Harley's competence and ensure that it was competent to undertake the work and capable of providing the services required of it. It was complacent about the need for fire engineering advice and took the decision not to retain Exova without consulting the TMO, Studio E or Artelia. Its understanding of the work already carried out by Exova was superficial; as a result, it failed to realise that the fire safety strategy had not been completed.

2.84 Harley itself failed in many respects to meet the standards to be expected of a reasonably competent cladding contractor and it too bears a significant degree of responsibility for the fire.12 See generally Part 6 Chapter 65. It did not concern itself sufficiently with fire safety at any stage of the refurbishment and appears to have thought that there was no need for it to do so, because others involved in the project, and ultimately building control, would ensure that the design was safe. It failed to ask the kind of questions about the materials being considered that a reasonably competent cladding contractor would have asked. It was induced to buy Reynobond 55 PE panels partly by its existing relationship with Arconic and the cladding fabricator, CEP Architectural Facades, with which it was able to negotiate a favourable price. Its staff were unaware of the requirements of the Building Regulations relating to fire safety, the guidance in Approved Document B or industry guidance and did not understand the underlying testing regime.

2.85 Although Celotex RS5000 (as opposed to Celotex FR5000) had not been specified, Harley accepted it for use on the tower without enquiring in any detail whether it could be safely used and did not ask any of the other members of the design team that question before doing so. Its design for the cavity barriers was incomplete and did not comply with the guidance in Approved Document B.

2.86 RBKC's building control department failed to perform its statutory function of ensuring that the design of the refurbishment complied with the Building Regulations.13 See generally Part 6 Chapter 62. It therefore bears considerable responsibility for the dangerous condition of the building immediately on completion of the work. The surveyor responsible for the refurbishment was overworked, inadequately trained and had a very limited understanding of the risks associated with the use of ACM panels. He failed to obtain full information about the construction of the external wall at the stage of the full plans application and did not ask whether Exova had provided a completed fire safety strategy. He knew that ACM was to be used as the rainscreen but paid little or no attention to the BBA certificate for Reynobond 55 PE. He failed to recognise that Celotex RS5000 insulation was not a material of limited combustibility and, if he looked at any information about it, he simply accepted the assertion that it was suitable for use on tall buildings. He failed to consider whether the external wall system proposed for Grenfell Tower was the same as that tested by Celotex and said to support the use of RS5000.

23

2.87 The TMO must also take a share of the blame for the disaster.14 See generally Part 6 Chapter 66. As the client it failed to take sufficient care in its choice of architect and paid insufficient attention to matters affecting fire safety, including the work of the fire engineer.

24

Part 7: Replacement of the gas riser (Chapter 68)

2.88 This short chapter describes the work carried out in 2016 and 2017 to replace one of the six gas risers in Grenfell Tower that was suffering from corrosion. There were defects in the design and execution of the work, to which we draw attention. The work had not been completed by the time of the fire, but neither the defects we have identified nor the failure to have completed the work contributed to the fire.

2.89 On the night of the fire it was not possible to find the two pipeline isolation valves designed to enable the supply of gas to the tower to be shut off quickly, almost certainly because they had been covered over in the course of landscaping work. However, that did not affect the course of events surrounding the fire because burning debris falling on the east side of the tower would have prevented access to them.

25

Part 8: The London Fire Brigade (Chapters 69 – 83)

2.90 The Lakanal House fire in July 2009 should have alerted the LFB to the shortcomings in its ability to fight fires in high-rise buildings that revealed themselves once more at Grenfell Tower on the night of 14 June 2017. Those shortcomings could have been made good if the LFB had been more effectively managed and led. In particular, it should have responded more effectively to its experience at Lakanal House and made better use of the knowledge it had gained of the dangers posed by modern materials and methods of construction. Importantly, it failed to ensure that in the years immediately preceding the Grenfell Tower fire regular training of a suitable kind was provided to its control room operators on handling many fire survival guidance calls concurrently and on their duties more generally. Senior managers at the LFB failed to take steps to ensure that its arrangements for handling fire survival calls reflected national guidance.

2.91 Those failures were attributable to a chronic lack of effective management and leadership, combined with an undue emphasis on process. Senior officers were complacent about the operational efficiency of the brigade and lacked the management skills to recognise the problems or the will to correct them. Those managerial weaknesses were partly the result of an historic failure to integrate the operational departments and the departments responsible for support functions, in particular the control room. There was a tendency to treat problems of which managers became aware as undeserving of change or too difficult to resolve, even when they concerned operational or public safety.

2.92 Those failures were compounded by an entrenched but unfounded assumption that the Building Regulations were sufficient to ensure that external wall fires of the kind that were known to have occurred in other countries would not occur in this country. After the Lakanal House fire senior officers recognised that compliance with the regulations could not be guaranteed, but no one appears to have thought that firefighters needed to be trained to recognise and deal with the consequences.

