Deep Water: The Gulf Oil Disaster and the Future of Offshore Drilling
DEVELOPMENT & PRODUCTION PLAN DEVELOPMENT & PRODUCTION PLAN APPROVED PRODUCTION WELL APPLICATION FIRST OIL / GAS PRODUCTION
DEVELOPMENT & PRODUCTION PLAN DEVELOPMENT & PRODUCTION PLAN APPROVED PRODUCTION WELL APPLICATION FIRST OIL / GAS PRODUCTION
¶Four major steps guide the Outer Continental Shelf leasing and development process, from the decision to open an area to drilling, to the operations during oil and gas production. Before a lease is granted, Stage I establishes the "5-Year Program," setting the schedule and possible locations for individual lease sales, and Stage II lays out the details by which each individual lease sale is conducted. After a company acquires a lease, Stage III plans and executes the oil and gas exploration activities, and Stage IV plans and executes the oil and gas development and production operations.
¶At the same time, the statute also made clear that environmental safeguards are a relevant, important part of the Secretary's decisionmaking. For instance, it charged the Secretary "to obtain a proper balance between the potential for environmental damage, the potential for discovery of oil and gas, and the potential for adverse impact on the coastal zone."39 The law also expressly required the Secretary to prepare a series of "environmental studies"
62to assess the environmental impacts of activities on the outer continental shelf,40 and "the Secretary of the Department in which the Coast Guard is operating" (currently the Department of Homeland Security) to promulgate "safety regulations."41 Such regulations were to include "the use of the best available and safest technologies which the Secretary [of the Interior] determines to be economically feasible, wherever failure of equipment would have a significant effect on safety, health, or the environment."42 But this potentially demanding requirement included an exception "where the Secretary determines that the incremental benefits are clearly insufficient to justify the incremental costs of utilizing such technologies."43
The Gulf of Mexico exemption. Offsetting the apparent interest in environmental review, the Act reflected a carefully calibrated political compromise designed to promote offshore drilling: it expressly exempted leases in the "Gulf of Mexico" from the law's requirement that development and production pursuant to an oil and gas lease must be based on and consistent with a "development and production plan" submitted by the lessee and approved by the Secretary of the Interior.44 (No comparable exception applied to "exploration plans," which all lessees were required to submit for approval prior to conducting such drilling, which naturally occurs prior to development and production.45) The telling compromise lay in the details: the law specified that a development and production plan must set forth "the environmental safeguards to be implemented"46 and the Secretary must at least once declare the approval of a development and production plan in any area "to be a major Federal action"—language which triggers NEPA's requirement for an impact statement detailing the environmental consequences of development and production.47 Therefore, by exempting leases in the Gulf from the required "development and production plan," the Act was also exempting such leases from the related requirement of at least one NEPA impact statement.48 And the Act included one further bit of congressional horse-trading. It authorized the Secretary of the Interior to reinstate the development and production plan requirements, including NEPA review, for an oil and gas lease located in the eastern planning area of the Gulf abutting the western coastline of Florida, leaving only the central and western Gulf planning areas off limits from such requirements.49
63The legislative history makes clear that this was a deal brokered between the Carter administration, the oil and gas industry, Congress, and Gulf states. Industry had argued that NEPA and similar requirements could lengthen the interval between leasing and production by three to six years. In response to this concern, Congress amended the bill to draw a distinction between the Gulf of Mexico, where such consultation would not be required, and other offshore areas where it would. The rationale for singling out the Gulf of Mexico for less environmental oversight than other parts of the nation's offshore was that the oil and gas industry in the Gulf was already mature and therefore the environmental risks were already better known than they were in "frontier" areas. This rough geographically-defined generalization took no account of the Gulf 's remarkable fisheries, or the economic importance of the region's beaches to the tourism industry. Secretary of the Interior Cecil Andrus sought administrative discretion to require the full environmental review even in some non-frontier areas if drilling in those areas proved to present heightened environmental risks,50 but the final legislation made that further concession only for a part of the Gulf.51
¶A compromise comes undone. Whatever compromise Congress and President Carter may have thought they had struck in the 1978 legislation quickly unraveled. In the first five-year leasing schedule issued in June 1980, Secretary Andrus offered 55 million acres, and proposed Lease Sale 53 along the Pacific Coast. Unlike previous sales, which had been concentrated on one geographic region, Lease Sale 53 called for nominations of tracts from the Santa Barbara Channel all the way up the California coast to the Oregon border. Fierce opposition immediately greeted the proposed leasing schedule and Lease Sale 53. California and Alaska filed lawsuits challenging the legality of the leasing schedule under the 1978 law. After huge public rallies, Secretary Andrus formally withdrew the entire northern and central California portion of the proposed sale.52
¶The Creation of the Minerals Management Service (MMS) Against a backdrop of rising inflation, record interest rates, further turbulence in the oil market following the 1979 Iranian revolution, and a severe recession, the politics of offshore drilling became even more volatile early in the administration of President Ronald Reagan, who was inaugurated in January 1981. Perhaps not surprisingly, after the upwelling of new regulatory powers under Presidents Nixon, Ford, and Carter, the new President made clear from the outset his view that government regulation was a leading cause of the nation's problems—a drag on the nation's economy in general and the development of its rich natural resources in particular.
¶MMS originated in this context, driven by the administration's desire to ensure that it obtained the financial fruits of its plan for this massive expansion in offshore drilling. With the dramatic increase in oil prices over the previous decade, royalties and revenues from federal oil and gas resources had already become the second largest revenue source for the U.S. Treasury. (A September 1980 lease sale in New Orleans had demonstrated the sums potentially at stake, bringing in a record $2.8 billion of cash bonuses, far more than any prior lease sale; see Chapter 2.) Clearly, this was a consequential way to secure revenue without needing to raise taxes.
¶Revenue collection and regulation, separated. Until this time, the Interior Department's Bureau of Land Management and Bureau of Indian Affairs had been responsible for collecting royalties for mining and drilling on federal and Indian lands, respectively—and regulatory oversight of offshore exploration and energy production had been vested in the U.S. Geological Survey's Conservation Division.
¶But the department's management of royalties was subjected to frequent criticism. In July 1981, the administration created a Commission on Fiscal Accountability of the
64¶FIGURE 3.2: Federal Revenues from the Outer Continental Shelf, 1955-2010
$20 $18 $16
Nominal Dollars (Billions) $14 $12 $10 $8 $6 $4 $2 $0
-
¶
- 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 — 2010
Year* • Other Revenues • Lease Bonuses • Royalties Source: Sources: Minerals Commission Revenue Staff, Adapted Management, Total from DOIoffshore mineral revenue collections, Calendar Years 1953-2000, 2001, 7, Federal *Calendar year from 1955–2000; fiscal http://www.onrr.gov/Stats/pdfdocs/coll_off.pdf; year Office of from 2001–2010 Natural Resources Revenue, Total Federal Offshore Reported Royalty Revenues, http://www.onrr.gov/ONRRWebStats/Home.aspx.
Revenues from lease bonuses can occasionally dwarf royalties. A single 2008 lease sale in the Chukchi Sea, Alaska, brought in a record cash bonus of $2.6 billion.
-
¶
- Calendar year from 1955-200; fiscal year from 2001-2010
Nation's Energy Resources, charged with reviewing and recommending changes in the system for collecting royalties. Reporting the next January, the commission concluded that "[m]anagement of royalties for the nation's energy resources has been a failure for more than 20 years. . . . [T]he oil and gas industry is not paying all the royalties it rightly owes. The government's royalty recordkeeping . . . is in disarray."55 It accordingly called for a complete overhaul, including a wholesale reorganization of Interior Department responsibility for overseeing royalty collection from federal and Indian lands.
65Mixing oil and water: revenue-collection and regulation combined. Using the discretion conferred on him in the 1978 Outer Continental Shelf Lands Act Amendments, Secretary Watt moved quickly, issuing Secretarial Order No. 3071 on January 19, creating the Minerals Management Service. Moving beyond the commission recommendations for reform of royalty collection, he provided that the new agency would also absorb offshore leasing and oversight responsibilities from the U.S. Geological Survey. There is no available formal record of his reasoning for this further step, but the most likely reasons are revealed by a memorandum written by the Chief of the Conservation Division, Don Kash, dated December 11, 1981, just a few weeks earlier. In that memo, Kash vigorously argued in favor of relocating responsibilities for lease management from the Conservation Division into a new independent agency within the Interior Department—precisely what the Secretary then did.
¶But Secretary Watt's decision did not fully reflect Kash's concerns. The latter had worried that the controversial politics of lease management were "sullying the [U.S. Geological] Survey's scientific reputation" and threatened its "science ethos" and "scientific virtue." The collision of cultures between those engaged in scientific research and those engaged in lease management was a "continuing source of irritation" and "bitterness" within the U.S. Geological Survey. He was concerned that lease management would increasingly take priority, draining resources from the research that should be the hallmark of the U.S. Geological Survey. Finally, Kash described problems that leasing management would face going forward—foremost among them a tendency toward myopic thinking and inadequately trained personnel. On that last issue, he pointed out that the government could not retain "geologists and geophysicists associated with [outer continental shelf] activities" because they "can move to an industrial or business concern for a substantial increase in pay, almost at will." Kash recommended a series of steps to attract and train personnel capable of overseeing the management of offshore oil and gas activities.56
¶Secretary Watt organized two distinct programs within his newly-minted MMS: the Offshore Energy and Minerals Management program and the Minerals Revenue Management program. (He rejected the General Accounting Office's recommendation, which industry had opposed, that MMS also assume responsibility for onshore oil and gas leasing; the Bureau of Land Management retained that regulatory authority.57) The result was that the same agency became responsible for regulatory oversight of offshore drilling—and for collecting revenue from that drilling.
¶The Billion-Acre Leasing Land Rush It did not take long for Secretary Watt to make sure that his new agency was fully engaged. In July 1982, just after MMS's birth, he issued a new five-year plan that envisioned leasing nearly one billion acres of the outer continental shelf from August 1982 to June 1987—18 times the 55 million acres offered by the first five-year plan of June 1980. To meet this ambitious program, he scheduled 41 sales over the ensuing five years; divided the billion acres into 18 planning areas, ranging in size from 8 million to 133 million acres; and established a streamlined process for leasing in those areas. Under this new process, MMS would no longer lease just those tracts previously designated by industry to be of interest, but would instead offer vast acreage on an "area-wide" basis.58
¶As described in Chapter 2, area-wide leasing promoted significant new discoveries of large oil-bearing formations in contrast to the smaller fields found in shallower depths. Those additional discoveries in fact led to major technological advances and increased exploration of oil and gas reservoirs in Gulf waters. But the federal revenues generated fell short of expectations. With such a large increase in supply, the price offered for leases declined. The Sierra Club claimed that Secretary Watt's plans for accelerated leasing would cost the U.S. Treasury $77 billion over the five-year period.59 Moreover, the Gulf states persuaded Congress to increase their share of leasing revenues as compensation for physical drainage of oil and gas from reservoirs within state jurisdiction by offshore activities of federal lessees. In 1986, Congress amended the federal law to guarantee that the Gulf states would receive 27 percent of the revenues from leases in the federal zone three nautical miles
66¶Watt and Reagan
In January 1982, President Reagan's Interior Secretary, James Watt, created the Minerals Management Service (MMS) in support of his goal to open unprecedented reaches of U.S. territorial waters to oil and gas exploration. MMS had a conflicting and ultimately disastrous mandate: to both regulate offshore energy leases and collect the revenue they generated.
¶Frank Johnston/The Washington Post via Getty Images
beyond state waters.60 Previously the law had provided only that states should receive a "fair and equitable" portion of those revenues, an ambiguous standard that invited disagreement between the federal and state governments concerning what that portion should be.
The Gulf of Mexico's still-more-special status. The distinction first drawn in the 1978 Act between offshore drilling in the Gulf of Mexico and in other parts of the nation was widened further during the 1980s and 1990s. What began as a policy allowing offshore drilling in the Gulf under a more relaxed regulatory regime than applied elsewhere gradually became a policy of allowing offshore drilling, as a practical matter, almost only in the Gulf.
67Court challenges quickly greeted Secretary Watt's efforts to expand offshore leasing throughout the United States. But decisively, Congress, not court rulings, ended the Secretary's plan and effectively singled out the Gulf for offshore drilling. In a series of
¶recurring one-year moratoriums imposed on the Interior Department's annual budgets, the House Appropriations Committee effectively prohibited everything from new leasing activities to exploration and development on existing leases in areas all over the outer continental shelf outside the Gulf of Mexico and a few sub-regions off of Alaska.61 From 1982 to 1993, the area covered by these moratoriums expanded from 0.7 million acres to 266 million.62 The persistent unpopularity of offshore drilling outside the Gulf was underscored by President George H.W. Bush. Despite his background as a former Gulf state (Texan) oil-industry executive, he issued a memorandum in June 1990 that canceled all scheduled sales off of the California, southern Florida,* North Atlantic, Washington, and Oregon coasts and withdrew those areas from leasing until after 2000 (Alaska was not mentioned). At the same time, the President began a process to buy back existing leases in the eastern Gulf of Mexico; he established the proposed Monterey Bay Marine Sanctuary, banning oil and gas leasing there; and he prepared legislation to provide coastal communities directly affected by outer continental shelf development with a greater share of revenues from development and more voice in decisionmaking.63
¶Secretary Watt's promise of offshore drilling throughout the outer continental shelf was never realized. But he succeeded in creating an agency (MMS) and a method of leasing (via area-wide sales) that dramatically expanded the reach of offshore drilling in one place: the Gulf of Mexico. In that one oil- and gas-rich region, that same agency would increasingly struggle to keep up with the pace of industry expansion, while juggling four distinct responsibilities—offshore leasing, revenue collection and auditing, permitting and operational safety, and environmental protection—requiring different skill sets and cultures.
¶Impediments to Safety Regulation
¶The federal government has never lacked the sweeping authority required to control whether, when, and how valuable oil and gas resources located on the outer continental shelf are leased, explored, or developed. As described at the outset, the government's authority is virtually without limitation, traceable to both its authority as proprietor and as sovereign, then further bolstered by the President's inherent authority as Chief Executive and Commander-in-Chief to ensure the security of the nation. The root problem has instead been that political leaders within both the Executive Branch and Congress have failed to ensure that agency regulators have had the resources necessary to exercise that authority, including personnel and technical expertise, and, no less important, the political autonomy needed to overcome the powerful commercial interests that have opposed more stringent safety regulation.
-
¶
- Although Florida's jurisdiction offshore extends to 9 nautical miles, Florida has not joined those other states in favoring significant offshore oil and gas drilling. Florida has instead supported continuing moratoriums on drilling in the outer continental shelf off the Florida coast. Nor has the State sought to promote such drilling within its territorial jurisdiction offshore. Florida's principal reason has been to protect its coast from the potential adverse environmental consequences of drilling activity, including oil spills. See Robert Gramling, Oil on the Edge: Offshore Development, Conflict, Gridlock (Albany, NY: SUNY Press, 1996), 13.
Safety on the Outer Continental Shelf: Increasing Risk, Absence of Necessary Regulatory Reform, and Decreasing Government Oversight Capacity Modern oil and gas drilling rigs and producing platforms are, in effect, enormous floating machines, densely equipped with powerful engines and responsible for keeping within geologic formations large volumes of highly combustible hydrocarbons at high temperatures and pressures. For all their productivity, the rigs expose their crews to the risks of injury or death if not properly operated and maintained—risks compounded for operations conducted in progressively deeper waters, ever farther from shore.
From its creation until the Macondo well blowout, MMS was the federal agency primarily responsible for leasing, safety, environmental compliance, and royalty collection from offshore drilling.* In carrying out its duties, MMS subjected oil and gas activities to an array of prescriptive safety regulations: hundreds of pages of technical requirements for pollution prevention and control, drilling, well-completion operations, oil and gas well- workovers (major well maintenance), production safety systems, platforms and structures, pipelines, well production, and well-control and -production safety training.64 As required by the 1978 Act, MMS also attempted to conduct both annual and periodic unscheduled (unannounced) inspections of all offshore oil and gas operations to try to assess compliance with those requirements. Agency officials have tried to meet the requirement for annual inspections of the operation of safety equipment designed to prevent blowouts, fires, spills, and other major accidents. In both annual and unannounced inspections, MMS officials used a national checklist, covering categories such as pollution, drilling, well completion, production, crane, electrical, and personal safety. Most inspections tend to cover a subset of the elements on the list. Roughly 20 percent of the matters for inspection (those for the production meters) are not related to safety.65
But over time, MMS increasingly fell short in its ability to oversee the offshore oil industry. The agency's resources did not keep pace with industry expansion into deeper waters and industry's related reliance on more demanding technologies. And, senior agency officials' focus on safety gave way to efforts to maximize revenue from leasing and production.
The "Safety Case" and MMS's Inability to Adopt New Practices By the early 1990s, some MMS officials had begun to rethink the agency's approach to safety oversight of the offshore industry. In the wake of an accumulation of accidents in U.S. waters, and several devastating accidents elsewhere around the globe, they had come to appreciate that a command and control, prescriptive approach to regulation did not adequately address the risks generated by the offshore industry's new technologies and exploration, development, and production activities, including industrial expansion into deeper waters.
In March 1980, the Alexander Kielland—built as a drilling rig but under lease to Phillips Petroleum Company to house offshore workers at the Ekofisk Field in the Norwegian North Sea—capsized, killing 123 of the 212 people on board the "flotel." Two years
69
- Other federal agencies, including the United States Coast Guard, Department of Transportation, Occupational Safety and Health Administration, Environmental Protection Agency, and National Oceanic and Atmospheric Administration possess regulatory authority over discrete aspects of oil and gas operations offshore.
¶later, during preparation for an approaching North Atlantic storm, the Ocean Ranger semisubmersible drilling the Hibernia field for Mobil Oil of Canada, sank off the coast of Newfoundland; all 84 crew members were lost in the freezing-cold waters. And in July 1988, the Piper Alpha production platform operated by Occidental Petroleum 120 miles northeast of Aberdeen, Scotland, exploded and sank, killing 167 people, including 2 rescuers.66 Although the causes of the three accidents varied, they all involved international operations of U.S.-based oil and gas companies. Common contributing factors included inadequate safety assurance, worker training, and evacuation procedures. Poor communication and confusion about lines of authority amplified the death toll in at least two of the accidents.
¶The Norwegian government responded to the loss of the Alexander Kielland by transforming its approach to industry operations. Under the new regime, rather than relying solely on prescribed operational and safety standards, the government required the industry to demonstrate thorough consideration of all risks associated with the structures and operations for a drilling or production plan. The regulator no longer "approved" operations. Shifting the burden of demonstrating safety to the operator, the regulator would instead now "consent" to development activity proceeding only upon the operator's demonstration that sufficient safety and risk management systems were in place.
¶The Piper Alpha accident and the subsequent investigation led by Lord Cullen had a similar impact on United Kingdom regulation. As in Norway, the previous prescriptive regulatory approach evolved into one where regulations were supplemented with a requirement for companies to demonstrate to the regulator that they had undertaken a thorough assessment of risks associated with an activity and they had adequate safety and risk management systems to address those risks.
¶All these foreign regulators—the United Kingdom, Norway, and Canada—had previously relied on the kind of prescriptive approach used in the United States, but in the aftermath of these fatal accidents in harsh, remote offshore environments, authorities elsewhere concluded that adding a risk-based approach was essential. They faulted reliance on the "prescriptive regulation with inspection model" for being fundamentally reactive and therefore incapable of driving continuous improvement in policies and practices.67 According to Magne Ognedal, the Director General of the Norwegian Petroleum Safety Authority, the prescription-only model engendered hostility between the parties and put the risk—legal and moral—onto the regulator to accommodate changing technology, geology, and location, rather than onto the operator, where the responsibility rightly belonged.68 Under the new safety-management model, minimum standards for structural and operational integrity (well control, prevention of fires and explosions, and worker safety) remained in place. But the burden now rested on industry to assess the risks associated with offshore activities and demonstrate that each facility had the policies, plans, and systems in place to manage those risks. In the United Kingdom, such risk-management plans were called a "Safety Case."
70On March 19, 1989, while the Piper Alpha accident was still under review, a platform operated by ARCO exploded in the South Pass Block 60 off the Louisiana coast. An uncontrolled release of liquid hydrocarbons ignited, destroying the platform and killing seven people. An MMS investigation concluded that poor management of a repair operation was to blame: not only was there an "absence of detailed and coordinated planning for the project," there was a dearth of much-needed "oversight over contractor activities."69
After South Pass Block 60, the latest in the series of tragic accidents involving U.S- based companies, MMS convened an internal task force to review its offshore drilling inspection and enforcement program by October 1989. That same year, the agency also commissioned the Marine Board of the National Research Council to make recommendations for overhauling MMS's regulatory program to best fulfill its safety mission at current levels of staffing and budget.70 The Marine Board's report, delivered in January 1990,71 concluded that MMS's emphasis on a list of "potential incidents of non-compliance" could lead to an attitude on the part of an operator that compliance with the list equals safety, thereby diminishing "recognition of [the operator's] primary responsibility for safety."72 The report recommended that MMS place its primary emphasis on the detection of potential accident-producing situations—particularly those involving human factors, operational procedures, and modification of equipment and facilities— rather than scattered instances of noncompliance with hardware specifications.
The Marine Board found that MMS needed to upgrade its program to address changes in the operating environment on the outer continental shelf—including its aging platforms, more complex systems and operations, activities in deeper water at greater distances from shore, and changing characteristics of operating companies. Further, the Board urged continuation of frequent and comprehensive inspections of facilities engaged in drilling and workover operations, including the conduct of the operations themselves, because of "(1) the high frequency of events per unit for these facilities as compared to production facilities, and (2) the large population of workers on each facility. . . ." Overall, the Board recommended that MMS cultivate a more proactive inspector corps and develop a greater focus on identifying emerging safety risks.73
71Safety reform run aground. Unfortunately, by the time the Marine Board delivered its report, hardly anyone was listening. Five days after the South Pass Block tragedy in March 1989, the Exxon Valdez ran aground in Prince William Sound, spilling an estimated 11 million gallons of crude oil on the Alaskan shore. The Board's calls for change were thus presented to a government still preoccupied with cleanup duties in Prince William Sound and to a nation attuned to demands for requiring double-hulled tankers. Ironically, Congress enacted the Oil Pollution Act of 1990, but failed to address any of the regulatory deficiencies identified by the Marine Board, while adding to MMS's regulatory responsibilities (the agency was charged, under the Act and a supplementary Presidential Executive Order74 with overseeing offshore pipelines and oil-spill response planning and prevention).75 The agency's already scarce regulatory resources were stretched even thinner.