2.93 The main failings on the part of the LFB that led to the shortcomings identified in the Phase 1 report included a failure to identify training needs combined with a system for commissioning new training packages that was cumbersome and slow. Incident command training was poorly devised and was not effectively delivered; inadequate provision was made for refresher training and regular assessment.

2.94 The LFB failed to ensure that the knowledge of the dangers presented by the increasing use of combustible materials, in particular the risk of external fire spread and the resulting loss of compartmentation, held by some specialist officers was shared with the wider organisation and reflected in training, operational policies and procedures. Firefighters were not given proper training or guidance on how to carry out inspections of complex buildings and there were no effective arrangements for sharing information about risks posed by particular buildings. Internal recommendations for improving the inspection of high-rise residential buildings were not implemented.

2.95 The policy on high-rise firefighting did not reflect national guidance and senior management failed to recognise that producing contingency plans for a full evacuation and training firefighters to implement them was an essential aspect of fighting fires in high-rise buildings.

26

2.96 One significant shortcoming was a failure to recognise the possibility that in the event of a fire in a high-rise residential building a large number of calls seeking help, both from within and outside the building, might be generated. The LFB failed to take any steps to enable it to respond effectively to that kind of demand. As a result, when faced with a large number of calls about people needing to be rescued from Grenfell Tower, both those in the control room and those responsible for handling that information at the fireground were forced to resort to various improvised methods of varying reliability to handle the large amount of information they received.

2.97 The senior officers responsible for the control room understood the need to give priority to training staff in handling fire survival guidance calls, but in the years between 2010 and 2017 no structured or regular refresher training in handling fire survival guidance calls was designed or delivered to control room staff. Such training as was provided did not reflect national guidance in some respects; nor did it respond to the experience of those control room officers who had been on duty at the time of the Lakanal House fire. The failures in the effective functioning of the control room were due in a large measure to weak management over the preceding years combined with sporadic and ineffectual oversight by senior officers.

2.98 The communication equipment in use at the time of the Grenfell Tower fire proved to function inadequately in a high-rise building constructed largely of reinforced concrete. That was a well known problem but nothing had been done to alleviate it and firefighters were not trained to recognise and respond to it. The LFB's approach was to do its best with what it had available. As a result, it failed to make sufficient efforts to modernise its equipment, thereby significantly impairing its operational efficiency. The LFB's policies did not contemplate a widespread loss of communications or provide guidance on how it could effectively be restored.

27

Part 9: The deceased (Chapters 84 – 97)

2.99 The detailed description of the events of 14 June 2017 contained in the Phase 1 report places us in a good position to make comprehensive findings about the circumstances in which the deceased met their deaths. Although it is for the coroner to decide whether she should adopt our findings as sufficient to enable her to discharge her responsibilities, we hope that she will be able to do so and thus spare the bereaved the distress of a further investigation.

2.100 We begin this Part with a general introduction followed by a description of the painstaking methods adopted to recover and identify the remains of the individual deceased. In that context we refer to the work of the teams of forensic archaeologists, forensic anthropologists and forensic pathologists, as well as other experts and police disaster victim identification officers and licensed search officers. We also describe in general terms the evidence given by Professor David Purser CBE BSc PhD DipRCPath, an expert on toxicology.

2.101 We devote a separate chapter of this Part to each floor on which people died. After a general description of the circumstances affecting that floor, our findings deal in turn with each of those who died on, or fell from, that floor. In the case of those who died on the stairs we have described the circumstances relating to the floor on which their flat was located. In each case we give a brief description of the deceased before describing the immediate circumstances in which he or she died.

2.102 Although the evidence was sometimes rather confused, we have been able to make findings about emergency calls made by those who were trapped, the transmission of information from the LFB control room to the incident ground and thence to the bridgehead and the deployment of firefighters in response. To the extent possible we have made what we consider to be reliable findings about the time of death in each case, although in many cases there is inevitably a large measure of uncertainty. In the light of the expert evidence we are able to make findings about the cause of death, including findings that all those whose bodies were destroyed by the fire were dead or unconscious when the fire reached them.

28

Part 10: Response and recovery (Chapters 98 – 107)

2.103 In the first week after the fire at Grenfell Tower the response of the government and RBKC was muddled, slow, indecisive and piecemeal. RBKC's systems and leadership were wholly inadequate to the task of handling an incident of such magnitude and gravity, involving, as it did, mass homelessness and mass fatalities. The resilience machinery in London and within central government was not flexible enough and took too long to move into action.

2.104 Certain aspects of the response demonstrated a marked lack of respect for human decency and dignity and left many of those immediately affected feeling abandoned by authority and utterly helpless. RBKC should have done more to cater for those from diverse backgrounds, in particular those many residents of the Muslim faith who were observing Ramadan at the time. They were left feeling that the council had no regard for their cultural and religious needs. For many, their only source of support was local voluntary organisations, which moved in to help and provide for basic needs where those in authority had failed. Many who had particular religious, cultural or social needs suffered a significant degree of discrimination in ways that could and would have been prevented if the guidance had been properly followed.

2.105 The response to the disaster was inadequate principally because RBKC did not have an effective plan to deal with the displacement of a large number of people from their homes and such plan as it did have did not make effective use of the TMO. It had made no contingency arrangements for obtaining a large amount of emergency accommodation at short notice and had no arrangements for identifying those who had been forced to leave their homes or for communicating with them. Arrangements for obtaining and disseminating reliable information were also lacking.

2.106 One reason for the lack of effective plans was that RBKC had failed to train its staff adequately. They did not have a sufficient understanding of the importance of resilience or sufficient commitment to it. Exercises had not been held regularly and staff had not been required to attend the training sessions run by the London Resilience Group. Deficiencies that were well known to senior management had not been corrected.

2.107 Over a number of years, RBKC had allowed the capacity of its staff to respond to major emergencies to decline. There had been clear warnings to senior management that it did not have enough trained staff to enable it to carry out its responsibilities as a Category 1 responder and that contingency plans had not been practised enough. As a consequence, RBKC lacked the people it needed to respond to the fire effectively, both for the purposes of staffing the borough emergency communication centre and to deal with those who needed help. It was therefore ill-equipped to deal with a serious emergency. None of that was due to any lack of financial resources.

2.108 RBKC's chief executive, Nicholas Holgate, was not capable of taking effective control of the situation and mobilising support of the right kind without delay. He had no clear plan and did not receive all the information he needed. He was not well suited to dealing with the crisis that was unfolding in front of him and lacked a strong group of officers to whom he could delegate responsibility for some aspects of the response. He was reluctant to take advice from those with greater experience and was unduly concerned for RBKC's reputation.

29

2.109 RBKC had failed to integrate the TMO into its emergency planning. It should have realised that the TMO's knowledge of its buildings and their occupants could play an important part in the response to any disaster affecting any part of its housing stock.

2.110 The arrangements designed to promote the resilience of London as a whole did not provide for an experienced leader to take over the direction of the response to a disaster that had occurred within the confines of a single borough except by agreement with the chief executive of that borough. In the event, Nicholas Holgate was persuaded under pressure from a senior government official to hand over control to John Barradell, but not until two days after the fire.

2.111 The training of resilience personnel in London was piecemeal and not co-ordinated; it was also voluntary and not subject to any external assessment or validation. That contributed to a situation in which the capacity of individual local authorities to respond to emergencies varied between boroughs.

2.112 The government began monitoring the response to the fire at an early stage, but its ability to take effective steps to provide practical assistance was undermined by a shortage of reliable information and by the restricted nature of its powers to intervene. The Civil Contingencies Act 2004 did not give it the power to take control of the response without invoking the powers under sections 5 or 7. Those powers are far-reaching but cumbersome in operation and not well suited to taking control of the response when a local authority is failing.

2.113 The TMO attracted criticism from many quarters, but in relation to its response to the fire much of it was unfair. Although its staff should have received more training in how to respond to an emergency, they threw themselves into the response and helped to provide support, insofar as they were equipped to do so. Some of those within government who criticised the TMO did not properly understand its position or the scope of its powers, and it was unfairly tainted by association with RBKC. Many of the difficulties encountered in returning residents to flats in the Walkways were not of its making. The TMO teams that went to some of the rest centres on 14 June 2017 to give what help they could are to be commended for their willingness to become directly involved and for the efforts they made at what was a very difficult time.

2.114 Those who emerge from the events with the greatest credit, and whose contribution only emphasised the inadequacies of the official response, are the members of the local community. With the support of local voluntary organisations, they provided support in the hours immediately following the fire when the authorities were conspicuous by their absence. Indeed, one of RBKC's failings was to make too little use of the local voluntary organisations and to fail to have adequate standing arrangements to enable them to be called on in the event of a major emergency.

30

Part 11: Matters outstanding from Phase 1 (Chapters 108 – 110)

2.115 Two matters remained outstanding from Phase 1. The first concerned the respective contributions to the fire made by the ACM rainscreen panels and the polyisocyanurate and phenolic insulation boards. The second concerned the mechanism by which the fire had escaped from the kitchen of Flat 16 into the external wall of the building.

2.116 In a series of experiments designed by Professor Bisby and Professor Torero and carried out at Edinburgh University by Professor Bisby and his colleagues the ACM panels were shown to have been by far the largest potential contributor to energy release in the external wall system at Grenfell Tower. Celotex RS5000 (a polyisocyanurate foam) and Kingspan K15 (a phenolic foam) both had a much lower heat release rate per unit area.