¶MMS nonetheless tried to take the initiative for regulatory reform. In July 1991, in response to the Marine Board report and MMS's own internal task force report, MMS published a notice requesting comments on alternative strategies to promote safety and environmental protection, specifically a requirement that outer continental shelf lessees and/or operators develop, maintain, and implement "a safety and environmental management program (SEMP), similar to the United Kingdom's Formal Safety Assessment or Norway's Concept Safety Evaluation programs."76 Declaring that lessees and operators already had "full responsibility to plan and prepare for the overall safety and reliability of Outer Continental Shelf operations," MMS asserted that requiring SEMP would help to enhance offshore safety and environmental protection.77 Acknowledging the difference in scale and scope of the activities between the Gulf of Mexico and the North Sea—as the Gulf consists of many more, but smaller facilities78—MMS sought in its request for comments "to determine the degree to which such programs exist and to draw upon that experience in establishing the requirements for a management control program."79
¶Reform indefinitely frozen in time. At the time of the Macondo blowout—almost 20 years after its original proposal—MMS had still not published a rule mandating that all operators have plans to manage safety and environmental risks. The agency's efforts to adopt a more rigorous and effective risk-based safety regulatory regime were repeatedly revisited, refined, delayed, and blocked alternatively by industry or skeptical agency political appointees.80 MMS thus never achieved the reform of its regulatory oversight of drilling safety consonant with practices that most other countries had embraced decades earlier.
¶Industry served as an initial impediment to MMS reform efforts—and has largely remained so. In late 1991, the American Petroleum Institute asked the agency to postpone action in order to allow the institute itself to develop an offshore safety standard.81 MMS agreed, and actively participated in the institute's committee-based process over the next two years. The American Petroleum Institute's "recommended practice" guidance document was published in May 1993—the same month that the UK Safety Case regulations came into force.82 Missing from the first edition of the Institute's guideline, however, was a key element of standard process safety management83—nor did it even cover drilling rigs,84 clearly an integral element in operating offshore.
¶MMS announced in June 1994 that it would continue evaluating the new safety concept for two additional years in order to determine whether it should be mandated85—a deadline it soon extended by yet another year, delaying a final decision until late 1997.86 In the meantime, the agency urged companies to adopt safety and environmental management systems voluntarily, and hinted that wide industry participation might prevent a formal rulemaking.87
¶By this time, there appears to have been a working assumption within both the agency and the industry it was charged with overseeing that technological advances had made equipment remarkably reliable. As one MMS official put it in 1996, conceding that the best the agency could do with available resources was to encourage voluntary compliance with SEMP, "We want to approach our relationship with the offshore industry more as a partner
72than a policeman. We need to create an atmosphere where the primary concern is to fix the problem, not the blame"—an apt characterization for a period of "regulatory reform" in Congress and fiscal restraint nationwide.88
Holy Grail or Poisoned Chalice? The MMS voluntary approach to risk assessment was met with skepticism by regulators in the North Sea. At a May 1996 industry forum in Houston, Texas, an official with the UK Health and Safety Executive (HSE) compared the two safety regimes in a presentation titled US Voluntary SEMP Initiative: Holy Grail or Poisoned Chalice? "Last year, with the safety cases of most UK rigs already accepted well ahead of the deadline, IADC [the International Association of Drilling Contractors] told us they were pleased to be operating a premium fleet in North Sea and that HSE was not to think of relaxing the safety case requirements." By contrast, he described the voluntary SEMP scheme as an unrealistic halfway position, while noting that "both the US and the UK need more time to find out which way provides the best lasting effect."89
Almost a decade later, MMS was no more successful when it tried to resurrect movement toward even a weakened version of a safety and environmental management rule. In May 2006, when MMS finally proposed a rule on "Safety and Environmental Management Systems"—the successor to the long-moribund SEMP initiative—its proposed rule was limited in its reach. The proposal would have required that only 4 of the 12 widely accepted elements of industrial process safety management be put into place. Industry opposition even to this watered-down proposal was swift. And, ultimately, it was only after the Macondo well blowout four years later that the federal agency finalized a more comprehensive, mandatory SEMP rule.
Other MMS regulatory initiatives critical to safety faced strong and effective opposition. In 2003, the White House stiffly opposed MMS's efforts to update its requirements for the reporting of key risk indicators.90 (MMS had proposed that all unintentional gas releases be reported, because even small gas leaks can lead to explosions.91) "It was like pulling teeth," one senior MMS official involved with the process told the Commission: "We never got positive cooperation" from either industry or the Office of Management and Budget.92 The Offshore Operators Committee, an industry association, vehemently objected that the requirement would be too burdensome and not conducive to safety; MMS disagreed, yet the final rule in 2006 mandated that a gas release be reported to MMS only if it resulted in an "equipment or process shut-in," or mechanical closure—a much less complete standard.93
73Safety Regulation on a Starvation Diet During the 1990s, the resources available to MMS decreased precipitously just as it faced a dramatic increase in the offshore activity it was charged with overseeing—and matters only deteriorated thereafter. Perversely, MMS's budget reached its lowest point in November 1996,94 just as major development activities in deepwater were expanding. That December, the Houston Chronicle reported with tragic detail an 81 percent increase in offshore fires, explosions, and blowouts in the Gulf since 1992.95 The oil and gas industry drilled a record number of Gulf wells in 1997—many in deepwater.96 By 1999, oil production from deepwater eclipsed production from shallow water for the first
¶FIGURE 3.3: MMS Budget and Gulf of Mexico Crude Oil Production, 1984-2009
¶600 $300
¶250 $250
¶Real 2005 Doallars (Millions) Barrels of Oil (Millions)200 Interview with Coast Guard official, August 30, 2010; Interview with government official, August 24, 2010. $200
¶150 $150
¶100 $100
¶50 $50
-
¶
- 0 — 1984
¶1994 $0
Year • Ultra-Deep (5,000+ ft) • Deep (1,000–4,999 ft) • Shallow (0–999 ft) OEMM Enacted Budget
¶Sources: "Budget Division: Congressional Budget Justifications," Bureau of Ocean Energy Management, Regulation, and Enforcement, http://www.boemre.gov/adm/budget.html; Minerals Management Service, Deepwater Gulf of Mexico 2009: Interim Report of 2008 Highlights, (May 2009), 71-72, http://www.gomr.boemre.gov/PDFs/2009/2009-016.pdf; U.S. Energy Information Administration, This Week in Petroleum: Production, Proved Reserves and Drilling in the Ultra-Deepwater Gulf of Mexico, (May 26, 2010), http://www.eia.gov/oog/info/twip/ twiparch/100526/twipprint.html.
¶In the last twenty years, MMS's leasing, environmental, and regulatory budget decreased or remained static while deepwater oil production in the Gulf of Mexico boomed. Note: OEMM (Office of Energy and Minerals Management) has responsibility for renewable energy, leasing and environmental, resource evaluation, regulatory, and information management programs. It does not include revenue management or general administration.
¶time.97 Oil production in the Gulf grew from 275 million barrels in 1990 (when only 4.4 percent of that volume came from deepwater wells) to 567 million barrels in 2009 (when deepwater wells yielded more than 80 percent of the total).98
¶Changing technology and changing industry structure outpacing regulations. As MMS's resources lagged behind the industry's expansion into deepwater drilling—with its larger-scale and more demanding technology, greater pressures, and increasing distance from shore-based infrastructure and environmental and safety resources—the agency's ability to do its job was seriously compromised.99 Of particular concern, MMS was unable to maintain up-to-date technical drilling-safety requirements to keep up with industry's rapidly evolving deepwater technology. As drilling technology evolved, many aspects of drilling lacked corresponding safety regulations. The regulations increasingly lagged behind industry and what was happening in the field.
¶When industry contended that blowout-preventer stacks—the critical last line of defense in maintaining control over a well—were more reliable than the regulations recognized, warranting less frequent pressure testing, MMS conceded and halved the mandated
74Drill Pipe frequency of tests.100* Soon afterward, a series of third-party technical studies raised the possibility of high failure rates for the blowout preventers' control systems, annular rams, and blind-shear rams under certain deepwater conditions and due to changes in the configuration and strength of drill pipe used by industry.101 Two studies commissioned by MMS found that many rig operators, by not testing blowout preventers, were basing their representations that the tool would work "on information not necessarily consistent with the equipment in use."102 Yet, MMS never revised its blowout-preventer regulations nor added verification as an independent inspection item in light of this new information.103
Nor did MMS adapt its regulatory framework in response to significant ways in which the Waiting their turn, lengths of colored drill pipe stack up oil and gas industry has changed over time. aboard a Transocean rig. Independent studies suggest that In particular, the industry has witnessed a failures of crucial blowout preventer components could be caused in part by industry-driven changes to drill-pipe rise in specialized service contractors, such strength and configuration. as Halliburton and Transocean that serviced Derick E. Hingle/Bloomberg via Getty Images BP at the Macondo well. When the lessee directly regulated by the government is itself not performing many of the activities critical to well safety, that separation of functions poses heightened challenges for the regulator. But there was no apparent effort by MMS to respond to those challenges by making the service companies more accountable.
Permit "shopping." With increasing industry activity, MMS regulators could not possibly keep pace. The oil and gas industry works 24/7, but MMS regulators generally work regular office hours, requiring "on-call" responsibility to be assigned to individual senior engineers. Those engineers, however, work at a marked disadvantage because they cannot gain access to the permit database from off-site locations due to security concerns.104 Even during normal business hours, the Gulf of Mexico office lacks a sufficient number of engineers to process permit reviews with necessary scrutiny. From 2005 to 2009, the number of applications for drilling permits in just the MMS New Orleans District increased 71 percent: from 1,246 to 2,136.105 Without enough engineers in the Gulf of Mexico district office to process all the applications, some operators literally "shop around." They "contact district offices outside the appropriate jurisdictional area . . . to find an engineer who will eventually give approval."106
Inspections forgone. Not surprisingly, with diminished resources, MMS inspections became less effective, as the Interior Department's Inspector General reported in 1999.107
75
- "The MMS said the revised testing requirements could save industry $35-46 million per year without compromising safety." See "MMS eases rule for BOP testing," Oil & Gas Journal, June 8, 1998, 32.
¶FIGURE 3.4: MMS Inspections in the Gulf of Mexico, 1990-2009
Number of MMS Inspections in the Gulf of Mexico, 1990-2009 8,000
¶7,000
¶6,000
¶Number of Inspections
¶5,000
¶4,000
¶3,000
¶2,000
¶1,000
-
¶
-
1992 1993 1994 — 1995
-
1998 1999 — 2000
-
2001 — 2003
-
1991 1997 2002 — 2004
-
2008 — 2009
Year • Announced • Unannounced Source: Bureau of Ocean Energy Management, Regulation, and Enforcement data upon National Commission Staff
¶Source: Bureau ofrequest
Ocean to the Department Energy of the Interior Management, Regulation, and Enforcement data upon National Commission Staff request to the
¶Department of the Interior.
¶"Unannounced" or surprise inspections of offshore oil and gas activity grew increasingly rare over time. Less than 3% of MMS inspections conducted in 2009 were unannounced.
¶The frequency of unannounced inspections plummeted.108 Although the raw incident data are online, MMS last produced an analysis of offshore incidents—critical data for promoting the safety of offshore operations—for calendar year 2000.109 And MMS's progressive reduction in oversight relative to the level of industry activity occurred just as the industry struggled to find highly trained staff needed to work the expanding population of deepwater drilling rigs.110 Precisely when the need for regulatory oversight intensified, the government's capacity for oversight diminished.
¶Overlaps and "underlaps." The lack of resources extended beyond MMS. The United States Coast Guard is responsible for regulating the "safety of life and property on Outer Continental Shelf (OCS) facilities, vessels, and other units engaged in OCS activities."111 Because most drilling rigs and even some production platforms fall under the definition of "vessels," part of the responsibility for regulating their safe operation (and full authority for certifying their seaworthiness) is within the jurisdiction of the Coast Guard.112 But just when the need for Coast Guard oversight increased during the 1990s—as industry drilled in deeper waters farther offshore and used more ambitious floating drilling and production systems—it, too, faced more severe budgetary restraints. Accordingly, the Coast Guard failed to update its marine-safety rules—the last major revision was in 1982113—to reflect the industry's new technology. The resource plight worsened further following the terrorist attacks of September 11, 2001, given the nation's overriding need to focus on border and port security. The Coast Guard's "solution"—to transfer much of
76its responsibility for fixed platform safety to MMS in 2002114—eerily echoed earlier cycles of expanding MMS's mandate in the face of inadequate resources, stretching its capabilities thinner still. The practical effect of the Coast Guard and MMS's shared responsibility for offshore safety has been the presence of "overlaps" in jurisdiction that have required the renegotiation of informal interagency agreements ever since 1989—the continuance of which has left MMS with "underlaps" in resources.115
The Culture of Revenue Maximization When Interior Secretary Watt moved regulatory oversight of offshore energy exploration and production to a new entity that was also responsible for collecting revenue from the activity it regulated, he created a new agency that inexorably came to be dominated by its focus on maximizing that revenue.
For at least the past 15 years, every former MMS Director has freely acknowledged that the royalty issues have taken most of the Director's time—at the expense of offshore regulatory oversight.116 In 1995, as the United States faced global competition for oil exploration and development capital during a period of low prices, Congress enacted the Deep Water Royalty Relief Act.117 It provided a suspension of royalty payments on a portion of new production from deepwater operations.
But when prices and volumes increased, the sheer amount of money at stake—literally billions of dollars (MMS total onshore and offshore revenues for 2008 were $23 billion118)—compelled even greater attention, as the White House, members of Congress, and certainly the states each advanced competing notions of how those sums might best be spent.* Litigation, new regulations, and legislation designed to increase one party's relative share of such massive sums have been a constant feature of managing the flow of royalties from onshore and offshore energy production. Such disputes have invariably been controversial, politically sensitive, and time-consuming for MMS decisionmakers.119
Agency leadership and technical expertise. Agency personnel naturally look to agency leadership to signal what constitutes their primary mission, including the expertise and experience that such leaders bring with them. In the case of MMS, those signals were profoundly disturbing, yet nonetheless consistent over time. No one who has led MMS since it was created almost 30 years ago has possessed significant training or experience in petroleum engineering or petroleum geology, or any significant technical expertise related to drilling safety.
In the absence of a clear statement from the top about the necessity for such expertise to ensure drilling safety, it should be no surprise that MMS personnel have suffered from the loss of essential expertise throughout their ranks. Indeed, the lack of requisite training is abysmal. According to a recent survey conducted at the request of the Secretary of the Interior, "[a]lmost half of the [MMS] inspectors surveyed do not believe they have received sufficient training." MMS, unlike Interior's Bureau of Land Management (which
77
- Because of a bureaucratic mistake within Interior, however, federal lease sales held in 1998 and 1999 failed to include price thresholds in each lease, meaning that those lessees received relief from royalty payments even though higher oil prices made such relief wholly unnecessary. The Government Accountability Office has estimated that the error could cost the government at least $10 billion and perhaps as much as $80 billion. Government Accountability Office, "Oil and Gas Royalties – Royalty Relief Will Likely Cost the Government Billions, but the Final Costs Have Yet to Be Determined" (January 18, 2007), 3, 5.
¶inspects onshore oil and gas drilling operations), has no "oil and gas inspection certification program" and no exam "is required of each inspector in order to be certified." MMS "does not provide formal training specific to the inspections process, and does not keep up with changing technology. Some inspectors noted that they rely on industry representatives to explain the technology at a facility."120
¶The Macondo well blowout makes all too clear the cost of such a departure from the standards of excellence that the nation expects from its public servants. As described in Chapter 4, the MMS personnel responsible for reviewing the permit applications submitted to MMS for the Macondo well were neither required nor prepared to evaluate the aspects of that drilling operation that were in fact critical to ensuring well safety. The regulations did not mandate that MMS regulators inquire into the specifics of "rupture disks," "long string" well designs, cementing process, the use of centralizers, lockdown sleeves, or the temporary abandonment procedures (see Chapter 4). And, no doubt for that same reason, the MMS personnel responsible for deciding whether the necessary drilling permits were granted lacked the expertise that would have been necessary in any event to determine the relative safety of the well based on any of these factors.*
¶Agency integrity and pockets of corruption. The preoccupation with revenues did not merely divert MMS leaders' attention from drilling safety. It also allowed the ethical culture to degenerate in a few isolated offices, leading to serious charges of abuse of government authority and even charges of criminal misconduct by a few individuals. This conduct was far removed from the daily work of almost all those agency personnel who performed regulatory oversight of offshore drilling. But the conduct of a few working elsewhere in the agency unfairly cast a cloud over the agency as a whole, especially in the immediate aftermath of the Macondo well blowout, providing a ready reminder of the critical importance of public trust in the management of the nation's resources.
¶The most notorious example arose from the "royalty in kind" program, based in Denver, Colorado. Under the program, MMS exercised its option to accept royalty payments "in kind" rather than in cash.† A September 2008 Inspector General's report implicated more than a dozen employees in the Denver royalty-in-kind office in unethical and criminal conduct.121 Those MMS staff had also socialized with, and received a wide array of gifts from, companies with whom they were conducting business. The Inspector General further acknowledged that although "99.9 percent of [Interior] employees are hardworking, ethical, and well-intentioned[,] . . . the conduct of a few has cast a shadow on an entire bureau."122
¶Nor was unethical conduct limited to MMS's revenue collections. It extended to some of those who worked on overseeing offshore oil and gas activities in the Gulf of Mexico. An Inspector General's investigation in 2010 revealed that prior to 2007, "a culture of
-
¶
- See, e.g., Written submission to the National Commission from MMS permitting official, November 5, 2010 ("I did not know they were using nitrogen foamed cement. . . . [I]t would not have mattered under the regulations. We do not do any evaluations of types of cement.") id. ("I do not recall them informing me as to why they decided not to drill to that length. . . . We do not need an explanation as to why a well is not drilled to the proposed depth.").; id. ("At the time I reviewed the APD [drilling permit application], my knowledge of rupture disks was limited to what I had learned from the previous drilling engineer when working with him learning the review process."); id. ("I did not receive training on lock down sleeve setting procedures.").
¶The royalty-in-kind program allowed MMS to market the natural gas or oil to establish a reference against which it could evaluate industry reports of their market value.
78accepting gifts from oil and gas companies was prevalent throughout the MMS Lake Charles[, Louisiana] office." "[A] number of MMS employees at th[at] district office admitted to attending sporting events prior to 2007 in which oil and gas production companies sponsored teams, as well as receiving lunches and accepting gifts." The investigation found that one employee had conducted inspections on a company's oil platforms while in the process of negotiating (and later accepting employment) with the company.123 Here again, the actions of a few damaged the reputation of the agency as a whole, and demoralized the vast majority of MMS employees who avoided such conflicts.124 In January 2009, only days after taking office, Secretary Salazar met with MMS employees and announced an ethics reform initiative in response to the problems identified at MMS and elsewhere in the agency.125
Mismanagement and Misdirection Perhaps because of the cumulative lack of adequate resources, absence of a sustained agency mission, or sheer erosion of professional culture within some offices, MMS came progressively to suffer from serious deficiencies of organization and management: the fundamental traits of any effective institution. According to the Outer Continental Shelf Safety Oversight Board,* MMS lacks "a formal, bureau-wide compilation of rules, regulations, policies, or practices pertinent to inspections, nor does it have a comprehensive handbook addressing inspector roles and responsibilities." As a result, the Board concluded, "policies and enforcement mechanisms vary among the [Gulf of Mexico] districts and the regions, and there is no formal process to promote standardization, consistency, and operational efficiency."126
The Safety Oversight Board singled out MMS's handling of inspections for pointed criticism. For example, management promoted inspections by single inspectors in order to increase the total number of inspections, even though "most inspectors interviewed said that two-person teams would increase efficiencies, eliminate reliance on an operator representative for observations on safety tests, improve the thoroughness of the inspection, and reduce the ability of operators to successfully pressure an inspector not to issue [a citation]." The Board's interviews revealed "staff concerns regarding a perceived emphasis on the quantity rather than quality of inspection."127
The agency's management shortcomings were underscored, and compounded, by lack of communication and inconsistencies among its three regional offices for the Gulf of Mexico, the Pacific, and Alaska. The directors of each regional office naturally adapted practices to best suit the specific characteristics and needs of the region. But by acting in parallel fashion, with little coordination in decisionmaking and resource allocation, program implementation, regulatory interpretation, and enforcement policies became inconsistent, undermining the integrity of MMS's work.128 For example, the Safety Oversight Board found that "the Pacific Region employs 5 inspectors to inspect 23 production facilities—a ratio of 1 inspector for every 5 facilities. By contrast, the [Gulf of Mexico Region] employs 55 inspectors to inspect about 3,000 facilities—a ratio of 1 inspector for every 54 facilities."129 Testimony of Daun Winslow, August 23, 2010, 450; BP, Deepwater Horizon Accident Investigation Report, 123. Internal BP document (BP-HZN-MBI 128489); BP, Deepwater Horizon Accident Investigation Report, 64 ("the BP Macondo well team did not ask for the OptiCem model to be re-run"). This may have been because of Mr. Guide's distrust of the OptiCem model. Testimony of John Guide, 275 ("it's wrong a lot"). When Halliburton rig personnel eventually informed Gagliano of BP's decision themselves, he responded by e-mailing BP modeling data suggesting again that more centralizers would be needed to prevent channeling. Internal BP document (BP-HZN-MBI 128708). Ibid.
79
- Secretary Salazar created the Outer Continental Shelf Safety Oversight Board in the immediate aftermath of the Macondo well blowout and charged the Board with reviewing the effectiveness of MMS's management. The Board issued its report on September 1, 2010.
¶Ultimately, MMS was unable to ensure that its staffing capabilities and competencies kept pace with the changing risks and volume of offshore activity. As the Safety Oversight Board concluded, the Gulf of Mexico "district offices did not have a sufficient number of engineers to efficiently and effectively conduct permit reviews."130 As the Chief of the U.S. Geological Survey's Conservation Division had warned nearly 30 years earlier,131 salaries— for engineers stuck in the midranges of the federal pay scale—were far too low to attract individuals possessing the experience and expertise needed to oversee the increasingly complicated oil and gas drilling activities in the deepwater Gulf.132 At the most elementary level, MMS frequently lacked defined qualifications that new employees must meet before they start performing their jobs, or clear procedures for on-the-job training. The Board report further observed that the "amount of time and the structure of this training vary from office to office and from inspector to inspector," and it concluded that the on-the-job training "does not address the need for substantive, consistent training in all aspects of the job."133
¶An Environment Unfavorable to Responsible Drilling
¶Erosion of Environmental-Protection Safeguards in the Gulf of Mexico Even as oversight of drilling safety became less effective while the industry pursued more demanding deepwater plays in the Gulf of Mexico, environmental safeguards eroded, too—putting the rich natural resources of the Gulf waters and the surrounding coasts at increasing risk.
¶The legislative promise. The 1978 Outer Continental Shelf Lands Act Amendments promised full consideration of concerns for environmental protection. The Act provides that "[m]anagement of the outer Continental Shelf shall be conducted in a manner which considers economic, social, and environmental values of the renewable and nonrenewable resources contained in the outer Continental Shelf, and the potential impact of oil and gas exploration on other resource values of the outer Continental Shelf and the marine, coastal, and human environments."134 It further requires that the timing and location of exploration, development, and production of oil and gas take environmental factors into consideration, including: existing ecological characteristics; an equitable sharing of development benefits and environmental risks among the regions; the relative environmental sensitivity and marine productivity of areas; and relevant environmental and predictive information.135 Based on an evaluation of these and other factors, the Act directsthe Secretary of the Interior to select the "timing and location of leasing, to the maximum extent practicable, so as to obtain a proper balance between the potential for environmental damage, the potential for the discovery of oil and gas, and the potential for adverse impact on the coastal zone."136
¶A host of other laws, many enacted by Congress during the 1970s surge of environmental legislation, buttress these promised priorities. Of particular relevance to oil and gas leasing on the outer continental shelf is the National Environmental Policy Act requirement that federal agencies prepare environmental impact statements for all major federal actions
80significantly affecting the human environment.137 Those detailed statements must include not only discussion of the immediate adverse impacts on the natural environment that might result from the federal action, but also the "socio-economic"* effects of those impacts.138 The Magnuson-Stevens Fishery Conservation and Management Act requires agencies to analyze the potentially adverse impacts of oil and gas activities on fish habitat and populations, and provide conservation measures to mitigate those impacts.139 The Endangered Species Act requires federal agencies to determine the potential adverse impact of oil and gas activities on endangered and threatened species, limits activities that harm individual members of such species, and bars altogether activities that place such species in jeopardy.140 The Marine Mammal Protection Act imposes limits on activities that injure or even harass marine mammals.141 The National Marine Sanctuaries Act requires consultations to guard against harm to marine sanctuary resources from oil and gas leasing activities.142 The federal Clean Water Act imposes permitting requirements on any discharge of pollutants into navigable waters from such activities.143 And, the Oil Pollution Act of 1990,144 supplemented by a Presidential Executive Order,145 imposes a panoply of oil-spill planning, preparedness, and response requirements on fixed and floating facilities engaged in oil and gas exploration, development, and production on the outer continental shelf.
Promise vs. practice. But some of these apparent statutory promises dim upon closer examination. The Outer Continental Shelf Lands Act routinely requires consideration of environmental protection concerns in leasing location and timing—but ultimately gives the Secretary of the Interior tremendous discretion in deciding what weight to give those concerns.146 The balance ultimately struck depends largely on the politics of the moment. The Secretary can assign significant weight to environmental protection concerns—or not.
And in fact, parts of the 1978 Act arguably stack the deck against full consideration of environmental concerns. For instance, the law provides that the Secretary must approve a lessee's exploration plan within 30 days of submission.147 If environmental review is to occur after plan submission, that timetable effectively precludes the kind of exacting review necessary to ensure that the Act's environmental safeguards can be achieved. It would, in effect, be a statement by Congress that the rush to energy exploration is too important to be delayed.
The Act also expressly singles out the Gulf of Mexico for less rigorous environmental oversight under NEPA. As a result of political compromise with oil and gas interests, the Act exempts lessees from submitting development and production plans (which include environmental safeguards) for agency approval. Accordingly, Gulf leases, unlike those applicable to other offshore areas, are not subject to the requirement of at least one NEPA environmental impact statement for development plans for a particular geographic area.148
None of the other statutes includes such a stark exception, but their effects still are more limited than it might at first seem. For instance, both the Endangered Species Act and the
81
- As the Macondo well blowout makes clear, the socio-economic effects of an oil spill are hardly an incidental concern. As described in Chapter 6, the economic costs of the spill to the Gulf states can be measured in the billions of dollars. Yet absent careful NEPA review, there are no assurances that these potential consequences of a decision to lease, explore, develop, or drill in any given location will be carefully considered by the governmental decisionmaker before the decision is made.
¶Clean Water Act impose tough substantive limits on activities. But each has only a narrow, discrete focus and statutory trigger: threats to endangered or threatened species or their critical habitat under the Endangered Species Act or, under the Clean Water Act, only the incidental aspects of oil and gas activities that discharge pollutants into navigable waters (unless, of course there is an oil spill).
¶Neither the Magnuson-Stevens Act nor the Marine Sanctuaries law imposes any mandatory substantive limitation on oil and gas activities offshore. Each instead authorizes the National Oceanic and Atmospheric Administration (NOAA) to make recommendations to MMS about possible adverse environmental impacts (to fish habitat and marine sanctuaries) and appropriate conservation measures. Congress clearly assigned NOAA this central role because it is the federal agency most expert on ocean science and has a clear mission to serve as the steward safeguarding the nation's ocean resources. But, notwithstanding that assignment, neither law provides any corresponding obligation on the part of MMS to heed NOAA's advice. MMS can, and has, on occasion given little or no weight to NOAA's views; according to NOAA officials, that causes some NOAA scientists to expend fewer resources on generating such views.
¶As a result, although the various laws create the potential for comprehensive environmental protection in oil and gas drilling on the outer continental shelf, neither alone nor in combination do any of the laws come close to ensuring a reasonable level of overall environmental protection applicable to all aspects of oil and gas activities on the outer continental shelf. Whether they have achieved their statutory objectives has therefore historically depended instead entirely on the discretionary determinations of MMS officials.
¶Limiting NEPA. The Department of the Interior and MMS also took a series of steps that further limited the potential for NEPA to ensure government decisions were based on full consideration of their environmental consequences. Erosion of NEPA's application to offshore oil and gas activities began, as noted, when Congress exempted a category of leasing activities in the Gulf of Mexico from NEPA review. The Interior Department, however, subsequently took that legislative exemption and unilaterally expanded its scope beyond those original legislative terms.
¶Although the 1978 Act exempted only the Interior Department's review of a lessee's "development and production plan" from the environmental impact statement process, Interior unilaterally extended that exemption. In January 1981, the Department promulgated final rules declaring that exploration plans in the central and western Gulf of Mexico were "categorically excluded" from NEPA review.* At that same time, the Department also categorically excluded from NEPA review applications to drill wells (for exploration or subsequent development and production of oil and gas) "when said well and appropriate mitigation measures are described in an approved exploration plan, development plan, or production plan."149 In 1986, MMS scaled back the categorical
¶The President's Council on Environmental Quality, which is responsible for the administration of NEPA, has promulgated a regulation that permits agencies to create "categorical exclusions" from NEPA review for categories of minor activities that can be reasonably assumed in advance not to have significant environmental impacts. See 40 C.F.R. § 1508.4.
82exclusion to account for the possibility that NEPA review would be needed for these activities in certain narrowly defined "extraordinary circumstances." Extraordinary circumstances include those actions that have highly uncertain and potentially significant environmental effects or involve unique or unknown environmental risks.150
But because MMS personnel were apparently reluctant to conclude that such extraordinary circumstances were present, the rule in practice in the Gulf of Mexico was the categorical exclusion—rather than the exception to that exclusion. MMS staff have reported that leasing coordinators and managers discouraged them from reaching conclusions about potential environmental impacts that would increase the burden on lessees, "thus causing unnecessary delays for operators." The Safety Oversight Board also noted that "[s]ome [MMS] environmental staff also reported that environmental assessments for smaller operators may be minimized if the [Regional Office of Field Operations] manager determines that implementing the recommendation may be too costly."151
With regard to NEPA specifically, some MMS managers reportedly "changed or minimized the [MMS] scientists' potential environmental impact findings in [NEPA] documents to expedite plan approvals." According to several MMS environmental scientists, "their managers believed the result of NEPA evaluations should always be a 'green light' to proceed." In some cases, there may also have been built-in employee financial incentives that "distort[ed] balanced decision-making" to the extent that "[e]mployee performance plans and monetary awards [were] . . . based on meeting deadlines for leasing or development approvals."152
Finally, just as a matter of sheer practicality, MMS personnel plainly lacked the substantial resources that would have been required to engage in meaningful NEPA review in light of the extraordinary expansion of leasing activity in the Gulf. There were literally hundreds of exploration, development, and production plans, as well as individual permit drilling applications to be processed. No President ever sought for MMS the level of resources that would have been required to prepare individual assessments concerning whether each of those activities required an environmental impact statement, let alone such a statement for those that did. Nor did Congress. It should be no surprise under such circumstances that a culture of complacency with regard to NEPA developed within MMS, notwithstanding the best intentions of many MMS environmental scientists.
The Macondo Well The gap between the protections promised by environmental statutes and regulations and actual practice is fully illustrated in the review and permitting of the Macondo well itself. MMS engaged in no NEPA review of the well's permitting, and neither MMS nor other federal agencies gave significant attention to the environmental mandates of other federal laws.
83NEPA. MMS performed no meaningful NEPA review of the potentially significant adverse environmental consequences associated with its permitting for drilling of BP's exploratory Macondo well. MMS categorically excluded from environmental impact review BP's initial and revised exploration plans—even though the exploration plan could have qualified for
¶an "extraordinary circumstances" exception to such exclusion, in light of the abundant deep-sea life in that geographic area and the biological and geological complexity of that same area.153 MMS similarly categorically excluded from any NEPA review the multiple applications for drilling permits and modification of drilling permits associated with the Macondo well. The justification for these exclusions was that MMS had already conducted NEPA reviews for both the Five-Year Program and the Lease Sale that applied to the Macondo well. The flaw in that agency logic is that both those prior NEPA reviews were conducted on a broad programmatic basis, covering huge expanses of leased areas of which the Macondo well was a relatively incidental part. Neither, moreover, included a "worst case analysis" because the President's Council on Environmental Quality had eliminated the requirement for such analysis under NEPA for all federal agencies in 1986.154 As a result, none of those prior programmatic reviews carefully considered site-specific factors relevant to the risks presented by the drilling of the Macondo well.*
¶Fishery conservation and management. Under the Magnuson-Stevens Fishery Conservation and Management Act, federal agencies must consult with NOAA on all activities (or proposed activities) authorized, funded, or undertaken by the agency that may adversely affect essential fish habitat. For the Gulf of Mexico, accordingly, NOAA prepared a "programmatic" Essential Fish Habitat Consultation for the entire Gulf.155 To similar effect, MMS complied with the Magnuson-Stevens consultation requirement by preparing Essential Fish Habitat Assessments that looked at offshore oil and gas leasing activities in the Gulf broadly.156 Neither NOAA nor MMS considered the possible adverse impacts of any one well, such as the Macondo well, in isolation. Nor would it have been practical for them to do so in light of their understandable focus on possible cumulative impacts on fish populations from many offshore leasing activities. What is more telling, however, is that to the extent that the MMS Assessment identified potential threats to essential fish habitat and marine fishery resources from oil spills, both NOAA and MMS ultimately relied exclusively on conservation measures included in oil-spill response plans prepared by the oil and gas industry pursuant to the Oil Pollution Act of 1990 to address those threats.157 For the Macondo well, both agencies assumed that BP's plan would adequately address those threats and therefore there was no need to seek to do so directly through the Magnuson-Stevens Act. There was, however, little reason to assume that those plans were in fact up to the task.
¶Oil Pollution Act of 1990 and Oil Spill Response Plans. Under the Oil Pollution Act of 1990, as supplemented by a Presidential Executive Order, MMS is responsible for oilspill planning and preparedness as well as select response activities for fixed and floating facilities engaged in exploration, development, and production of liquid hydrocarbons and for certain oil pipelines. The agency requires all owners or operators of offshore oil-handling, storage, or transportation facilities to prepare Oil Spill Response Plans. MMS regulations detail the elements of the response plan (an emergency-response action plan, oil-spill response equipment inventory, oil-spill response contractual agreements, a
-
¶
- For instance, bluefin tuna are both commercially vital and biologically significant as predators in the Gulf. But in the relevant Five-Year (2007–2012) Programmatic Environmental Impact Statement on the entire offshore leasing program—covering the entire outer continental shelf of the United States—MMS discusses potential impacts of leasing activities on bluefin tuna in one sentence. Subsequent MMS environmental impact statements for lease sales within the Gulf of Mexico contained no significant or geographically-focused analysis of the potential impacts on bluefin tuna. And, in finally permitting the drilling of the Macondo well, MMS categorically excluded the action from any NEPA review, and thus conducted no analysis of the potential impacts of drilling on bluefin tuna, based on the rationale that it had already adequately reviewed environmental impacts in its prior reviews.
calculation of the worst-case discharge scenario, plan for dispersant use, in-situ burning plan, and information regarding oil-spill response training and drills).158 The emergency-response plan is supposed to be the core of the overall plan, and in turn is required to include information regarding the spill-response team; the types and characteristics of oil at the facilities; procedures for early detection of a spill; and procedures to be followed in the case of a spill.159
But neither BP, in crafting its Oil Spill Response Plan for the Gulf of Mexico applicable to the Macondo well, nor MMS in approving it, evidenced serious attention to detail.160 For instance, the BP plan identified three different worst-case scenarios that ranged from 28,033 to 250,000 barrels of oil discharge and used identical language to "analyze" the shoreline impacts under each scenario.161 To the same effect, half of the "Resource Identification" appendix (five pages) to the BP Oil Spill Response Plan was copied from material on NOAA websites, without any discernible effort to determine the applicability of that information to the Gulf of Mexico. As a result, the BP Oil Spill Response Plan described biological resources nonexistent in the Gulf—including sea lions, sea otters, and walruses.*
Even more troubling, the MMS Gulf of Mexico Regional Office approved the BP plan without additional analysis. There is little in that approval to suggest that BP and MMS gave close scrutiny to the contents of the Oil Spill Response Plan. The Regional Office's routine practice was to review and approve oil-spill response plans within 30 days of their receipt. Absent any legal requirement to do so, the office did not distribute submitted plans to other federal agencies for review or comment, nor did it seek public review or comment.
The inescapable conclusion is striking, and profoundly unsettling. Notwithstanding statutory promises of layers of required environmental scrutiny—by NEPA, the Magnuson-Stevens Act, the Outer Continental Shelf Lands Act, and the Oil Pollution Act—and the potential application of some of the nation's toughest environmental restrictions—the Endangered Species Act and Clean Water Act—none of these laws resulted in site-specific review of the drilling operations of the Macondo well. The agency in charge, MMS, lacked the resources and committed agency culture to do so, and none of the other federal agencies with relevant environmental expertise had adequate resources or sufficient statutory authority to make sure the resulting gap in attention to environmental protection concerns was filled.†
Federal oversight of oil and gas activities in the Gulf of Mexico—almost the only area where substantial amounts of drilling were taking place—took a generally minimalist approach in the years leading up to the Macondo explosion. The national government failed to exercise the full scope of its power, grounded both in its role as owner of the natural resources to be developed and in its role as sovereign and responsible for ensuring the safety of drilling operations. Many aspects of national environmental law
85
- The BP plan does not appear to be an aberration. It was prepared by a contractor who also prepared the Gulf of Mexico plans for Chevron, ConocoPhillips, ExxonMobil, Shell, and other companies operating in the Gulf. The result is four nearly identical plans that repeat the same mistakes found in the BP plan applicable to the Macondo well. † The President's decision in March 2010 to expand offshore oil and gas leasing is a more recent example of the absence of full consideration of environmental protection concerns. According to their testimony before the Commission in August 2010, the White House did not ask either the Chair of the President's Council on Environmental Quality or the Administrator of NOAA to be directly involved in reviewing the plans before the President's decision. See Testimony of The Honorable Nancy Sutley, Chair, Council on Environmental Quality, and The Honorable Jane Lubchenco, Administrator, NOAA, Hearing before the National Commission, August 25, 2010.
¶were ignored, resulting in less oversight than would have applied in other areas of the country. In addition, MMS lacked the resources and technical expertise, beginning with its leadership, to require rigorous standards of safety in the risky deepwater and had fallen behind other countries in its ability to move beyond a prescription and inspection system to one that would be based on more sophisticated risk analysis.
¶In short, the safety risks had dramatically increased with the shift to the Gulf 's deepwaters, but Presidents, members of Congress, and agency leadership had become preoccupied for decades with the enormous revenues generated by such drilling rather than focused on ensuring its safety. With the benefit of hindsight, the only question had become not whether an accident would happen, but when. On April 20, 2010, that question was answered.
-
¶
- 87 — 87
¶Part II
¶Explosion and Aftermath: The Causes and Consequences of the Disaster
¶The loss of control of the Macondo well; the resulting explosion, fire, and destruction of the Deepwater Horizon rig; and the ensuing spill of nearly 5 million barrels of oil before the well was capped on July 15 reflect specific decisions about well design, construction, monitoring, and testing. The Commission's detailed analysis (Chapter 4) explains those actions in the context of this specific reservoir and subsurface geology as well as the regulatory framework and practices that affected those business decisions. Once the rig was destroyed and the uncontrolled flow of oil began leaking into the Gulf, industry and government struggled to contain and respond to the spill—prompting important questions about public and private authority, technical capability and capacity, and the current state of the art in addressing such crises. Understanding of the Gulf ecosystem and the regional economy underlies an early assessment of the spill's impacts and how to restore damaged natural resources, respond to economic losses, and address adverse impacts on human health. Chapters 4, 5, 6, and 7 address the related issues of containment and response, impact assessment, recovery, and restoration.
89¶Chapter Four "But, who cares, it's done, end of story, [we] will probably be fine and we'll get a good cement job." The Macondo Well and the Blowout In March 2008, BP paid a little over $34 million to the Minerals Management Service for an exclusive lease to drill in Mississippi Canyon Block 252, a nine-square-mile plot in the Gulf of Mexico. Although the Mississippi Canyon area has many productive oil fields, BP knew relatively little about the geology of Block 252: Macondo would be its first well on the new lease. BP planned to drill the well to 20,200 feet, both to learn more about the geology of the area and because it thought—based on available geological data—that it might find an oil and gas reservoir that would warrant installing production equipment at the well.1 At the time, BP would have had good reason to expect that the well would be capable of generating a large profit.
¶Little more than two years later, however, BP found itself paying out tens of billions of dollars to
¶Fighting a losing battle, fireboats pour water onto the doomed rig in the hours after the Macondo well blowout. The tragic loss of the Deepwater Horizon at the close of the complex drilling project resulted from a series of missteps and oversights and an overall failure of management.
¶< U.S. Coast Guard photo
90contain a blowout at the Macondo well, mitigate the damage resulting from the millions of gallons of oil flowing from that well into the Gulf of Mexico, and compensate the hundreds of thousands of individuals and businesses harmed by the spill. And that is likely just the beginning. BP, its partners (Anadarko and MOEX), and its key contractors (particularly Halliburton and Transocean) face potential liability for the billions more necessary to restore natural resources harmed by the spill.
The well blew out because a number of separate risk factors, oversights, and outright mistakes combined to overwhelm the safeguards meant to prevent just such an event from happening. But most of the mistakes and oversights at Macondo can be traced back to a single overarching failure—a failure of management. Better management by BP, Halliburton, and Transocean would almost certainly have prevented the blowout by improving the ability of individuals involved to identify the risks they faced, and to properly evaluate, communicate, and address them. A blowout in deepwater was not a statistical inevitability.
¶The Challenges of Deepwater Drilling at the Macondo Well
High Pressures and Risk of a Well Blowout Oil forms deep beneath the Earth's surface when organic materials deposited in ancient sediments slowly transform in response to intense heat and pressure. Over the course of millions of years, these materials "cook" into liquid and gaseous hydrocarbons. The transformed materials can flow through porous mineral layers, and tend to migrate upward because they are lighter than other fluids in the pore spaces. If there is a path that leads to the surface, the hydrocarbons will emerge above ground in a seep or tar pit. If an impermeable layer instead blocks the way, the hydrocarbons can collect in porous rock beneath the impermeable layer. The business of drilling for oil consists of finding and tapping these "pay zones" of porous hydrocarbon-filled rock.
Pore Pressure and Fracture Gradient Pore pressure is the pressure exerted by fluids in the pore space of rock. If drillers do not balance pore pressure with pressure from drilling fluids, hydrocarbons can flow into the wellbore (the hole drilled by the rig, including the casing) and unprotected sections of the well can collapse. The pore- pressure gradient, expressed as an equivalent mud weight, is a curve that shows the increase of pore pressure in a well by depth.