2.117 The experiments showed that the presence of a cavity is not by itself sufficient to cause a fire in the rainscreen panels to develop to full involvement. Insulation also needs to be present, either to retain energy in the system or to burn and contribute additional energy. Even non-combustible insulation in the form of mineral wool resulted in the growth of the fire to full involvement of the ACM panel. The method of fixing the panels has a significant effect on the way in which they perform in a fire. Panels in cassette form behave far worse than panels in riveted form.

2.118 The experimental work confirms that the principal factor which led to the rapid growth of the fire was the presence of unmodified polyethylene in the cores of the ACM panels rather than the insulation, although the presence of the insulation and its ability to retain heat was a decisive factor in promoting the growth of the fire.

2.119 The second matter outstanding concerned the mechanism by which the fire had escaped from the kitchen of Flat 16 into the external wall of the building. A reconstruction carried out by BRE in May 2019 had led it to conclude that the mechanism was different from that identified by Professor Bisby and Professor Torero. The chairman therefore indicated that the findings expressed in the Phase 1 report would remain provisional until they had had a better opportunity to study the report of the reconstruction. Having done so, Professor Bisby and Professor Torero both concluded that the reconstruction had not been truly representative of the fire that occurred on 14 June 2017 and adhered to their original opinions. We therefore confirm the findings made in the Phase 1 report.

31

Part 12: The fire testing regime (Chapter 111)

2.120 In the years leading up to the Grenfell Tower fire test methods available for determining the reaction to fire of materials, products and even external wall systems did not provide designers with the information needed to assess the risk of fire spreading across the external wall of a building. Moreover, the statutory guidance on complying with functional requirement B4(1) of the Building Regulations was fundamentally defective.

2.121 The use of Class 0 as a standard of fire performance for products to be used on the external wall of tall buildings was wholly inappropriate. Neither of the main British Standard tests relevant to that classification reflected the development of a fire on the outside of a building or provided the information needed to assess how an external wall incorporating the product would perform in a fire. The European classifications based on the single burning item test were of similarly limited assistance in assessing the fire performance of external wall systems.

2.122 The performance criteria for large-scale system tests in BR 135 were inadequate, in particular because they could not be clearly linked to the functional requirements in the Building Regulations or the guidance in Approved Document B. They were also directed too much to the spread of flame through cavities and contained no criteria for mechanical performance. The BS 8414 test itself provided limited information relevant to assessing the rate at which fire was likely to spread over an external wall. Critically, an external wall system that met the criteria in BR 135 could still allow fire to spread through it and beyond the compartment of origin at a rate that was incompatible with a stay put strategy. Accordingly, although failure to meet the performance criteria in BR 135 would demonstrate that a system was unlikely to comply with functional requirement B4(1) of the Building Regulations, the converse was not necessarily true. A system might meet the performance criteria of BR 135 and yet fail to comply with the functional requirement.

2.123 There was a widespread but erroneous assumption that, if an external wall system tested in accordance with BS 8414 met the performance criteria in BR 135, the building would comply with functional requirement B4(1) without any need to analyse the information obtained from the test or the conditions likely to be encountered in use. Approved Document B helped to perpetuate that assumption, not least by failing to make it clear that the results of the test always had to be analysed in conjunction with all other available information in order to understand the way in which the wall was likely to behave when exposed to the flames and heat of a fully developed compartment fire. The method adopted in BR 135 for assessing compliance was too simplistic. It provided a simple pass or fail result, when the results of the test required a degree of interpretation beyond the competence of most in the industry.

32

Part 13: The response of other countries (Chapter 112)

2.124 We have referred in the course of our report to fires that have occurred in other tall buildings around the world, principally as a result of the use of ACM rainscreen products. With the help of Professor Torero, who has extensive knowledge of the regulatory regimes in many other jurisdictions, we have examined the response of other countries to the danger posed by combustible cladding in order to see what we can learn from their experience.

2.125 In this chapter we describe the approaches to the problem that have been adopted in countries from the United States through Europe and the Middle East to Australia. Some countries have adopted a prescriptive approach to regulating construction, which is fundamentally different from a regime based on functional requirements of the kind that applies in this country and is therefore less useful as a model. Others, however, in particular Australia, have adopted functional requirements similar to our own and provide an example from which we can learn.

Part 14: Recommendations (Chapter 113)

2.126 We are invited by our Terms of Reference to make recommendations that we have reason to think will help prevent another disaster of the kind that overwhelmed Grenfell Tower and improve the ability of the authorities to respond to emergencies when they occur, as inevitably they will.

2.127 We do not think it would be appropriate or helpful to attempt to summarise those recommendations here because to do so would inevitably fail to do them justice. We should make it clear, however, that they are all firmly grounded in the evidence we have received and the findings we have made.

33