91Fracture pressure is the pressure at which the geologic formation is not strong enough to withstand the pressure of the drilling fluids in a well and hence will fracture. When fracture occurs, drilling fluids flow out of the wellbore into the formation instead of circulating back to the surface. This causes what is known as "lost returns" or "lost circulation." The fracture gradient, expressed as an equivalent mud weight, is a curve that shows the fracture pressure of rocks in a well by depth.
¶The weight of the rocks above a pay zone can generate tremendous pressure on the hydrocarbons. Typically, the deeper the well, the higher the pressure—and the higher the pressure, the greater the challenges in safely tapping those hydrocarbons. The first oil wells were drilled on land and involved relatively low-pressure oil reservoirs. As oil companies drilled farther offshore, they encountered large hydrocarbon deposits, often in more porous and permeable geologic formations, and, like at the Macondo well, at ever-higher pressures.
¶The principal challenge in deepwater drilling is to drill a path to the hydrocarbon-filled pay zone in a manner that simultaneously controls these enormous pressures and avoids fracturing the geologic formation in which the reservoir is found. It is a delicate balance. The drillers must balance the reservoir pressure (pore pressure) pushing hydrocarbons into the well with counter-pressure from inside the wellbore. If too much counter-pressure is used, the formation can be fractured. But if too little counter-pressure is used, the result can be an uncontrolled intrusion of hydrocarbons into the well, and a discharge from the well itself as the oil and gas rush up and out of the well. An uncontrolled discharge is known as a blowout.
¶Drill Pipe, Mud, Casing, Cement, and Well Control Those drilling in deepwater, just like those drilling on land, use drill pipe, casing, mud, and cement in a series of carefully calibrated steps to control pressure while drilling thousands of feet below the seafloor to reach the pay zone. Drilling mud, which is used to lubricate and cool the drill bit during drilling, plays a critical role in controlling the hydrocarbon pressure in a well. The weight of the column of mud in a well exerts pressure that counterbalances the pressure in the hydrocarbon formation. If the mud weight is too low, fluids such as oil and gas can enter the well, causing what is known as a "kick." But if the mud weight is too high, it can fracture the surrounding rock, potentially leading to "lost returns"—leakage of the mud into the formation. The rig crew therefore monitors and adjusts the weight (density) of the drilling mud as the well is being drilled—one of many sensitive, technical tasks requiring special equipment and the interpretation of data from difficult drilling environments.
Drilling Terminology Drilling through the seafloor does not differ fundamentally from drilling on land. The crews on any drilling rig use rotary drill bits that they lubricate and cool with drilling mud—an ordinary name for what is today a sophisticated blend of synthetic fluids, polymers, and weighting agents that often costs over $100 per barrel. The rig crews pump the mud down through a drill pipe that connects with and turns the bit. The mud flows out holes in the bit and then circulates back to the rig through the space between the drill pipe and the sides of the well (the annulus), carrying to the surface bits of rock called cuttings that the drill bit has removed from the bottom of the well. When the mud returns to the rig at the surface, the cuttings are sieved out and the mud is sent back down the drill string. The mud thus travels in a closed loop.
92As the well deepens, the crew lines its walls with a series of steel tubes called casing. The casing creates a foundation for continued drilling by reinforcing upper portions of the hole as drilling progresses. After installing a casing string, the crews drill farther, sending each successive string of casing down through the prior ones, so the well's diameter becomes progressively smaller as it gets deeper. A completed deepwater well typically telescopes down from a starting casing diameter of three feet or more at the wellhead to a diameter of 10 inches or less at the bottom.
Casing strings, which are a series of steel tubes installed to line the well as the drilling progresses, also help to control pressures. First, they protect more fragile sections of the well structure outside the casing from the pressure of the mud inside. Second, they prevent high-pressure fluids (like hydrocarbons) outside the casing from entering the wellbore and flowing up the well. To secure the casing, crews pump in cement to seal the space between the casing and the wellbore. If a completed well can yield economically valuable oil and gas, the crews can initiate production by punching holes through the casing and surrounding cement to allow hydrocarbons to flow into the well.
Designed and used properly, drilling mud, cement, and casing work together to enable the crew to control wellbore pressure. If they fail, the crew can, in an emergency, close powerful blowout-preventer valves that should seal off the well at the wellhead.
¶Deepwater Horizon Arrives and Resumes Drilling the Well
After purchasing the rights to drill in Block 252, BP became the legal "operator" for any activities on that block. But BP neither owned the rigs, nor operated them in the normal sense of the word. Rather, the company's Houston-based engineering team designed the well and specified in detail how it was to be drilled. A team of specialized contractors would then do the physical work of actually drilling the well—a common industry practice. Transocean, a leading owner of deepwater drilling rigs, would provide BP with a rig and the crew to run it. Two BP "Well Site Leaders" (the "company men") would be on the rig at all times to direct the crew and contractors and their work, and would maintain regular contact with the BP engineers on shore.
BP actually used two Transocean rigs to drill the Macondo well. The Marianas began work in October 2009 and drilled for 34 days, reaching a depth of 9,090 feet, before it had to stop drilling and move off-site to avoid Hurricane Ida. As described in Chapter 1, the storm nevertheless damaged the rig badly enough that BP called in the Deepwater Horizon to take over.
While the Marianas had been anchored in place with huge mooring chains, the Deepwater Horizon was a dynamically positioned mobile offshore drilling unit (MODU).2 It relied on thrusters and satellite-positioning technology to stay in place over the well. Once the rig arrived on January 31, 2010, and began drilling operations, Transocean's Offshore Installation Manager Jimmy Harrell took over responsibility as the top Transocean employee on the rig.
93When the Deepwater Horizon arrived, its first task was to lower its giant blowout preventer (BOP) onto the wellhead that the Marianas had left behind. The BOP is a stack of enormous valves that rig crews use both as a drilling tool and as an emergency safety device. Once it is put in place, everything needed in the well—drilling pipe, bits, casing, and mud—passes through the BOP. Every drilling rig has its own BOP, which its crew must test before and during drilling operations. After a week of surface testing, the Deepwater
¶FIGURE 4.1: Macondo Well Schematic
¶TrialGraphix
¶Horizon rig crew lowered the 400-ton device down through a mile of seawater and used a remotely operated vehicle (ROV) to guide it so that it could be latched onto the wellhead below.
¶The Deepwater Horizon's blowout preventer had several features that could be used to seal the well. The top two were large, donut-shaped rubber elements called "annular preventers" that encircled drill pipe or casing inside the BOP. When squeezed shut, they sealed off the annular space around the drill pipe. The BOP also contained five sets of metal rams. The "blind shear ram" was designed to cut through drill pipe inside the BOP to seal off the well in emergency situations. It could be activated manually by drillers on the rig, by an ROV, or by an automated emergency "deadman system." A casing shear ram was designed to cut through casing; and three sets of pipe rams were in place to close off the space around the drill pipe.
¶Below the wellhead stretched four telescopic casing strings installed by the Marianas to reinforce the hole it had begun drilling. The Deepwater Horizon crew proceeded to drill deeper into the Earth, setting progressively smaller-diameter casing strings along the way as required. (Figure 4.1) They cemented each new string into place, anchoring the well to— and sealing the well off from—the surrounding rock.
¶"Lost Circulation" Event at the Pay Zone, and a Revised Plan for the Well By early April, the Deepwater Horizon crew had begun to penetrate the pay zone—the porous hydrocarbon-bearing rock that BP had hoped to find. But on April 9, they suffered a setback. At 18,193 feet below sea level, the pressure exerted by the drilling mud exceeded
94the strength of the formation. Mud began flowing into cracks in the formation instead of returning to the rig. The rig had to stop drilling until the crew could seal the fracture and restore mud circulation.3
Lost circulation events are a fact of life in the oil business. The crew responded with a standard industry tactic. They pumped 172 barrels of thick, viscous fluid known as a "lost circulation pill" down the drill string, hoping it would plug the fractures in the formation.4 The approach worked, but BP's on-shore engineering team realized the situation had become delicate. They had to maintain the weight of the mud in the wellbore at approximately 14.0 pounds per gallon (ppg) in order to balance the pressure exerted by hydrocarbons in the pay zone.5 But drilling deeper would exert even more pressure on the formation, pressure that the BP team measured in terms of equivalent circulating density (ECD). The engineers calculated that drilling with 14.0 ppg mud in the wellbore would yield an ECD of nearly 14.5 ppg—enough of an increase that they risked further fracturing of the rock and more lost returns.
Equivalent Circulating Density (ECD) A column of fluid will exert an amount of pressure on its surroundings that can be calculated if one knows the height of the column and the density of the fluid. If one pumps the fluid to make it circulate through the column, it will exert even more pressure. Equivalent circulating density or ECD is used to describe the total effective pressure that a column of drilling mud exerts on a formation as it is circulated through the drill string and back up the wellbore. To pump a given fluid faster or through narrower restrictions, it has to be pumped at greater pressure, and this, in turn, increases the ECD.
The engineers concluded they had "run out of drilling margin": the well would have to stop short of its original objective of 20,200 feet.6 After cautiously drilling to a total depth of 18,360 feet, BP informed its lease partners Anadarko and MOEX that "well integrity and safety" issues required the rig to stop drilling further.7
At that point, Macondo was stable. Because the column of drilling mud in the wellbore was heavy enough to balance the hydrocarbon pressure, BP and its contractors, including Transocean, were able to spend the next five days8 between April 11 and 15 "logging" the open hole with sophisticated instruments. Based on the logging data, BP concluded that it had drilled into a hydrocarbon reservoir of sufficient size (at least 50 million barrels9) and pressure that it was economically worthwhile to install a final "production casing" string that BP would eventually use to recover the oil and gas.
¶Preparing the Well for Subsequent Production
95The engineers recognized that the lost circulation problems and delicacy of the rock formation at the bottom of the well would make it challenging to install the production casing.10 After the rig crew lowered the casing into its final position, Halliburton would cement it into place. Halliburton would pump a specialized cement blend down the inside of the casing string; when it reached the end of the casing, cement would flow out the bottom and up into the annular space between the casing and the sides of the open hole. Once cured, the cement would bond to the formation and the casing and—if all went
¶FIGURE 4.2: "Long String" vs. "Liner"
¶Two options for the Macondo production casing.
¶TrialGraphix well—seal off the annular space. BP and Halliburton had cemented the previous casing strings at Macondo, and this cement job would be particularly important. The first attempt at cementing any casing string is commonly called the primary cement job. For a primary cement job to be successful, it must seal off, or "isolate," the hydrocarbon-bearing zone from the annular space around the casing and from the inside of the casing itself.
¶The Engineers Select a "Long String" Casing BP's design team originally had planned to use a "long string" production casing—a single continuous wall of steel between the wellhead on the seafloor, and the oil and gas zone at the bottom of the well. But after the lost circulation event, they were forced to reconsider. As another option, they evaluated a "liner"—a shorter string of casing hung lower in the well and anchored to the next higher string. (Figure 4.2) A liner would result in a more complex—and theoretically more leak-prone—system over the life of the well. But it would be easier to cement into place at Macondo.
¶On April 14 and 15, BP's engineers, working with a Halliburton engineer, used sophisticated computer programs to model the likely outcome of the cementing process. When early results suggested the long string could not be cemented reliably, BP's
96design team switched to a liner. But that shift met resistance within BP.11 The engineers were encouraged to engage an in-house BP cementing expert to review Halliburton's recommendations. That BP expert determined that certain inputs should be corrected. Calculations with the new inputs showed that a long string could be cemented properly. The BP engineers accordingly decided that installing a long string was "again the primary option."12
Centralizers and the Risk of Channeling Installing the agreed-upon casing was a major job. Even moving at top speed, the crew on the Deepwater Horizon needed more than 18 hours just to lower a tool, such as a drill bit, from the rig floor to the bottom of the well, 18,000 feet below sea level. Assembling the production casing section-by-section and lowering the lengthening string down into the well below would require roughly 37 hours.13
As the crew gradually assembled and lowered the casing, they paused several times to install centralizers (Figure 4.3) at predetermined points along the casing string. Centralizers are critical components in ensuring a good cement job. When a casing string hangs in the center of the wellbore, cement pumped down the casing will flow evenly back up the annulus, displacing any mud and debris that were previously in that space and leaving a clean column of cement. If the casing is not centered, the cement will flow preferentially up the path of least resistance—the larger spaces in the annulus—and slowly or not at all in the narrower annular space. That can leave behind channels of drilling mud that can severely compromise a primary cement job by creating paths and gaps through which pressurized hydrocarbons can flow.
BP's original designs had called for 16 or more centralizers to be placed along the long string.14 But on April 1, team member Brian Morel learned that BP's supplier (Weatherford) had in stock only six "subs"15—centralizers designed to screw securely into place between sections of casing. The alternative was to use FIGURE 4.3: Centralizer Sub "slip-on" centralizers—devices that slide onto the exterior of a piece of casing where they are normally secured in place by mechanical "stop collars" on either side. These collars can either be welded directly to the centralizers or supplied as separate pieces. The BP team—and Wells Team Leader John Guide in particular—distrusted slip-on centralizers with separate stop collars because the pieces can slide out of position or, worse, catch on other equipment as the casing is lowered.16
97Shortly after the BP team decided on the long string, Halliburton engineer Jesse Gagliano ran computer simulations using proprietary software called OptiCem, in part to predict whether mud channeling would occur. OptiCem calculates the likely outcome of a cement job based on a number of variables, Centralizer "subs" screw into place including the geometry of the wellbore and casing, the size between sections of casing. and location of centralizers, the rate at which cement will be Weatherford pumped, and the relative weight and viscosity of the cement
¶compared to the mud it displaces. Gagliano's calculations suggested that the Macondo production casing would need more than six centralizers to avoid channeling.
¶Gagliano told BP engineers Mark Hafle and Brett Cocales about the problem on the afternoon of April 15.17 With de facto leader John Guide out of the office, Gregory Walz, the BP Drilling Engineering Team Leader, obtained permission from senior manager David Sims to order 15 additional slip-on centralizers—the most BP could transport immediately in a helicopter. That evening, Gagliano reran his simulations and found that channeling due to gas flow would be less severe with 21 centralizers in place. Late that night, Walz sent an e-mail to Guide explaining that he and Sims felt that BP needed to "honor the [OptiCem] modeling to be consistent with our previous decisions to go with the long string."18
¶When Guide learned the next day of the decision to add more centralizers, he initially deferred, but then challenged the decision. Walz had earlier assured Guide that the 15 additional centralizers would be custom-designed one-piece units that BP had used on a prior well FIGURE 4.4: Shoe Track and would limit the potential for centralizer "hang up."19 But when the centralizers arrived, BP engineer Brian Morel, who happened to be out on the rig, reported that the centralizers were of conventional design with separate stop collars. Morel e-mailed BP drilling engineer Brett Cocales to question the need for additional centralizers.20 Cocales responded that the team would "probably be fine" even without the additional centralizers and that "Guide is right on the risk/reward equation."21
¶Guide pointed out to Walz that the new centralizers were not custom-made as specified.22 "Also," he noted, "it will take 10 hrs to install them." He complained that the "last minute addition" of centralizers would add 45 pieces of equipment to the casing that could come off during installation, and concluded by saying that he was "very concerned." In the end, Guide's view prevailed; BP installed only the six centralizer subs on the Macondo production casing.
¶Lowering the Casing String Into Position Early on the morning of April 18, with a centralizer plan in hand, the rig crew finally The shoe track, showing the float collar assembly at the top and the reamer shoe at the bottom. began assembling and lowering the long string into position. The leading end of the casing, TrialGraphix
98the "shoe track," began with a "reamer shoe"—a bullet-shaped piece of metal with three holes designed to help guide the casing down the hole. (Figure 4.4) The reamer shoe was followed by 180 feet of seven-inch-diameter steel casing. Then came a Weatherford- manufactured "float collar," a simple arrangement of two flapper (float) valves, spaced one after the other, held open by a short "auto-fill tube" through which the mud in the well could flow. As the long string was lowered down the wellbore, the mud passed through the holes in the reamer shoe and auto-fill tube that propped open the float valves, giving it a clear flow path upward.
Preparation for Cementing—and Unexpected Pressure Anomalies in the Well The long string was installed in its final position early on the afternoon of April 19. With the top end of the string seated in the wellhead and its bottom end located just above the bottom of the wellbore, the crew's next job was to prepare the float-valve system for cementing. During the cementing process, fluids pumped into the well should flow in a one-way path: down the center of the last casing string, out the bottom, and up the annulus (between the exterior of the steel casing and the surrounding rock formations). To ensure unidirectional flow, the crew needed to push the auto-fill tube downward, so it would no longer prop open the float valves. With the tube out of the way, the flapper valves would spring shut and convert from two-way valves into one-way valves that would allow mud and cement to flow down the casing into the shoe track, but prevent any fluid from reversing direction and coming back up the casing. Once the float valves had converted, Halliburton could pump cement down through the casing and up around the annulus; the valves would keep cement from flowing back up the casing once the crew stopped pumping.
To convert the float valves, that evening the crew began pumping mud down through the casing. Based on Weatherford's specifications, the valves should convert once the rate of flow though holes in the auto-fill tube had reached roughly 6 barrels per minute (bpm), causing a differential pressure on the tube of approximately 600 pounds per square inch (psi).23 But the crew hit a stumbling block. They pumped fluids into the well, eventually pressuring up to 1,800 psi, but could not establish flow.
Well Site Leader Bob Kaluza and BP engineer Morel24 called Guide, their supervisor on shore. In consultation with Guide and Weatherford staff, the rig team decided to increase the pump pressure in discrete increments, hoping eventually to dislodge the auto-fill tube.25 On their ninth attempt, pump pressure peaked at 3,142 psi and then suddenly dropped as mud finally began to flow. Significantly, however, the pump rate of mud into the well and through the shoe track thereafter never exceeded approximately 4 bpm.26
99BP's team concluded that the float valves had converted, but noted another anomaly. The drilling-mud subcontractor, M-I SWACO, had predicted that it would take a pressure of 570 psi to circulate mud after converting the float valves.27 Instead, the rig crew reported that circulation pressure was much lower: only 340 psi. BP's Well Site Leader Bob Kaluza expressed concern about low circulating pressure.28 He and the Transocean crew switched circulating pumps to see if that made a difference, and eventually concluded that the pressure gauge they had been relying on was broken.29 Believing they had converted the
¶float valves and reestablished mud circulation in the well, BP was ready at last to pump cement down the production casing and complete the primary cement job.
¶The Inherently Uncertain Cementing Process Cementing an oil well is an inherently uncertain process. To establish isolation across a hydrocarbon zone at the bottom of a well, engineers must send a slug of cement down the inside of the well. They then pump mud in after it to push the cement down until it "turns the corner" at the bottom of the well and flows up into the annular space. If done properly, the slug of cement will create a long and continuous seal around the production casing, and will fill the shoe track in the bottom of the final casing string. But things can go wrong even under optimal conditions. If the cement is pumped too far or not far enough, it may not isolate the hydrocarbon zones. If oil-based drilling mud contaminates the water-based cement as the cement flows down the well, the cement can set slowly or not at all. And, as previously noted, the cement can "channel," filling the annulus unevenly and allowing hydrocarbons to bypass cement in the annular space. Given the variety of things that can go wrong with a cement job, it is hardly surprising that a 2007 MMS study identified cementing problems as one of the "most significant factors" leading to blowouts between 1992 and 2006.30
¶Even following best practices, a cement crew can never be certain how a cement job at the bottom of the well is proceeding as it is pumped. Cement does its work literally miles away from the rig floor, and the crew has no direct way to see where it is, whether it is contaminated, or whether it has sealed off the well. To gauge progress, the crew must instead rely on subtle, indirect indicators like pressure and volume: they know how much cement and mud they have sent down the well and how hard the pumps are working to push it. The crew can use these readings to check whether each barrel of cement pumped into the well displaces an equal volume of drilling mud—producing "full returns." They can also check for pressure spikes to confirm that "wiper plugs" (used to separate the cement from the surrounding drilling mud) have landed on time as expected at the bottom of the well. And they can look for "lift pressure"—a steady increase in pump pressure signifying that the cement has turned the corner at the bottom of the well and is being pushed up into the annular space against gravity.
¶While they suggest generally that the job has gone as planned, these indicators say little specific about the location and quality of the cement at the bottom of the well. None of them can take the place of pressure testing and cement evaluation logging (see below).
¶The Cementing Design: Critical Decisions for a Fragile Formation In the days leading up to the final cementing process, BP engineers focused heavily on the biggest challenge: the risk of fracturing the formation and losing returns. John Guide explained after the incident that losing returns "was the No. 1 risk."31 He and the other BP engineers worried that if their cementing procedure placed too much pressure on the geologic formation below, it might trigger another lost-returns event similar to the one on April 9. In this case, critical cement—not mud—might flow into the formation and be lost, potentially leaving the annular space at the bottom of the well open to hydrocarbon flow.
100The BP team's concerns led them to place a number of significant constraints on Halliburton's cementing design. The first compromise in BP's plan was to limit the circulation of drilling mud through the wellbore before cementing. Optimally, mud in the wellbore would have been circulated "bottoms up"—meaning the rig crew would have pumped enough mud down the wellbore to bring mud originally at the bottom of the well all the way back up to the rig. There are at least two benefits to bottoms up circulation. Such extensive circulation cleans the wellbore and reduces the likelihood of channeling. And circulating bottoms up allows technicians on the rig to examine mud from the bottom of the well for hydrocarbon content before cementing. But the BP engineers feared that the longer the rig crew circulated mud through the casing before cementing, the greater the risk of another lost-returns event. Accordingly, BP circulated approximately 350 barrels of mud before cementing, rather than the 2,760 barrels needed to do a full bottoms up circulation.32
BP compromised again by deciding to pump cement down the well at the relatively low rate of 4 barrels or less per minute.33 Higher flow rates tend to increase the efficiency with which cement displaces mud from the annular space. But the increased pump pressure required to move the cement quickly would mean more pressure on the formation (ECD) and an increased risk of lost returns. BP decided to reduce the risk of lost returns in exchange for a less-than-optimal rate of cement flow.
BP made a third compromise by limiting the volume of cement that Halliburton would pump down the well. Pumping more cement is a standard industry practice to insure against uncertain cementing conditions: more cement means less risk of contamination and less risk that the cement job will be compromised by slight errors in placement. But more cement at Macondo would mean a higher cement column in the annulus, which in turn would exert more pressure on the fragile formation below. Accordingly, BP determined that the annular cement column should extend only 500 feet above the uppermost hydrocarbon-bearing zone (and 800 feet above the main hydrocarbon zones), and that this would be sufficient to fulfill MMS regulations of "500 feet above the uppermost hydrocarbon-bearing zone."34 However, it did not satisfy BP's own internal guidelines, which specify that the top of the annular cement should be 1,000 feet above the uppermost hydrocarbon zone.35 As designed, BP would have Halliburton pump a total of approximately 60 barrels of cement down the well—a volume that its own engineers recognized would provide little margin for error.36
101Finally, in close consultation with Halliburton, BP chose to use "nitrogen foam cement"—a cement formula that has been leavened with tiny bubbles of nitrogen gas, injected into the cement slurry just before it goes down the well. This formula was chosen to lighten the resulting slurry from approximately 16.7 ppg to 14.5 ppg—thereby reducing the pressure the cement would exert on the fragile formation. The bubbles, in theory, would also help to balance the pore pressure in the formation and clear the annular space of mud as the cement flowed upward. Halliburton is an industry leader in foam cementing, but BP appears to have had little experience with foam technology for cementing production casing in the Gulf of Mexico.37
¶The Cement Slurry: Laboratory Analyses A cement slurry must be tested before it is used in a cement job. Because the pressure and temperature at the bottom of a well can significantly alter the strength and curing rate of a given cement slurry—and because storing cement on a rig can alter its chemical composition over time—companies like Halliburton normally fly cement samples from the rig back to a laboratory shortly before pumping a job to make sure the cement will work under the conditions in the well. The laboratory conducts a number of tests to evaluate the slurry's viscosity and flow characteristics, the rate at which it will cure, and its eventual compressive strength.
¶When testing a slurry that will be foamed with nitrogen, the lab also evaluates the stability of the cement that results. A stable foam slurry will retain its bubbles and overall density long enough to allow the cement to cure. The result is hardened cement that has tiny, evenly dispersed, and unconnected nitrogen bubbles throughout. If the foam does not remain stable up until the time the cement cures, the small nitrogen bubbles may coalesce into larger ones, rendering the hardened cement porous and permeable.38 If the instability is particularly severe, the nitrogen can "break out" of the cement, with unpredictable consequences.
¶On February 10, soon after the Deepwater Horizon began work on the well, Jesse Gagliano asked Halliburton laboratory personnel to run a series of "pilot tests" on the cement blend stored on the Deepwater Horizon that Halliburton planned to use at Macondo.39 They tested the slurry40 and reported the results to Gagliano. He sent the laboratory report to BP on March 8 as an attachment to an e-mail in which he discussed his recommended plan for cementing an earlier Macondo casing string.41
¶The reported data that Gagliano sent to BP on March 8 included the results of a single foam stability test. To the trained eye, that test showed that the February foam slurry design was unstable. Gagliano did not comment on the evidence of the cement slurry's instability, and there is no evidence that BP examined the foam stability data in the report at all.
¶Documents identified after the blowout reveal that Halliburton personnel had also conducted another foam stability test earlier in February. The earlier test had been conducted under slightly different conditions than the later one and had failed more severely.42 It appears that Halliburton never reported the results of the earlier February test to BP.
¶Halliburton conducted another round of tests in mid-April, just before pumping the final cement job. By then, the BP team had given Halliburton more accurate information about the temperatures and pressures at the bottom of the Macondo well, and Halliburton had progressed further with its cementing plan. Using this information, the laboratory personnel conducted several tests, including a foam stability test, starting on approximately April 13. The first test Halliburton conducted showed once again that the cement slurry would be unstable.43 The Commission does not believe that Halliburton ever reported this information to BP. Instead, it appears that Halliburton personnel subsequently ran a second foam stability test, this time doubling the pre-test "conditioning time" to three hours.44
102The evidence suggests that Halliburton began the second test at approximately 2:00 a.m. on April 18.45 That test would normally take 48 hours. Halliburton finished pumping the cement job just before 48 hours would have elapsed.46 Although the second test at least arguably suggests the foam cement design used at Macondo would be stable, it is unclear whether Halliburton had results from that test in hand before it pumped the job. Halliburton did not send the results of the final test to BP until April 26, six days after the blowout.47
Evaluating the Cementing Job Transocean's rig crew and Halliburton's cementers finished pumping the primary cement job at 12:40 a.m. on April 20.48 Once the pumps were off, a BP representative and Vincent Tabler of Halliburton performed a check to see whether the float valves were closed and holding. They opened a valve at the cementing unit to see whether any fluid flowed from the well. If more fluid came back than expected, that would indicate that cement was migrating back up into the casing and pushing the fluids above it out of the top of the well. Models had predicted 5 barrels of flow back. According to Brian Morel, the two men observed 5.5 barrels of flow, tapering off to a "finger tip trickle."49 According to Morel, 5.5 barrels of flow-back volume was within the acceptable margin for error.50 Tabler testified that they watched flow "until it was probably what we call a pencil stream," which stopped, started up again, and then stopped altogether.51 While it is not clear how long the two men actually watched for potential flow, they eventually concluded the float valves were holding.
With no lost returns, BP and Halliburton declared the job a success. Nathaniel Chaisson, one of Halliburton's crew on the rig, sent an e-mail to Jesse Gagliano at 5:45 a.m. saying, "We have completed the job and it went well."52 He attached a detailed report stating that the job had been "pumped as planned" and that he had seen full returns throughout the process.53 And just before leaving the rig, Morel e-mailed the rest of the BP team to say "the Halliburton cement team . . . did a great job."54
Cement Evaluation Tools Cement evaluation tools (including "cement bond logs") test the integrity of cement in the annular space around a casing. The tools measure whether and to what extent cement has bonded to the outside of the casing and formation, and the location and severity of any channels through the cement. Although a modern cement evaluation combines several different instruments, the primary approach is to analyze the casing's response to acoustic signals. Just as a muffled bell sounds different than a free-swinging bell, a well casing will respond differently depending on the volume and quality of cement around it. Cement evaluation tools do have important limits. Among other things, they work better after the cement has had time to cure completely. They also cannot evaluate cement in the shoe track of a casing, or in the annular space below the float valves.
103At the 7:30 a.m. morning meeting with contractors on the rig, the BP team concluded the cement job went well enough to send home a team of technicians from Schlumberger who had been standing by on the rig for at least one day already55 waiting to perform a suite of cement evaluation tests on the primary cement job, including cement bond logs.56 The BP team relied on a "decision tree" that Guide and BP engineers had prepared beforehand. The
¶FIGURE 4.5: Temporary Abandonment
¶The status of the well before and after temporary abandonment.
¶TrialGraphix primary criterion BP appears to have used to determine whether to perform the cement evaluation test was whether there were "[l]osses while cementing [the] long string."57 Having seen no lost returns during the cement job, BP sent the Schlumberger team home and moved on to prepare the well for temporary abandonment.
¶Temporary Abandonment and Preparing to Move On to the Next Job
¶Once BP decided to send the Schlumberger team home, Deepwater Horizon's crew began the final phase of its work. Drilling the Macondo well had required a giant offshore rig of Deepwater Horizon's capabilities. By contrast, BP, like most operators, would give the job of "completing" the well to a smaller (and less costly) rig, which would install hydrocarbon-collection and -production equipment. To make way for the new rig, the Deepwater Horizon would have to remove its riser* and blowout preventer from the wellhead—and before it could do those things, the crew had to secure the well through a process called "temporary abandonment."
¶Four features of the temporarily abandoned well are worth noting. First is the single 300-foot-long cement plug inside the wellbore. MMS regulations required BP to install a cement plug as a backup for the cement job at the bottom of the well. Second is the location of the cement plug: BP planned to put it 3,300 feet below the ocean floor, or "mud line" (which was deeper than MMS regulations allowed without dispensation, and deeper than usual).58 Third is the presence of seawater in the well below the sea floor: BP planned to replace 3,000 feet of mud in the wellbore above the cement plug with much
¶The riser is the piping that connects the drilling rig at the surface with the BOP at the wellhead on the seafloor.
104lighter seawater (seawater weighs roughly 8.6 ppg, while the mud in the wellbore weighed roughly 14.5 ppg). Fourth is the lockdown sleeve—a mechanical device that locks the long casing string to the wellhead to prevent it from lifting out of place during subsequent production operations. (Figure 4.5)
At 10:43 a.m., Morel e-mailed an "Ops Note" to the rest of the Macondo team listing the temporary abandonment procedures for the well.59 It was the first time the BP Well Site Leaders on the rig had seen the procedures they would use that day. BP first shared the procedures with the rig crew at the 11 a.m. pre-tour meeting that morning.60 The basic sequence was as follows:
Lockdown Sleeve Before the Macondo blowout, a lockdown sleeve was not generally considered a safety mechanism or barrier to flow prior to the production phase of the well. Drilling rigs did not generally set lockdown sleeves. Rather, completion or production rigs did so after the drilling phase. BP decided to have the Deepwater Horizon set the lockdown sleeve because the Horizon could do the job more quickly than the completion rig. Based on the Macondo event, and given early concerns that upward forces during the blowout had approached or exceeded the force needed to lift the production casing up out of its seat in the wellhead, the Commission believes operators should consider installing a lockdown sleeve or other device to lock the casing hanger in place as part of drilling operations (or, at the very least, at the outset of temporary abandonment).
- Perform a positive-pressure test to test the integrity of the production casing; 2. Run the drill pipe into the well to 8,367 feet (3,300 feet below the mud line); 3. Displace 3,300 feet of mud in the well with seawater, lifting the mud above the BOP and into the riser; 4. Perform a negative-pressure test to assess the integrity of the well and bottom-hole cement job to ensure outside fluids (such as hydrocarbons) are not leaking into the well; 5. Displace the mud in the riser with seawater; 6. Set the surface cement plug at 8,367 feet; and 7. Set the lockdown sleeve.61
¶The crew would never get through all of the steps in the procedure.
105BP's Macondo team had made numerous changes to the temporary abandonment procedures in the two weeks leading up to the April 20 "Ops Note." For example, in its April 12 drilling plan, BP had planned (1) to set the lockdown sleeve before setting the surface cement plug and (2) to set the surface cement plug in seawater only 6,000 feet below sea level (as opposed to 8,367 feet). The April 12 plan did not include a negative-pressure test.62 On April 14, Morel sent an e-mail entitled "Forward Ops" setting forth a different procedure, which included a negative-pressure test but would require setting the surface cement plug in mud before displacement of the riser with seawater.63 On April 16, BP sent an Application for Permit to Modify to MMS describing a temporary abandonment procedure that was different from the procedure in either the April 12 drilling plan, the April 14 e-mail, or the April 20 "Ops Note."64 There is no evidence that these changes went through any sort of formal risk assessment or management of change process.
¶Countdown to Blowout The first step in the temporary abandonment was to test well integrity: to make sure there were no leaks in the well.
¶The Positive-Pressure Test The positive-pressure test evaluates, among other things, the ability of the casing in the well to hold in pressure. MMS regulations require a positive-pressure test prior to temporary abandonment.65 To perform the test at Macondo, the Deepwater Horizon's crew first closed off the well below the BOP by shutting the blind shear ram (there was no drill pipe in the well at the time).66 Then, much like pumping air into a bike tire to check for leaks, the rig crew pumped fluids into the well (through pipes running from the rig to the BOP) to generate pressure and then checked to see if it would hold.
¶The crew started the positive-pressure test at noon.67 They pressured the well up to 250 psi for 5 minutes, and then pressured up to 2,500 psi and watched for 30 minutes. The pressure inside the well remained steady during both tests, showing there were no leaks in the production casing through which fluids could pass from inside the well to the outside. The drilling crew and BP's Well Site Leader Bob Kaluza considered the test successful. Later in the afternoon, Kaluza showed visiting BP executive Pat O'Bryan the pressure chart from the test; O'Bryan remarked, "Things looked good with the positive test."68
¶The Negative-Pressure Test: Unexpected Pressure Readings The negative-pressure test checks not only the integrity of the casing, like the positive-pressure test, but also the integrity of the bottomhole cement job. At the Macondo well, the negative-pressure test was the only test performed that would have checked the integrity of the bottomhole cement job.
¶Instead of pumping pressure into the wellbore to see if fluids leak out, the crew removes pressure from inside the well to see if fluids, such as hydrocarbons, leak in, past or through the bottomhole cement job. In so doing, the crew simulates the effect of removing the mud in the wellbore and the riser (and the pressure exerted by that mud) during temporary abandonment. If the casing and primary cement have been designed and installed properly, they will prevent hydrocarbons from intruding even when that "overbalancing" pressure is removed.69 First, the crew sets up the well to simulate the expected hydrostatic pressure exerted by the column of fluids on the bottom of the well in its abandoned state. Second, the crew bleeds off any pent-up pressure that remains in the well, taking it down to 0 psi. Third, the crew and Well Site Leaders watch to make sure that nothing flows up from and out of the well and that no pressure builds back up inside of the well. If there is no flow or pressure buildup, that means that the casing and primary cement have sealed the well off from external fluid pressure and flow. A negative-pressure test is successful if there is no flow out of the well for a sustained period and if there is no pressure build-up inside the well when it is closed at the surface.
¶To conduct a proper negative test at Macondo, BP would have to isolate the well from the effect of the 5,000-foot-plus column of drilling mud in the riser and a further 3,300-foot column of drilling mud below the seafloor. Those heavy columns of mud exerted much
106more pressure on the well than the seawater that would replace them after temporary abandonment. Specifically, the pressure at the bottom of the well would be approximately 2,350 psi lower after temporary abandonment than before.70 Once this pressure was removed, the downward force of the column of fluids in the well would be less than the pressure of the hydrocarbons in the reservoir, so the well would be in what is called an "underbalanced" state. It was therefore critical to test and confirm the ability of the well (including the primary cement job) to withstand the underbalance. If the test showed that hydrocarbons would leak into the well once it was underbalanced, BP would need to diagnose and fix the problem (perhaps remediating the cement job) before moving on, a process that could take many days.
The crew began the negative test of Macondo at 5:00 p.m. Earlier in the day, the crew had prepared for the negative test by setting up the well to simulate the planned removal of the mud in the riser and 3,300 feet of drilling mud in the wellbore. The crew ran the drill pipe down to approximately 8,367 feet below sea level and then pumped a "spacer"—a liquid mixture that serves to separate the heavy FIGURE 4.6: Displacing Mud With Spacer and drilling mud from the seawater—followed by Seawater Before the Negative Pressure Test seawater down the drill pipe to push (displace) 3,300 feet of mud from below the mud line to above the BOP. (Figure 4.6)
107While drilling crews routinely use water-based spacer fluids to separate oil-based drilling mud from seawater, the spacer BP chose to use during the negative pressure test was unusual. BP had directed M-I SWACO mud engineers on the rig to create a spacer out of two different lost-circulation materials left over on the rig—the heavy, viscous drilling fluids used to patch fractures in the formation when the crew experiences lost returns.71 M-I SWACO had previously mixed two different unused batches, or "pills," of lost-circulation materials in case there were further lost returns.72 BP wanted to use these materials as spacer in order to avoid having to dispose of them onshore as hazardous waste pursuant to the Resource and Conservation Recovery Act, exploiting an exception that allows companies to dump water-based "drilling fluids" overboard if they have been circulated down through a well.73 At BP's direction, M-I SWACO combined the materials to create an unusually large volume of spacer that Seawater (blue) displaces mud (brown) from wellbore and had never previously been used by anyone on riser, with spacer fluid separating the two. the rig or by BP as a spacer, nor been thoroughly TrialGraphix tested for that purpose.74
¶Once the crew had displaced the mud to above the BOP, they shut an annular preventer in the BOP, isolating the well from the downward pressure exerted by the heavy mud and spacer in the riser. The crew could now perform the negative-pressure test using the drill pipe: it would open the top of the drill pipe on the rig, bleed the drill pipe pressure to zero, and then watch for flow. The crew opened the drill pipe at the rig to bleed off any pressure that had built up in the well during the mud-displacement process. The crew tried to bleed the pressure down to zero, but could not get it below 266 psi. When the drill pipe was closed, the pressure jumped back up to 1,262 psi.
¶Around this time, the driller's shack was growing crowded. The night crew was arriving in preparation for the 6:00 p.m. shift change, which meant that both toolpushers—Wyman Wheeler and Jason Anderson—and both Well Site Leaders—Bob Kaluza and Don Vidrine— were present. In addition, a group of visiting BP and Transocean executives entered as part of a rig tour escorted by Transocean Offshore Installation Manager Jimmy Harrell.75 It was apparent to at least one member of the tour that the crew was having a "little bit of a problem."76
¶The crew had noticed that the fluid level inside the riser was dropping, suggesting that spacer was leaking down past the annular preventer, out of the riser, and into the well (Figure 4.7). Harrell, who stayed behind in the drill shack as the tour continued, ordered the annular preventer closed more tightly to stop the leak.77 Harrell then left the rig floor.
¶With that problem solved, the crew refilled the riser and once again opened up the drill pipe and attempted a second time to bleed the pressure down to 0 psi. This time, they were able to do so. But when they shut the drill pipe in again, the pressure built back up to at least 773 psi. The crew then attempted a third time to bleed off the pressure from the drill pipe, and was again able to get it down to 0 psi. When the crew shut the well back in, however, the pressure increased to 1,400 psi. At this point, the crew had bled the drill-pipe pressure down three times, but each time it had built back up. For a successful negative-pressure test, the pressure must remain at 0 psi when the pipe is closed after the pressure is bled off.
¶The Transocean crew and BP Well Site Leaders met on the rig floor to discuss the readings. In addition to Kaluza, Vidrine, and Anderson, Dewey Revette (Transocean's on-duty driller) and BP Well Site Leader trainee Lee Lambert were there. According to post-incident statements from both Well Site Leaders, Anderson said that the 1,400 psi pressure on the drill pipe was being caused by a phenomenon called the "bladder effect."78 According to Lambert, Anderson explained that heavy mud in the riser was exerting pressure on the annular preventer, which in turn transmitted pressure to the drill pipe. Lambert said that he did not recall anyone agreeing or disagreeing with Anderson's explanation.79
¶According to Harrell, after a lengthy discussion, BP Well Site Leader Vidrine then insisted on running a second negative-pressure test, this time monitoring pressure and flow on the kill line rather than the drill pipe. (The kill line is one of three pipes, each approximately 3 inches in diameter, that run from the rig to the BOP to allow the crew to circulate fluids into and out of the well at the sea floor.) The pressure on the kill line during the negative-pressure test should have been identical to the pressure on the drill pipe, as both flow
108¶FIGURE 4.7: Fluids Leak Past Annular Preventer
¶Spacer fluids (orange) leak past annular preventer.
¶TrialGraphix
paths went to the same place (and both should have been filled with seawater). Vidrine apparently insisted the negative test be repeated on the kill line because BP had specified that the test would be performed on the kill line in a permit application it submitted earlier to MMS.80
109For the second test, the crew opened the kill line and bled the pressure down to 0 psi. A small amount of fluid flowed, and then stopped.81 Rig personnel left the kill line open for 30 minutes but did not observe any flow from it. The test on the kill line thus satisfied the criteria for a successful negative pressure test—no flow or pressure buildup for a sustained period of time. But the pressure on the drill pipe remained at 1,400 psi throughout. The Well Site Leaders and crew never appear to have reconciled the two different pressure readings.82 The "bladder effect" may have been proposed as an explanation for the anomaly—but based on available information, the 1,400 psi reading on the drill pipe could
¶only have been caused by a leak into the well. Nevertheless, at 8 p.m., BP Well Site Leaders, in consultation with the crew, made a key error and mistakenly concluded the second negative test procedure had confirmed the well's integrity. They declared the test a success and moved on to the next step in temporary abandonment.
¶Displacing Mud from the Riser—and Mounting Signs of a Kick At 8:02 p.m., the crew opened the annular preventer and began displacing mud and spacer from the riser. Halliburton cementer Chris Haire went to the drill shack to check on the status of the upcoming surface cement plug job. Revette and Anderson told him the negative-pressure test had been successful and that Haire should prepare to set the surface cement plug.83
¶Revette sat down in his driller's chair to monitor the well for kicks—any unplanned influxes of gas or fluids—and other anomalies. As gaseous hydrocarbons in a kick rise up the wellbore, they expand with ever-increasing speed—a barrel of natural gas at Macondo could expand over a hundredfold as it traveled the 5,000 feet between the wellhead and the rig above.84 And as the gas expands, it pushes mud upward faster and faster, reducing the pressure on the gas and increasing the speed of the kick—making it imperative that rig crews recognize and respond to a kick as early as possible.
¶The individuals responsible for detecting kicks on a rig include the driller, assistant drillers, and the mudlogger.85 Dewey Revette was the driller on duty at the time; the two assistant drillers on duty were Donald Clark and Stephen Curtis. Joseph Keith of Sperry Sun was the mudlogger.
¶These individuals look for kicks by monitoring real-time data displays in the driller's shack, mudlogger's shack, and elsewhere on the rig. They watch two primary parameters. The first, and most reliable when available, is the volume of mud in the active pits. The volume of mud sent from the active pits into the well should equal the volume of mud returning to the active pits from the well. An increase in volume is a powerful indicator that something is flowing into the well.
¶Second, under normal circumstances, the volume and rate of flow of fluids coming from the well should equal the volume and rate of flow of fluid pumped into the well. If flow out of the well is greater than flow into the well, it is a strong indicator that a kick may be under way.
Active Pit System Rigs contain multiple mud pits. The Deepwater Horizon had 20 in all. Various fluids can be stored in these pits, including drilling mud. The active pit system is a subset of the mud pits that the driller selects for monitoring purposes.
¶In addition to these two primary parameters, the crew can perform visual "flow checks." There were a number of cameras and stations on the Deepwater Horizon where the driller, mudlogger, and others could observe whether fluids were flowing from the well. When
110the pumps are shut off and mud is no longer being sent into the well, flow out of the well should stop. Visual flow checks are a reliable way to monitor for kicks when pumps are off and are often used to confirm other kick indicators.
Finally, the driller and mudlogger also monitor drill-pipe pressure, but it is a more ambiguous kick indicator than the other parameters because there can be many reasons for a change in drill pressure. If drill-pipe pressure decreases while the pump rate remains constant, that may indicate that hydrocarbons have entered the wellbore and are moving up the well past the sides of the drill pipe. The lighter-weight hydrocarbons exert less downward pressure, meaning the pumps do not need to work as hard to push fluids into the well. If drill-pipe pressure increases while the pump rate remains constant, that may indicate that heavier mud is being pushed up from below (perhaps by hydrocarbons) and displacing lighter fluids in the well adjacent to the drill pipe. Unexplained changes in drill-pipe pressure may not always indicate a kick, but when observed should be investigated. The crew should shut down the pumps and monitor the well to confirm it is static; if they are unable to do so, they should shut in the well until the source of the readings can be determined.
The Deepwater Horizon had two separate systems for collecting and displaying real-time data. The "Hitec" system, owned by Transocean, was the source on which the Deepwater Horizon's drilling crew typically relied for monitoring the well. The "Sperry Sun" system—installed and operated by a Halliburton subsidiary at BP's request—sent data back to shore in real time, allowing BP personnel to access and monitor this data from anywhere with an Internet connection.* Individuals on the rig could monitor data from the Sperry Sun system as well.
Once the crew began displacing the riser with seawater at 8:02 p.m., they confronted the challenge of dealing with all of the returning mud. The driller repeatedly rerouted the mud returns from one pit to another in order to accommodate the incoming volume.86 During that time, the crew also sent mud from other locations into the active pit system.87 It is not clear whether the driller, assistant drillers, or mudlogger could adequately monitor active pit volume (or flow-in versus flow-out) during that time given all the activity.
Nevertheless, things appear to have been relatively uneventful until 9:00 p.m. Drill-pipe pressure was slowly but steadily decreasing over that time as lighter seawater displaced heavy drilling mud in the riser, lowering the pressure in the well and making it progressively easier to push seawater down into the well through the drill pipe.88
At approximately 9:01 p.m., however, drill-pipe pressure (shown by the red line in Figure 4.8) began slowly increasing, despite the fact that the pump rate remained constant.89 Over the next seven minutes, it crept slowly upward from 1,250 to 1,350 psi.90 While the
111
- It is difficult, if not impossible, to know precisely what the driller, assistant drillers, and mudloggers were doing and what data they were looking at between 8:00 p.m. and the first explosion at 9:49 p.m. Both the Hitec and Sperry Sun displays can be customized, and each operator typically has his own preferred set-up. Moreover, the full Hitec data set sank with the rig, leaving only the Sperry Sun subset of the data behind. Because the Sperry Sun data are all that is now available, the Commission focuses upon that data while recognizing that it is at best an approximation of what the driller, mudlogger, and others on the rig may have been looking at in the hours and minutes leading up to the blowout.
¶FIGURE 4.8: Increasing Drill-Pipe Pressure
¶Sperry Sun drill-pipe pressure data (in red).
¶magnitude of the increase may have appeared only as a subtle trend on the Sperry Sun display, the change in direction from decreasing to increasing was not.91 Testimony of Andrea Fleytas, 14. Oil and Gas and Sulphur Operations in the Outer Continental Shelf–Incident Reporting Requirements, 68 Fed. Reg. 40,585 (July 8, 2003). The Commission believes, based on interviews of the mudloggers on the Horizon, that the Hitec system may have shown a more obvious trend because it displays numeric values as opposed to trend lines such as those seen in the Sperry data shown in the text. Joseph Keith (Sperry), interview with Commission staff, October 6, 2010; Cathleenia Willis (Sperry), interview with Commission staff, October 21, 2010. National Transportation Safety Board, Safety Recommendation (September 18, 1990), http://www.ntsb.gov/recs/ letters/1990/M90_26_31A.pdf.
¶Had someone noticed it, he would have had to explain to himself how the drill-pipe pressure could be increasing while the pump rate was not. One possible reason might have been that hydrocarbons were flowing into the well and pushing heavy drilling mud up past the drill pipe.
¶The crew may have been distracted by other matters. At about that time, the last of the mud in the riser was arriving at the rig.92 After that point, the next returning fluid would be the 400-plus barrels of spacer the crew had pumped into the well during the negative-pressure test. BP planned to dump that spacer overboard, but, according to regulations, would first have to run a test to make sure that it had removed all of the oil-based mud from the riser.93
112At 9:08 p.m., the crew shut down the pumps to perform this "sheen test."94 They closed a valve on the flow line that had been carrying fluids from the well to the pit system.95 Mud engineer Greg Meche sampled the fluid and had it tested. Well Site Leader Vidrine waited for confirmation that there was no oily "sheen" on the returning spacer.96 And mudlogger Joseph Keith performed a visual flow check to ensure the well was not flowing while the pumps were off. According to Keith, there was no flow.97
The pumps were shut down for 6 minutes, from 9:08 p.m. to 9:14 p.m. Meche took a sample of the returning fluid from the shaker house* and went to the mud lab to run the test.98 He then returned to the shaker house, weighed the sample, and spoke with another of the mud engineers about the results.99 When Vidrine learned the results, he signed off on the test and the crew turned the pumps back on.100
What nobody appears to have noticed during those six minutes (perhaps as a result of all of the activity) was that drill-pipe pressure was increasing again. With the pumps off, the drill-pipe pressure (red line in yellow box in Figure 4.8) should have stayed constant or gone down. Instead, it went up by approximately 250 psi.101 This increase in pressure was clear in the Sperry Sun data, and likely would have been clearer on the Hitec display. Had someone noticed it, he would have recognized this as a significant anomaly that warranted further investigation before turning the pumps back on. But by 9:14 p.m., the crew turned the pumps back on, obscuring the signal. Drill-pipe pressure increased, but so did the pump rate.102
Four minutes later, a pressure-relief valve on one of the pumps blew.103 Revette organized a group of crewmembers to go to the pump room to fix the valve. The group included derrickhand Wyatt Kemp, floorhands Shane Roshto and Adam Weise, and possibly one of the assistant drillers.104 These men were still attending to the repair at the time of the first explosion.105
At about 9:20 p.m., senior toolpusher Randy Ezell called the rig floor and asked Jason Anderson about the negative-pressure test. Anderson responded that, "It went good." Ezell then asked about the displacement. Anderson reassured Ezell, "It's going fine. . . . I've got this."106
Shortly before 9:30 p.m., Revette noticed an odd and unexpected pressure difference between the drill pipe and the kill line. At roughly 9:30 p.m., the crew shut off the pumps to investigate.107 At about that time, Chief Mate David Young arrived at the rig floor to discuss the upcoming cement plug job with Revette and Anderson.108 Young witnessed Revette and Anderson having a calm discussion about a "differential pressure."109 Anderson informed Young that the cement plug would be delayed.110
113The drill-pipe pressure initially decreased after the pumps were turned off, but then increased by 550 psi over a 5.5 minute period.111 (Figure 4.9) Meanwhile, the pressure on the kill line remained significantly lower. At approximately 9:36 p.m., Revette ordered The "shaker house" is a room or small separate structure on the rig for "shale shakers"—sieves and shakers that remove cuttings from the mud as it comes out of the well.
¶FIGURE 4.9: Fluctuating Drill-Pipe Pressure
¶Sperry Sun drill-pipe pressure data (in red).
¶floorhand Caleb Holloway to bleed off the drill-pipe pressure, in an apparent attempt to eliminate the difference.112 The drill-pipe pressure initially dropped off as expected, but immediately began climbing again.113 Young and Anderson left the rig floor.114 Despite the mounting evidence of a kick, however, neither Revette nor Anderson performed a visual flow check or shut in the well.
¶At 9:39 p.m., drill-pipe pressure shifted direction and started decreasing.115 In retrospect, this was a very bad sign. It likely meant that lighter-weight hydrocarbons were now pushing heavy drilling mud out of the way up the casing past the drill pipe.
¶Diversion and Explosion Sometime between 9:40 and 9:43 p.m., drilling mud began spewing from the rotary onto the rig floor. This appears to have been the first moment Revette or others realized that a kick had occurred. At about that time, Anderson and assistant driller Stephen Curtis returned to the rig floor.116
114The men took immediate action. First, they routed the flow coming from the riser through the diverter system, deciding to send it into the mud-gas separator rather than overboard into the sea (which was another option).117 Second, they closed one of the annular preventers on the BOP to shut in the well.118 At roughly 9:45 p.m., assistant driller Curtis called senior toolpusher Ezell to tell him that the well was blowing out, that mud was going into the crown on top of the derrick, and that Anderson was shutting the well in.119
Their efforts were futile. By the time the rig crew acted, gas was already above the BOP, rocketing up the riser, and expanding rapidly. At the Commission's November 8, 2010, hearing, a representative from Transocean likened it to "a 550-ton freight train hitting the rig floor," followed by what he described as "a jet engine's worth of gas coming out of the rotary."120 The flow from the well quickly overwhelmed the mud-gas separator system. Ignition and explosion were all but inevitable. The first explosion occurred at approximately 9:49 p.m. On the drilling floor, the Macondo disaster claimed its first victims.
The Well is Not Sealed by the Blowout Preventer The BOP is designed to contain pressure within the wellbore and halt an uncontrolled flow of hydrocarbons to the rig. The Deepwater Horizon's BOP did not succeed in containing the Macondo well.
Diverter System The diverter system provides two alternate paths for gas or gas-bearing mud returning to the rig from the well. The first path is through the mud-gas separator ("MGS"). The MGS consists of a series of pipes, valves, and a tank configured to remove gas entrained in relatively small amounts of mud. The gas is then vented from an outlet valve located high on the derrick. The MGS cannot accommodate substantial rates of mud flow. The second path is overboard. The diverter system has two 14-inch pipes, one starboard and one portside, through which flow can be sent overboard on the downwind side of the rig.
Witness accounts indicate that the rig crew activated one of the annular preventers around 9:41 p.m., and pressure readings suggest they activated a variable bore ram (which closes around the drill pipe) around 9:46 p.m.121 Flow rates at this point may have been too high for either the annular preventer or a variable bore ram to seal the well. (Earlier kick detection would have improved the odds of success.)
115After the first explosion, crewmembers on the bridge attempted to engage the rig's emergency disconnect system (EDS). The EDS should have closed the blind shear ram, severed the drill pipe, sealed the well, and disconnected the rig from the BOP.122 But none of that happened. Amid confusion on the bridge, and initial hesitancy from Captain Kuchta, subsea supervisor Chris Pleasant rushed to the main control panel and pushed the EDS button.123 Although the panel indicators lit up, the rig never disconnected.124 It is possible that the first explosion had already damaged the cables to the BOP, preventing the disconnect sequence from starting.
¶Even so, the BOP's automatic mode function (the "deadman" system) should have triggered the blind shear ram after the power, communication, and hydraulics connections between the rig and the BOP were cut. But the deadman failed too. Although it is too early to tell at this point, this failure may have been due to poor maintenance. Post-incident testing of the two redundant "pods" that control the deadman revealed low battery charges in one pod and defective solenoid valves in the other. If those problems existed at the time of the blowout, they would have prevented the deadman system from working.125*
¶The Immediate Causes of the Macondo Well Blowout
¶As this narrative suggests, the Macondo blowout was the product of several individual missteps and oversights by BP, Halliburton, and Transocean, which government regulators lacked the authority, the necessary resources, and the technical expertise to prevent. We may never know the precise extent to which each of these missteps and oversights in fact caused the accident to occur. Certainly we will never know what motivated the final decisions of those on the rig who died that night. What we nonetheless do know is considerable and significant: (1) each of the mistakes made on the rig and onshore by industry and government increased the risk of a well blowout; (2) the cumulative risk that resulted from these decisions and actions was both unreasonably large and avoidable; and (3) the risk of a catastrophic blowout was ultimately realized on April 20 and several of the mistakes were contributing causes of the blowout.
¶The immediate cause of the Macondo blowout was a failure to contain hydrocarbon pressures in the well. Three things could have contained those pressures: the cement at the bottom of the well, the mud in the well and in the riser, and the blowout preventer. But mistakes and failures to appreciate risk compromised each of those potential barriers, steadily depriving the rig crew of safeguards until the blowout was inevitable and, at the very end, uncontrollable.
¶Cementing Long string casing vs. liner. BP's decision to employ a long string was not unprecedented. Long strings are used with some frequency by other operators in the Gulf of Mexico, although not very often at wells like Macondo—a deepwater well in an unfamiliar geology requiring a finesse cement job.126 It is not clear whether the decision to use a long string well design contributed directly to the blowout:127 But it did increase the difficulty of obtaining a reliable primary cement job in several respects,128 and primary cement failure was a direct cause of the blowout. The long string decision should have led BP and Halliburton to be on heightened alert for any signs of primary cement failure.
¶Number of centralizers. The evidence to date does not unequivocally establish whether the failure to use 15 additional centralizers was a direct cause of the blowout. But the process
¶The Commission has not yet determined whether the BOP failed to operate as designed or whether any of the factors discussed contributed to such a failure. The Commission believes it is inappropriate to speculate about answers to those questions at this time. Test records of critical emergency backup systems have not yet been made available. More importantly, a government-sponsored forensic analysis of the BOP is still under way; when completed, that should shed light on why the BOP failed to shut in the Macondo well.
116by which BP arrived at the decision to use only six centralizers at Macondo illuminates the flaws in BP's management and design procedures, as well as poor communication between BP and Halliburton.
For example, it does not appear that BP's team tried to determine before April 15 whether additional centralizers would be needed. Had BP examined the issue earlier, it might have been able to secure additional centralizers of the design it favored. Nor does it appear that BP based its decision on a full examination of all potential risks involved. Instead, the decision appears to have been driven by an aversion to one particular risk: that slip-on centralizers would hang up on other equipment.
BP did not inform Halliburton of the number of centralizers it eventually used, let alone request new modeling to predict the impact of using only six centralizers.129 Halliburton happened to find out that BP had run only six centralizers when one of its cement engineers overheard a discussion on the rig.130
Capping off the communication failures, BP now contends that the 15 additional centralizers the BP team flew to the rig may, in fact, have been the ones they wanted. BP's investigation report states that BP's Macondo team "erroneously believed" they had been sent the wrong centralizers.131 To this day, BP witnesses provide conflicting accounts as to what type of centralizers were actually sent to the rig.
BP's overall approach to the centralizer decision is perhaps best summed up in an e-mail from BP engineer Brett Cocales sent to Brian Morel on April 16. Cocales expressed disagreement with Morel's opinion that more centralizers were unnecessary because the hole was straight, but then concluded the e-mail by saying
But, who cares, it's done, end of story, [we] will probably be fine and we'll get a good cement job. I would rather have to squeeze [remediate the cement job] than get stuck above the WH [wellhead]. So Guide is right on the risk/reward equation.132
Float-valve conversion and circulating pressure. Whether the float valves converted, let alone whether "unconverted" float valves contributed to the eventual blowout, has not yet been, and may never be, established with certainty. But, what is certain is that BP's team again failed to take time to consider whether and to what extent the anomalous pressure readings may have indicated other problems or increased the risk of the upcoming cement job.
117BP's team appears not to have seriously examined why it had to apply over four times the 750 psi design pressure to convert the float valves. More importantly, the team assumed that the sharp drop from 3,142 psi meant the float valves had in fact converted. That was not at all certain. The auto-fill tube was designed to convert in response to flow-induced pressure. Without the required rate of flow, an increase in static pressure, no matter how great, will not dislodge the tube.
¶While BP's Macondo team focused on the peak pressure reading of 3,142 psi and the fact that circulation was reestablished, it does not appear the team ever considered whether sufficient mud flow rate had been achieved to convert the float valves. They should have considered this issue. Because of ECD concerns, BP's engineers had specified a very low circulating pump rate—lower than the flow rate necessary to convert the float valves. BP does not appear to have accounted for this fact.
¶Cement evaluation log decision. The BP team erred by focusing on full returns as the sole criterion for deciding whether to run a cement evaluation log. Receiving full returns was a good indication that cement or other fluids had not been lost to the weakened formation. But full returns provided, at best, limited or no information about: (1) the precise location where the cement had ended up; (2) whether channeling had occurred; (3) whether the cement had been contaminated;133 or (4) whether the foam cement had remained stable. Although other indicators—such as on-time arrival of the cement plugs and observation of expected lift pressure—were reassuring, they too provided limited information. Other cement evaluation tools could have provided more direct information about cementing success.
¶Cement evaluation logs plainly have their limitations, particularly at Macondo. But while many companies do not run cement evaluation logs until the completion phase, BP should have run one here—or sought other equivalent indications of cement quality in light of the many issues surrounding and leading up to the cement job. BP's own report agrees.134
¶Foam cement testing. As explained in an October letter written by the Commission's Chief Counsel, independent cement testing conducted by Chevron strongly suggests the foam cement slurry used at Macondo was unstable.135 As it turned out, Chevron's tests were consistent with several of Halliburton's own internal test results, some of which appear never to have been reported to BP.
¶Halliburton's two February tests both indicated that the foam cement slurry would be unstable, which should have prompted the company to reconsider its slurry design.136 It is irrelevant that the February tests were performed on a slightly different slurry than was actually pumped at Macondo or that assumptions about down-hole temperatures and pressures in February had changed by April 19. Under the circumstances, Halliburton should have examined why the February foam cement slurry was unstable, and should have highlighted the problematic test results for BP.
¶The two April foam stability tests further illuminate problems with Halliburton's cement design process. Like the two February tests, the first April test indicated the slurry was unstable.* This should have prompted Halliburton to review the Macondo slurry design immediately, especially given how little time remained before the cement was to be pumped. There is no indication that Halliburton ever conducted such a review or alerted BP to the results. It appears that Halliburton personnel responded instead by modifying the
¶Halliburton contends that its lab personnel performed this test improperly, but has not yet produced adequate evidence to support this assertion.
118test conditions—specifically, the pre-testing conditioning time—and thereby achieving an arguably successful test result.
Halliburton has to date provided nothing to suggest that its personnel selected the final conditioning time based on any sort of disciplined technical analysis of the Macondo well conditions.137 Moreover, Halliburton has not yet provided the Commission with evidence to support its view that cement should be "conditioned" for an extended time before stability testing. Given the apparent importance of this view, it should have been supported by careful pre-incident technical analysis and actual physical testing. At present, it appears only to be an unconfirmed hypothesis.
Even more serious, Halliburton documents strongly suggest that the final foam stability test results indicating a stable slurry may not even have been available before Halliburton pumped the primary cement job at Macondo.138 If true, Halliburton pumped foam cement into the well at Macondo at a time when all available test data showed the cement would be, in fact, unstable.
Risk evaluation of Macondo cementing decisions and procedures. BP's fundamental mistake was its failure—notwithstanding the inherent uncertainty of cementing and the many specific risk factors surrounding the cement job at Macondo—to exercise special caution (and, accordingly, to direct its contractors to be especially vigilant) before relying on the primary cement as a barrier to hydrocarbon flow.
Those decisions and risk factors included, among other things: • Difficult drilling conditions, including serious lost returns in the cementing zone; • Difficulty converting float equipment and low circulating pressure after purported conversion; • No bottoms up circulation; • Less than recommended number of centralizers; • Low rate of cement flow; and • Low cement volume.
Based on evidence currently available, there is nothing to suggest that BP's engineering team conducted a formal, disciplined analysis of the combined impact of these risk factors on the prospects for a successful cement job. There is nothing to suggest that BP communicated a need for elevated vigilance after the job. And there is nothing to indicate that Halliburton highlighted to BP or others the relative difficulty of BP's cementing plan before, during, or after the job, or that it recommended any post-cementing measures to confirm that the primary cement had in fact isolated the high-pressure hydrocarbons in the pay zone.
119Negative-Pressure Test Even when there is no reason for concern about a cement job, a negative-pressure test is "very important."139 By sending Schlumberger's cement evaluation team back to shore, BP chose to rely entirely on the negative-pressure test to directly evaluate the integrity of the primary cement at Macondo.
¶It is now undisputed that the negative-pressure test at Macondo was conducted and interpreted improperly. For instance, BP used a spacer that had not been used by anyone at BP or on the rig before, that was not fully tested, and that may have clogged the kill line.140 The pressure data were not ambiguous. Rather, they showed repeatedly that formation fluids, in this case hydrocarbons, were flowing into the well. The failure to properly conduct and interpret the negative-pressure test was a major contributing factor to the blowout.
¶Given the risk factors surrounding the primary cement job and other prior unusual events (such as difficulty converting the float valves), the BP Well Site Leaders and, to the extent they were aware of the issues, the Transocean crew should have been particularly sensitive to anomalous pressure readings and ready to accept that the primary cement job could have failed.141 It appears instead they started from the assumption that the well could not be flowing, and kept running tests and coming up with various explanations until they had convinced themselves their assumption was correct.142
¶The Commission has identified a number of potential factors that may have contributed to the failure to properly conduct and interpret the negative pressure test that night:
-
¶
- First, there was no standard procedure for running or interpreting the test in either MMS regulations or written industry protocols. Indeed, the regulations and standards did not require BP to run a negative-pressure test at all.
- Second, BP and Transocean had no internal procedures for running or interpreting negative-pressure tests, and had not formally trained their personnel in how to do so.
- Third, the BP Macondo team did not provide the Well Site Leaders or rig crew with specific procedures for performing the negative-pressure test at Macondo.
- Fourth, BP did not have in place (or did not enforce) any policy that would have required personnel to call back to shore for a second opinion about confusing data.
- Finally, due to poor communication, it does not appear that the men performing and interpreting the test had a full appreciation of the context in which they were performing it. Such an appreciation might have increased their willingness to believe the well was flowing. Context aside, however, individuals conducting and interpreting the negative-pressure test should always do so with an expectation that the well might lack integrity.
¶Temporary Abandonment Procedures Another factor that may have contributed to the blowout was BP's temporary abandonment procedure.
¶First, it was not necessary or advisable for BP to replace 3,300 feet of mud below the mud line with seawater. By replacing that much heavy drilling mud with much lighter
120seawater, BP placed more stress on the cement job at the bottom of the well than necessary. BP's stated reason for doing so was its preference for setting cement plugs in seawater rather than mud.143 While industry experts have acknowledged that setting cement plugs in seawater can avoid mud contamination and that it is not unusual for operators to set cement plugs in seawater,144 BP has provided no evidence that it or another operator has ever set a surface cement plug so deep in seawater (particularly without additional barriers). The risks BP created by its decision to displace 3,300 feet of mud with seawater outweighed its concerns about cement setting better in seawater than in mud. As BP has admitted, cement plugs can be set in mud.145 BP also could have set one or more non- cement bridge plugs (which work equally well in mud or seawater).146 No evidence has yet been produced that the BP team ever formally evaluated these options or the relative risks created by removing 3,300 feet of mud.
It was not necessary to set the cement plug 3,300 feet below the mudline. The BP Macondo team chose to do so in order to set the lockdown sleeve last in the temporary abandonment sequence to minimize the chances of damage to the sleeve. Setting the lockdown sleeve would require 100,000 pounds of force. The BP Macondo team sought to generate that force by hanging 3,000 feet of drill pipe below the sleeve—hence the desire to set the cement plug 3,000 feet below the mud line. BP's desire to set the lockdown sleeve last did not justify the risks its decision created. BP could have used other proven means to protect the lockdown sleeve if set earlier in the process. It also did not need 3,000 feet of space to generate 100,000 pounds of force.147 Merrick Kelley, the individual at BP in charge of lockdown sleeves in the Gulf of Mexico, told Commission staff that he had recommended setting the plug roughly 1,300 feet below the mud line (using heavier drill pipe), rather than 3,300 feet down. That would have significantly increased the margin of safety for the well.148
The most troubling aspect of BP's temporary abandonment procedure was BP's decision to displace mud from the riser before setting the surface cement plug or other barrier in the production casing.149 During displacement of the riser, the BOP would be open, leaving the cement at the bottom of the well (in the annulus and shoe track) as the only physical barrier to flow up the production casing between the pay zone and the rig.150 Relying so heavily on primary cement integrity put a significant premium on the negative-pressure test and well monitoring during displacement, both of which are subject to human error.
BP's decision under these circumstances to displace mud from the riser before setting another barrier unnecessarily and substantially increased the risk of a blowout. BP could have set the surface cement plug, or a mechanical plug, before displacing the riser.151 BP could have replaced the mud in the wellbore with heavier mud sufficient to overbalance the well.152 It is not apparent why BP chose not to do any of these things.
121Kick Detection The drilling crew and other individuals on the rig also missed critical signs that a kick was occurring. The crew could have prevented the blowout—or at least significantly reduced its impact—if they had reacted in a timely and appropriate manner. What is not now clear is precisely why the crew missed these signals.
¶The Sperry Sun data available to the crew from between 8:00 p.m. and 9:49 p.m. reveal a number of different signals that if observed, should at least have prompted the driller to investigate further, for instance, by conducting a visual flow check, and then shutting in the well if there were indications of flow. For instance, the increasing drill-pipe pressure after the pumps were shut down for the sheen test at 9:08 p.m. was a clear signal that something was happening in the well. Similarly, at roughly 9:30 p.m., the driller and toolpusher recognized an anomalous pressure difference between the drill pipe and kill line.153 Both of these signals should have prompted action—especially the latter: it was clearly recognized by the crew and echoed the odd pressure readings observed during the negative-pressure test. The crew should have done a flow check and shut in the well immediately upon confirmation of flow.
¶Why did the crew miss or misinterpret these signals? One possible reason is that they had done a number of things that confounded their ability to interpret signals from the well. For instance, after 9:08 p.m., the crew began sending fluids returning from the well overboard, bypassing the active pit system and the flow-out meter (at least the Sperry Sun flow-out meter). Only the mudlogger performed a visual flow check.154
¶It was neither necessary nor advisable—particularly where the cement at the bottom (in the annulus and shoe track) was the only barrier between the rig and pay zone—to bypass the active system and flow-out meter or to perform potentially confounding simultaneous operations during displacement of the riser. For instance, the crew could have routed the seawater through the active pit system before sending it into the well.
¶In the future, the instrumentation and displays used for well monitoring must be improved. There is no apparent reason why more sophisticated, automated alarms and algorithms cannot be built into the display system to alert the driller and mudlogger when anomalies arise. These individuals sit for 12 hours at a time in front of these displays. In light of the potential consequences, it is no longer acceptable to rely on a system that requires the right person to be looking at the right data at the right time, and then to understand its significance in spite of simultaneous activities and other monitoring responsibilities.
¶Diversion and Blowout Preventer Activation The crew should have diverted the flow overboard when mud started spewing from the rig floor. While that ultimately may not have prevented an explosion, diverting overboard would have reduced the risk of ignition of the rising gas. Considering the circumstances, the crew also should have activated the blind shear ram to close in the well. Diverting the flow overboard and/or activating the blind shear ram may not have prevented the explosion, but likely could have given the crew more time and perhaps limited the impact of the explosion.
122¶There are a few possible explanations for why the crew did neither:
- First, they may not have recognized the severity of the situation, though that seems unlikely given the amount of mud that spewed from the rig floor.
- Second, they did not have much time to act. The explosion occurred roughly six to eight minutes after mud first emerged onto the rig floor.
- Finally, and perhaps most significantly, the rig crew had not been trained adequately how to respond to such an emergency situation. In the future, well-control training should include simulations and drills for such emergencies—including the momentous decision to engage the blind shear rams or trigger the EDS.
¶The Root Causes: Failures in Industry and Government
Overarching Management Failures by Industry Whatever irreducible uncertainty may persist regarding the precise contribution to the blowout of each of several potentially immediate causes, no such uncertainty exists about the blowout's root causes. The blowout was not the product of a series of aberrational decisions made by rogue industry or government officials that could not have been anticipated or expected to occur again. Rather, the root causes are systemic and, absent significant reform in both industry practices and government policies, might well recur. The missteps were rooted in systemic failures by industry management (extending beyond BP to contractors that serve many in the industry), and also by failures of government to provide effective regulatory oversight of offshore drilling.
The most significant failure at Macondo—and the clear root cause of the blowout—was a failure of industry management. Most, if not all, of the failures at Macondo can be traced back to underlying failures of management and communication. Better management of decisionmaking processes within BP and other companies, better communication within and between BP and its contractors, and effective training of key engineering and rig personnel would have prevented the Macondo incident. BP and other operators must have effective systems in place for integrating the various corporate cultures, internal procedures, and decisionmaking protocols of the many different contractors involved in drilling a deepwater well.
123BP's management process did not adequately identify or address risks created by late changes to well design and procedures. BP did not have adequate controls in place to ensure that key decisions in the months leading up to the blowout were safe or sound from an engineering perspective. While initial well design decisions undergo a serious peer-review process155 and changes to well design are subsequently subject to a management of change (MOC) process,156 changes to drilling procedures in the weeks and days before implementation are typically not subject to any such peer-review or MOC process. At Macondo, such decisions appear to have been made by the BP Macondo team in ad hoc
¶fashion without any formal risk analysis or internal expert review.157 This appears to have been a key causal factor of the blowout.
¶A few obvious examples, such as the last-minute confusion regarding whether to run six or 21 centralizers, have already been highlighted. Another clear example is provided by the temporary abandonment procedure used at Macondo. As discussed earlier, that procedure changed dramatically and repeatedly during the week leading up to the blowout. As of April 12, the plan was to set the cement plug in seawater less than 1,000 feet below the mud line after setting the lockdown sleeve. Two days later, Morel sent an e-mail in which the procedure was to set the cement plug in mud before displacing the riser with seawater. By April 20, the plan had morphed into the one set forth in the "Ops Note": the crew would remove 3,300 feet of mud from below the mud line and set the cement plug after the riser had been displaced.
¶There is no readily discernible reason why these temporary abandonment procedures could not have been more thoroughly and rigorously vetted earlier in the design process.158 It does not appear that the changes to the temporary abandonment procedures went through any sort of formal review at all.
¶Halliburton and BP's management processes did not ensure that cement was adequately tested. Halliburton had insufficient controls in place to ensure that laboratory testing was performed in a timely fashion or that test results were vetted rigorously in-house or with the client. In fact, it appears that Halliburton did not even have testing results in its possession showing the Macondo slurry was stable until after the job had been pumped. It is difficult to imagine a clearer failure of management or communication.
¶The story of the foam stability tests may illuminate management problems within BP as well. By early April, BP team members had recognized the importance of timely cement testing.159 And by mid-April, BP's team had identified concerns regarding the timeliness of Halliburton's testing process.160 But despite their recognition that final changes to the cement design (made to accommodate their concerns about lost returns) might increase the risks of foam instability,161 BP personnel do not appear to have insisted that Halliburton complete its foam stability tests—let alone report the results to BP for review—before ordering primary cementing to begin.
¶BP, Transocean, and Halliburton failed to communicate adequately. Information appears to have been excessively compartmentalized at Macondo as a result of poor communication. BP did not share important information with its contractors, or sometimes internally even with members of its own team. Contractors did not share important information with BP or each other. As a result, individuals often found themselves making critical decisions without a full appreciation for the context in which they were being made (or even without recognition that the decisions were critical).
¶For example, many BP and Halliburton employees were aware of the difficulty of the primary cement job. But those issues were for the most part not communicated to the rig crew that conducted the negative-pressure test and monitored the well. It appears that
124BP did not even communicate many of those issues to its own personnel on the rig—in particular to Bob Kaluza, who was on his first hitch as a Well Site Leader on the Deepwater Horizon. Similarly, it appears at this time that the BP Well Site Leaders did not consult anyone on shore about the anomalous data observed during the negative-pressure test.162 Had they done so, the Macondo blowout may not have happened.
Transocean failed to adequately communicate lessons from an earlier near-miss to its crew. Transocean failed to adequately communicate to its crew lessons learned from an eerily similar near-miss on one of its rigs in the North Sea four months prior to the Macondo blowout. On December 23, 2009, gas entered the riser on that rig while the crew was displacing a well with seawater during a completion operation. As at Macondo, the rig's crew had already run a negative-pressure test on the lone physical barrier between the pay zone and the rig, and had declared the test a success.163 The tested barrier nevertheless failed during displacement, resulting in an influx of hydrocarbons. Mud spewed onto the rig floor—but fortunately the crew was able to shut in the well before a blowout occurred.164 Nearly one metric ton of oil-based mud ended up in the ocean. The incident cost Transocean 11.2 days of additional work and more than 5 million British pounds in expenses.165
Transocean subsequently created an internal PowerPoint presentation warning that "[t]ested barriers can fail" and that "risk perception of barrier failure was blinkered by the positive inflow test [negative test]."166 The presentation noted that "[f]luid displacements for inflow test [negative test] and well clean up operations are not adequately covered in our well control manual or adequately cover displacements in under balanced operations."167 It concluded with a slide titled "Are we ready?" and "WHAT IF?" containing the bullet points: "[h]igh vigilance when reduced to one barrier underbalanced," "[r]ecognise when going underbalanced—heightened vigilance," and "[h]ighlight what the kick indicators are when not drilling."168
Transocean eventually sent out an "operations advisory" to some of its fleet (in the North Sea) on April 14, 2010, reiterating many of the lessons learned and warnings from the presentation. It set out "mandatory" actions to take, acknowledging a "Lack of Well Control preparedness during completion phase," requiring that "[s]tandard well control practices must be maintained through the life span of the well" and stating that "[w]ell programs must specify operations where a single mechanical barrier . . . is in effect and a warning must be included to raise awareness. . . ."169
The language in this "advisory" is less pointed and vivid than the language in the earlier PowerPoint. Moreover, according to Transocean, neither the PowerPoint nor this advisory ever made it to the Deepwater Horizon crew.170
125Transocean has suggested that the North Sea incident and advisory were irrelevant to what happened in the Gulf of Mexico. The December incident in the North Sea occurred during the completion phase and involved failure of a different tested barrier. Those are largely
¶FIGURE 4.10: Examples of Decisions That Increased Risk At Macondo While Potentially Saving Time
Was There A Less Risky Less Time Than Decision Alternative Available? Alternative? Decision-maker
¶Not Waiting for More
¶Yes Saved Time BP on Shore
¶Centralizers of Preferred Design
¶Not Waiting for Foam Stability Test Halliburton
¶Results and/or Yes Saved Time (and Perhaps BP)
¶Redesigning Slurry on Shore
¶Not Running Cement
¶Yes Saved Time BP on Shore
¶Evaluation Log
¶Using Spacer Made from
¶Combined Lost Circulation Yes Saved Time BP on Shore
¶Materials to Avoid Disposal Issues
¶Displacing Mud from Riser Before
¶Yes Unclear BP on Shore
¶Setting Surface Cement Plug
¶Setting Surface Cement Plug 3,000 BP on Shore
¶Yes Unclear
¶Feet Below Mud Line in Seawater (Approved by MMS)
¶Not Installing Additional
¶Physical Barriers During Temporary Yes Saved Time BP on Shore
¶Abandonment Procedure
¶Not Performing Further Well Integrity Diagnostics in Light of Troubling BP (and Perhaps
¶Yes Saved Time and Unexplained Negative Pressure Transocean) on Rig
¶Test Results
¶Bypassing Pits and
¶Conducting Other Transocean
¶Simultaneous Operations Yes Saved Time (and Perhaps BP)
¶During Displacement on Rig cosmetic differences. The basic facts of both incidents are the same. Had the rig crew been adequately informed of the prior event and trained on its lessons, events at Macondo may have unfolded very differently.171
¶Decisionmaking processes at Macondo did not adequately ensure that personnel fully considered the risks created by time- and money-saving decisions. Whether purposeful or not, many of the decisions that BP, Halliburton, and Transocean made that increased the risk of the Macondo blowout clearly saved those companies significant time (and money).*
¶There is nothing inherently wrong with choosing a less-costly or less-time-consuming alternative—as long as it is proven to be equally safe. The problem is that, at least in regard to BP's Macondo team, there appears to have been no formal system for ensuring that alternative procedures were in fact equally safe. None of BP's (or the other companies') decisions in Figure 4.10 appear to have been subject to a comprehensive and systematic risk-analysis, peer-review, or management of change process. The evidence now available does not show that the BP team members (or other companies' personnel) responsible for these decisions conducted any sort of formal analysis to assess the relative riskiness of available alternatives.
¶The Commission cannot say whether any person at BP or another company at Macondo consciously chose a riskier alternative because it would cost the company less money.
126Corporations understandably encourage cost-saving and efficiency. But given the dangers of deepwater drilling, companies involved must have in place strict policies requiring rigorous analysis and proof that less-costly alternatives are in fact equally safe. If BP had any such policies in place, it does not appear that its Macondo team adhered to them. Unless companies create and enforce such policies, there is simply too great a risk that financial pressures will systematically bias decisionmaking in favor of time- and cost- savings. It is also critical (as described in greater length in Chapter 8) that companies implement and maintain a pervasive top-down safety culture (such as the ones described by the ExxonMobil and Shell CEOs at the Commission's hearing on November 9, 2010) that reward employees and contractors who take action when there is a safety concern even though such action costs the company time and money.172
Of course, some decisions will have shorter timelines than others, and a full-blown peer-reviewed risk analysis is not always practicable. But even where decisions need to be made in relatively short order, there must be systems in place to ensure that some sort of formal risk analysis takes place when procedures are changed, and that the analysis considers the impact of the decision in the context of all system risks. If it turns out there is insufficient time to perform such an analysis, only proven alternatives should be considered.
Regulatory Failures Government also failed to provide the oversight necessary to prevent these lapses in judgment and management by private industry. As discussed in Chapter 3, MMS regulations were inadequate to address the risks of deepwater drilling. Many critical aspects of drilling operations were left to industry to decide without agency review. For instance, there was no requirement, let alone protocol, for a negative-pressure test, the misreading of which was a major contributor to the Macondo blowout. Nor were there detailed requirements related to the testing of the cement essential for well stability.
Responsibilities for these shortfalls are best not assigned to MMS alone. The root cause can be better found by considering how, as described in Chapter 3, efforts to expand regulatory oversight, tighten safety requirements, and provide funding to equip regulators with the resources, personnel, and training needed to be effective were either overtly resisted or not supported by industry, members of Congress, and several administrations. As a result, neither the regulations nor the regulators were asking the tough questions or requiring the demonstration of preparedness that could have avoided the Macondo disaster.
127But even if MMS had the resources and political support needed to promulgate the kinds of regulations necessary to reduce risk, it would still have lacked personnel with the kinds of expertise and training needed to enforce those regulations effectively. The significance of inadequate training is underscored by MMS's approval of BP's request to set its temporary abandonment plug 3,300 feet below the mud line. At least in this instance, there was a MMS regulation that potentially applied. MMS regulations state that cement plugs for temporary abandonment should normally be installed "no more than 1,000 feet below the mud line," but also allow the agency to approve "alternate requirements for subsea wells case-by-case."173 Crucially, alternate procedures "must provide a level of safety and environmental protection that equals or surpasses current MMS requirements."174
¶BP asked for permission to set its unusually deep cement plug in an April 16 permit application to MMS.175 BP stated that it needed to set the plug deep in the well to minimize potential damage to the lockdown sleeve, and said it would increase the length of the cement plug to compensate for the added depth. An MMS official approved the request in less than 90 minutes.176 The official did so because, after speaking with BP, he was persuaded that 3,000 feet was needed to accommodate setting the lockdown sleeve, which he thought was important to do. It is not clear what, if any, steps the official took to determine whether BP's proposed procedure would "provide a level of safety . . . that equal[ed] or surpass[ed]" a procedure in which the plug would have been set much higher up in the well.
¶MMS's cursory review of the temporary abandonment procedure mirrors BP's apparent lack of controls governing certain key engineering decisions. Like BP, MMS focused its engineering review on the initial well design, and paid far less attention to key decisions regarding procedures during the drilling of the well. Also like BP, MMS did not assess the full set of risks presented by the temporary abandonment procedure. The limited scope of the regulations is partly to blame. But MMS did not supplement the regulations with the training or the processes that would have provided its permitting official with the guidance and knowledge to make an adequate determination of the procedure's safety.
¶Deepwater drilling provides the nation with essential supplies of oil and gas. At the same time, it is an inherently risky business given the enormous pressures and geologic uncertainties present in the formations where oil and gas are found—thousands of feet below the ocean floor. Notwithstanding those inherent risks, the accident of April 20 was avoidable. It resulted from clear mistakes made in the first instance by BP, Halliburton, and Transocean, and by government officials who, relying too much on industry's assertions of the safety of their operations, failed to create and apply a program of regulatory oversight that would have properly minimized the risks of deepwater drilling. It is now clear that both industry and government need to reassess and change business practices to minimize the risks of such drilling.
¶The tragic results of that accident included the immediate deaths of 11 men who worked on the rig, and serious injury to many others on the rig at the time of the explosion. During the next few hours, days, weeks, and ultimately months, BP and the federal government struggled with their next great challenge: containing the spill and coordinating a massive response effort to mitigate the threatened harm to the Gulf of Mexico and to the Gulf coast. They faced the largest offshore oil spill in the nation's history—and the first from a subsea well located a mile beneath the ocean's surface.
129¶Chapter Five "You're in it now, up to your neck!" Response and Containment No single story dominated newspaper headlines on April 21 and 22. America's most-read papers led with articles about the progress of financial reform legislation; the Supreme Court's 8–1 ruling in a case about video depictions of animal cruelty and the First Amendment; the death of civil rights leader Dorothy Height; and the Food and Drug Administration's plans to target sodium content in packaged foods.1 Editors appear to have viewed these as slow news days. The New York Times, for example, ran a front-page story on April 22 about how travelers in Europe were coping with flight cancellations caused by volcanic ash, titled "Routine Flights Become Overland Odysseys, Minus Clean Socks."2
¶A reader who flipped 12 more pages into the Times would have encountered a less lighthearted headline: "11 Remain Missing After Oil Rig Explodes Off Louisiana."3 USA Today and the Wall Street Journal covered the Deepwater Horizon explosion on their front pages on April 22.4 The articles described the tragic accident and ensuing search- and-rescue operation—USA Today said it "could be one of the worst offshore drilling accidents in U.S. history"5—but did not discuss the potential for environmental calamity. As the Los Angeles Times put it, "Coast Guard experts worked to assess any environmental cleanup that may be necessary. . .
¶Shrimp boats skim oil off the coast of Louisiana in mid-May. At its peak, the response to the spill involved over 45,000 people and thousands of watercraft, including private "vessels of opportunity" put to work by BP. The well was finally capped on July 15—87 days after the explosion.
¶< Tyrone Turner/Photo courtesy of National Geographic
130[b]ut the main focus was on the missing workers."6 Other dimensions of the disaster would emerge in the days that followed.
The Early Response (April 20–28) On the night of April 20, as the Deepwater Horizon burned and the rig's survivors huddled on the Bankston, the response began. Coast Guard helicopters from the Marine Safety Unit in Morgan City, Louisiana searched for missing crew members. The first Coast Guard cutter to join the search was the Pompano, with others to follow. An offshore supply vessel found two burned life rafts. Coast Guard responders knew that approximately 700,000 gallons of diesel fuel were on the rig and could spill into the Gulf. By 10:00 the next morning, planes involved in the search for survivors reported a variably-colored sheen, two miles long by half a mile wide, on the water.
The Captain of the Marine Safety Unit, Joseph Paradis, directed these preliminary efforts. He became the first Federal On-Scene Coordinator under what is known as the National Contingency Plan, a set of federal regulations prescribing the government's response to spills and threatened spills of oil and other hazardous materials.* Under the Plan, when a spill occurs in coastal waters, the Coast Guard has the authority to respond.7
As the search and rescue continued on April 21, the oily sheen grew, more Coast Guard personnel and resources became involved, and Rear Admiral Mary Landry took over as Federal On-Scene Coordinator. The commander of Coast Guard District 8 (which includes, among other regions, the Gulf coast from Texas to the Florida panhandle), she would remain Federal On-Scene Coordinator until June 1. While the firefighting efforts continued, she told reporters, "We are only seeing minor sheening on the water. . . . We do not see a major spill emanating from this incident."8 At this point, Admiral Landry's concern was the fuel oil that could spill from the rig, though she cautioned, "We don't know what's going on subsurface."9
As Coast Guard vessels continued the search and rescue operation, private offshore supply vessels sprayed water on the fire. Transocean hired Smit Salvage Americas, a salvage company, to try to save the rig. There was confusion about whether Transocean, the Coast Guard, the salvage company, or anyone at all was directing the firefighting operations.† Captain James Hanzalik, Chief of Incident Response in District 8, would later say that the Coast Guard, which was focused on the search and rescue and then on the spreading oil, "monitored what was going on, but [was] not directing any firefighting resources."10 By the morning of April 21, the rig was listing. At 11:53 that evening, it shifted and leaned even more.
At 10:22 a.m. on April 22, the rig sank, taking with it the diesel fuel still on board. By that time, the Coast Guard had established an Incident Command Post in a BP facility in Houma, Louisiana. BP had formed a command post in its corporate headquarters in
131
- Created in 1968, the National Contingency Plan has been amended and expanded in the years since. The Oil Pollution Act of 1990 substantially expanded the Plan in response to the Exxon Valdez spill. The Coast Guard/Bureau of Ocean Energy Management, Regulation, and Enforcement Deepwater Horizon Joint Investigation Team, which plans to issue a report in March 2011, is examining the firefighting efforts.
¶Houston, Texas shortly after the explosion, and the Coast Guard established an Incident Command Post there as well.
¶These Incident Command Posts, along with one in Mobile, Alabama, and others established later, would become the centers of response operations, with their activities directed by the Federal On-Scene Coordinator as part of the government's Unified Command. The latter is a command structure, created and implemented by the National Contingency Plan, which integrates the "responsible party" (here, BP) with federal and state officials "to achieve an effective and efficient response."11 The Coast Guard established a Unified Area Command— headquarters for the regional spill response—on April 23 in Robert, Louisiana, later moving it to New Orleans. It eventually included representatives from the federal government, Louisiana, Alabama, Mississippi, Florida, and BP.
¶Other federal agencies—including the National Oceanic and Atmospheric Administration (NOAA) and Minerals Management Service (MMS)*—immediately sent emergency responders to the Unified Area Command and Incident Command Posts. A host of senior officials, including Secretary of the Interior Ken Salazar and Secretary of Homeland Security Janet Napolitano, briefed the President on their departments' efforts on the afternoon of April 22.12 Members of the National Response Team, drawn from the 16 federal agencies responsible for coordinating emergency preparedness and response to oil- and hazardous-substance-pollution incidents,13 began conducting daily telephone meetings.
¶Even before the rig sank, BP and Transocean directed their attention to the 53-foot-tall blowout preventer (BOP) stack sitting atop the Macondo well. At about 6:00 p.m. on April 21, BP and Transocean began using remotely operated vehicles to try to close the BOP and stop the flow of oil and gas fueling the fire.
¶These early operations primarily attempted to activate the BOP's blind shear ram and seal off the well. During the attempts, MMS officials were embedded, as observers, in the operations centers at Transocean and BP headquarters in Houston. Because of the emergency, on-scene personnel from BP, Transocean, and Cameron (the company that manufactured the BOP) made decisions without the need for government approvals. Beginning on April 21 and continuing throughout the effort to control the well, Secretary Salazar received daily updates through conference calls with BP's technical teams.
¶The initial news was encouraging. On April 23, Admiral Landry told the press that, according to surveillance by remotely operated vehicles, the BOP, although "[i]t is not a guarantee," appeared to have done its job, sealing off the flow of oil and preventing any leak.14 The good news did not last. The Coast Guard suspended its search for the 11 missing workers later that day. And, when Admiral Landry spoke, remotely operated vehicles had not yet surveyed the entire length of the broken riser pipe—previously
-
¶
- On June 18, 2010, Secretary of the Interior Ken Salazar ordered that the Minerals Management Service be officially renamed the Bureau of Ocean Energy Management, Regulation, and Enforcement. For consistency, throughout this chapter, we refer to the agency as the Minerals Management Service (MMS), its name at the time of the April 20 blowout.
connecting the well to the now-sunk Deepwater Horizon—that still jutted out of the top of the BOP. By mid-afternoon on April 23, the vehicles had discovered that oil was leaking from the end of the riser, where it had broken off from the Deepwater Horizon when the rig sank. By the next morning, the vehicles had also discovered a second leak from a kink in the riser, located above the BOP. On April 24, Unified Command announced that the riser was leaking oil at a rate of 1,000 barrels per day.15 This number appears to have come from BP, although how it was calculated remains unclear.16
As BP realized that the early efforts to stop the flow of oil had failed, it considered ways to control the well other than by triggering the BOP. A primary Oil spews unchecked from the Deepwater Horizon's option was to drill a relief well to intersect the severed riser in this video frame taken May 26. When the rig sank, the riser broke off, settling on the sea floor. Macondo well at its source and enable a drilling rig © BP p.l.c to pump in cement to stop the flow of oil. While it could take more than three months to drill, a relief well was the only source-control option mentioned by name in BP's Initial Exploration Plan.17 Industry and government experts characterized a relief well as the only likely and accepted solution to a subsea blowout.18 BP had begun looking for available drilling rigs on the morning of April 21; it secured two, and began drilling a primary relief well on May 2 and a back-up well insisted upon by Secretary Salazar on May 17.19
Responders, meanwhile, shifted their focus to the release of large amounts of oil. Although the National Contingency Plan requires the Coast Guard to supervise an oil-spill response in coastal waters, it does not envision that the Coast Guard will provide all, or even most, of the response equipment. That role is filled by private oil-spill removal organizations, which contract with the oil companies that are required to demonstrate response capacity. BP's main oil-spill removal organization in the Gulf is the Marine Spill Response Corporation, a nonprofit created by industry after the Exxon Valdez disaster to respond to oil spills. The Marine Spill Response Corporation dispatched four skimmers within hours of the explosion.20 BP's oil-spill response plan for the Gulf of Mexico claimed that response vessels provided by the Marine Spill Response Corporation and other private oil-spill removal organizations could recover nearly 500,000 barrels of oil per day.21
133Despite these claims, the oil-spill removal organizations were quickly outmatched. While production technology had made great advances since Exxon Valdez (see Chapter 2), spill-response technology had not. The Oil Pollution Act of 1990, by requiring double hulls in oil tankers, had effectively reduced tanker spills.22 But it did not provide incentives for industry or guaranteed funding for federal agencies to conduct research on oil-spill response. Though incremental improvements in skimming and boom had been realized in
¶the intervening 21 years, the technologies used in response to the Deepwater Horizon and Exxon Valdez oil spills were largely the same.23
¶If BP's response capacity was underwhelming, some aspects of its response plan were embarrassing. In the plan, BP had named Peter Lutz as a wildlife expert on whom it would rely; he had died several years before BP submitted its plan. BP listed seals and walruses as two species of concern in case of an oil spill in the Gulf; these species never see Gulf waters. And a link in the plan that purported to go to the Marine Spill Response Corporation website actually led to a Japanese entertainment site.24 (Congressional investigation revealed that the response plans submitted to MMS by ExxonMobil, Chevron, ConocoPhillips, and Shell were almost identical to BP's—they too suggested impressive but unrealistic response capacity and three included the embarrassing reference to walruses.25 See Chapter 3 for more discussion of these plans.)
¶By April 25, responders had started to realize that the estimated spill volume of 1,000 barrels per day might be inaccurate. Dispersants applied to break up the surface slick were not having the anticipated effect. Either the dispersants were inexplicably not working, or the amount of oil was greater than previously suspected. Between April 26 and April 28, BP personnel within Unified Command reportedly said that they thought 1,000 to 6,000 barrels were leaking each day.26
¶To alert government leadership that the spill could be larger than 1,000 barrels per day, a NOAA scientist created a one-page report on April 26 estimating the flow rate at roughly 5,000 barrels per day. He based this estimate on other responders' visual observations of the speed with which oil was leaking from the end of the riser, as well as the size and color of the oil slick on the Gulf 's surface.27 Both methodologies, the scientist recognized, were highly imprecise: he relied on rough guesses, for example, of the velocity of the oil as it left the riser and the thickness of the surface slick. He told a NOAA colleague in Unified Command that the flow could be 5,000 to 10,000 barrels per day.28 At a press conference on April 28, Admiral Landry stated, "NOAA experts believe the output could be as much as 5,000 barrels" (emphasis added).29
¶Although it represented a five-fold increase over the then-current figure, 5,000 barrels per day was a back-of-the-envelope estimate, and Unified Command did not explain how NOAA calculated it. Nevertheless, for the next four weeks, it remained the official government estimate of the spill size.
¶The Response Ramps Up (April 29–May 1) At the peak of the response, more than 45,000 people participated.30 In addition to deploying active-duty members to the Gulf, the Coast Guard called up reservists. Some 1,100 Louisiana National Guard troops served under the direction of Unified Command.31 The Environmental Protection Agency (EPA), NOAA, and other federal agencies shifted hundreds of responders to the region.
¶Consistent with the Unified Command framework, BP played a major role from the outset. Most Coast Guard responders had a BP counterpart. For instance, Doug Suttles, BP's Chief
134In a joint press briefing, BP Chief Operating Officer of Exploration and Production Doug Suttles takes the podium alongside Federal On- Scene Coordinator and Coast Guard Rear Admiral Mary Landry. The Coast Guard considered BP a co-combatant in the effort to battle the oil.
¶U.S. Coast Guard photo/Petty Officer 3rd Class Cory J. Mendenhall
Operating Officer of Exploration and Production, was the counterpart to the Federal On- Scene Coordinator. BP employees were scattered through the command structure, in roles ranging from waste management to environmental assessment. Sometimes, a BP employee supervised Coast Guard or other federal responders.
135The preference under the National Contingency Plan is for the Federal On-Scene Coordinator to supervise response activities while the responsible party conducts—and funds—them. When a spill "results in a substantial threat to public health or welfare of the United States," the Plan requires the Federal On-Scene Coordinator to direct all response efforts.32 The Coast Guard also has the option to "federalize" the spill—conducting and funding all aspects of the response through the Oil Spill Liability Trust Fund, and later seeking reimbursement from the responsible party.33 But in most spills, especially when
¶the responsible party has deep pockets and is willing to carry out response activities, federalizing is not preferred. Coast Guard leaders, shaped by their experience implementing the National Contingency Plan through a unified command system, viewed the responsible party as a co-combatant in the fight against the oil. From their perspective, BP took its role as responsible party seriously and had an open checkbook for response costs.* That did not mean BP was happy to pay. Tony Hayward, the Chief Executive Officer of BP, reportedly asked board members, "What the hell did we do to deserve this?"34
¶Though willing to fund and carry out the response, BP had no available, tested technique to stop a deepwater blowout other than the lengthy process of drilling a relief well. Forty years earlier, the government had recognized the need for subsea containment technology. In 1969, following the Santa Barbara Channel spill, the Nixon administration had issued a report recommending, in part, that "[u]nderwater methods to collect oil from subsea leaks should be developed."35 For deepwater wells, however, such development had never occurred. Within a week of the explosion, BP embarked on what would become a massive effort to generate containment options, either by adapting shallow-water technology to the deepwater environment, or by designing entirely new devices. Different teams at BP's Houston headquarters focused on different ways either to stop the flow of oil or to collect it at the source. Each team had what amounted to a blank check. As one contractor put it, "Whatever you needed, you got it. If you needed something from a machine shop and you couldn't jump in line, you bought the machine shop."36
¶While the Coast Guard oversaw the response at the surface, MMS primarily oversaw source-control operations. BP would draft detailed procedures describing an operation it wished to perform around the wellhead. MMS and Coast Guard officials in Houston participated in the drafting process to help identify and mitigate hazards, including risks to worker safety. At Unified Area Command, Lars Herbst, MMS Gulf of Mexico Regional Director, or his deputy, Mike Saucier, would review and approve the procedures, before the Federal On-Scene Coordinator gave the final go-ahead. This hierarchy of approvals remained in place throughout the containment effort.
¶MMS was the sole government agency charged with understanding deepwater wells and related technology, such as BOPs. But its supervision of the containment effort was limited, in line with its role in overseeing deepwater drilling more generally. Its staff did not attempt to dictate whether BP should perform an operation, determine whether it had a significant likelihood of success, or suggest consideration of other options. This limited role stemmed in part from a lack of resources. At most, MMS had four to five employees in Houston trying to oversee BP's efforts. One employee described his experience as akin to standing in a hurricane.
¶Interviews of MMS staff members involved in the containment effort also suggest that the agency did not view itself as capable of, or responsible for, providing more substantive oversight. One MMS employee asserted that BP, and industry more broadly, possessed 10 *
¶The day the rig exploded, the emergency reserve available to the Federal On-Scene Coordinator in the Oil Spill Liability Trust Fund and not obligated to other ongoing response actions amounted to $18,600,000. In contrast, by November 11, 2010, BP had paid $580,977,461 to the federal government for response costs. BP's total expenditures on the response also included payments to states and to contractors it hired directly. Paul Guinee, e-mail to Commission staff, November 16, 2010; BP, Claims and Government Payments Gulf of Mexico Oil Spill Public Report (November 11, 2010).
136times the expertise that MMS could bring to bear on the complex problem of deepwater spill containment. Another pointed out that MMS had trouble attracting the most talented personnel, who are more likely to work in industry where salaries are higher. A third MMS employee stated that he could count on one hand the people from the agency whom he would trust to make key decisions in an effort of this magnitude. Perhaps most revealingly, two different MMS employees separately recalled being asked—one by Secretary Salazar, and the other by Assistant Secretary Tom Strickland—what they would do if the U.S. government took over the containment effort. Both said they would hire BP or another major oil company.
Though the Coast Guard and MMS believed they had to work closely with BP, others in government did not share this view of the relationship with the responsible party. At an April 29 press conference with several senior administration officials, Coast Guard Rear Admiral Sally Brice O'Hara referred to BP as "our partner," prompting Secretary Napolitano to emphasize, "They are not our partner."37 Secretary Salazar later said on CNN that the government would keep its "boot on the neck" of BP.38
While struggling to explain its oversight role to the public, the federal government increased its commitment to the spill response. On April 29, a week after the rig sank and a day after the flow-rate estimate rose to 5,000 barrels per day, the Coast Guard designated the disaster a "Spill of National Significance"39—the first time the government had used that designation. A Spill of National Significance is one "that due to its severity, size, location, actual or potential impact on the public health and welfare or the environment, or the necessary response effort, is so complex that it requires extraordinary coordination of federal, state, local, and responsible party resources to contain and clean up the discharge."40 The designation permitted a National Incident Commander to "assume the role of the [Federal On-Scene Coordinator] in communicating with affected parties and the public, and coordinating federal, state, local, and international resources at the national level."41 Other than the quoted sentence, the National Contingency Plan is silent on the role of the National Incident Commander, who can fill the position, and what tasks he or she will handle. As a result, there is no clear line between the National Incident Commander's responsibilities and those of the Federal On-Scene Coordinator. During the Deepwater Horizon spill response, the National Incident Commander coordinated interagency efforts on the wide variety of issues responders faced, and dealt with high-level political and media inquiries, while the Federal On-Scene Coordinator generally retained oversight of day-today operations. More than anyone else, the National Incident Commander became the face of the federal response. When President Obama visited the Gulf on May 2, a fisherman asked who would pay his bills while he was out of work; the President responded that the National Incident Commander would take care of it.42
137On May 1, Secretary Napolitano announced that Admiral Thad Allen, the outgoing Commandant of the Coast Guard and then its only four-star Admiral, would serve as National Incident Commander.43 Admiral Allen was well known in the Gulf. He had previously overseen the ocean rescue and return to Cuba of Elian Gonzalez in 1999; the Coast Guard's work securing harbors along the Eastern Seaboard after the attacks of September 11, 2001; and the federal response to Hurricanes Katrina and Rita, after the
¶Surrounded by orange containment boom, National Incident Commander Admiral Thad Allen speaks to the press in Venice, Louisiana. The outgoing Coast Guard Commandant postponed his retirement to assume the post, drawing on his experience leading the federal response to Hurricane Katrina and overseeing oil-spill readiness exercises in the Gulf.
¶Steven Johnson/Miami Herald/MCT via Getty Images
¶Bush Administration asked him to replace the stumbling director of the Federal Emergency Management Agency, Michael Brown, as the lead federal official.44 His leadership during Katrina was widely considered a success. A Baton Rouge Advocate editorial published near the end of his time in the Gulf highlighted his local popularity and thanked him for his service.45 Less celebrated in the media, but no less important for the task facing him as National Incident Commander, was Admiral Allen's role overseeing a 2002 simulation that tested the readiness of the Coast Guard and other agencies to respond to a Spill of National Significance off the coast of Louisiana.46 As Commandant, Admiral Allen was already participating in the response, and he put off his scheduled retirement when he became National Incident Commander.
¶As the National Incident Command took shape in early May, BP's efforts to stop the flow of oil continued to focus on actuating the BOP, which BP still believed was the best chance of quickly shutting in the well. These efforts were plagued by engineering and organizational problems. For instance, it took nearly 10 days for a Transocean representative to realize that the stack's plumbing differed from the diagrams on which BP and Transocean were relying, and to inform the engineers attempting to trigger one of the BOP's rams through a hydraulic panel that they had been misdirecting their efforts.47 (Without properly recording the change, Transocean had reconfigured the BOP; the panel
138that was supposed to control that ram actually operated a different, "test" ram, which could not stop the flow of oil and gas.48 BP Vice President Harry Thierens, who was BP's lead on BOP interventions, stated afterward that he was "quite frankly astonished that this could have happened."49) While this and other problems delayed BP's efforts, the flow of oil and sand continued to wear down the BOP's parts, making closure more difficult.50
BP stopped trying to close the BOP on May 5.51 By May 7, it had concluded that "[t]he possibility of closing the BOP has now been essentially exhausted."52 In mid-May, at the suggestion of Secretary of Energy Steven Chu, BP undertook gamma-ray imaging of the BOP, which lacked instrumentation to show the position of its rams.53 The imaging indicated that, although the blind shear ram had closed at least partially, oil continued to flow past it.
The "Social and Political Nullification" of the National Contingency Plan (April 29–May 1) The hurricane-stricken Gulf states are all too familiar with emergency response; all are among the top dozen states in number of declared major disasters.54 State and local officials in the Gulf are accustomed to setting up emergency-response structures pursuant to the Stafford Act, under which the federal government provides funding and assists state and local governments during a major disaster.55 In contrast, the National Contingency Plan, which governs oil spills, gives the Federal On-Scene Coordinator the power to direct all response actions.56 Thus, while the Stafford Act envisions a state-directed (though in part federally funded) response, the National Contingency Plan puts federal officials in charge.
State and local officials chafed under federal control of the response. Louisiana Governor Bobby Jindal's advisors reportedly spent days trying to determine whether the Stafford Act or the National Contingency Plan applied.57 On April 29, Governor Jindal declared a state of emergency in Louisiana, authorizing the director of the Governor's Office of Homeland Security and Emergency Preparedness to undertake any legal activities deemed necessary to respond and to begin coordinating state response efforts.58 These efforts took place outside of the Unified Command framework. The Governors of Mississippi, Alabama, and Florida followed suit, declaring states of emergency the next day.59
At the outset of the spill, the pre-designated State On-Scene Coordinators for Louisiana, Alabama, and Mississippi participated in Unified Command.60 These individuals were career oil-spill responders: familiar with the National Contingency Plan, experienced in responding to spills, and accustomed to working with the Coast Guard. Some had participated in the 2002 spill exercise run by Admiral Allen. They shared the Coast Guard's view that the responsible party is an important ally, not an adversary, in responding to a spill.
139During this spill, however, the Governors and other state political officials participated in the response in unprecedented ways, taking decisions out of the hands of career oil-spill responders. These high-level state officials were much less familiar with spill-response
¶planning. In addition to the National Contingency Plan, each Coast Guard sector is an "Area" with an Area Contingency Plan created by relevant state and federal agencies. When confronted with a contingency plan setting out how the federal and state governments were supposed to run an oil-spill response, one high-level state official told a Coast Guard responder that he never signed it. According to the Coast Guard officer, the state official was not questioning whether his signature appeared on the document, but asserting that he had not substantively reviewed the plan.61 State and local officials largely rejected the pre-spill plans and began to create their own response structures.
¶Because the majority of the oil would come ashore in Louisiana, these issues of control mattered most there. Louisiana declined to empower the officials that it sent to work with federal responders within Unified Command, instead requiring most decisions to go through the Governor's office. For example, the Louisiana representative at Unified Area Command could not approve the daily agenda of response activities.62 Responders worked around this problem, but it complicated operations.
¶Local officials were even less familiar with oil-spill planning, though they had robust experience with other emergencies. Under Louisiana law, Parish Presidents exercise substantial authority—mirroring that of the Governor—during hurricanes and other natural disasters.63 The parishes wanted to assert that same control during the spill, and many used money distributed by BP to purchase their own equipment and establish their own operating centers outside of Unified Command. Eventually, the Coast Guard assigned a liaison officer to each Parish President, who attempted to improve relationships with the parishes by providing information and reporting back to Unified Command on local needs.
¶Local resentment became a media theme and then a self-fulfilling prophesy. Even those who privately thought the federal government was doing the best it could under the circumstances did not say so publicly.64 Coast Guard responders watched Governor Jindal—and the TV cameras following him—return to what appeared to be the same spot of oiled marsh day after day to complain about the inadequacy of the federal response, even though only a small amount of marsh was then oiled. When the Coast Guard sought to clean up that piece of affected marsh, Governor Jindal refused to confirm its location.65 Journalists encouraged state and local officials and residents to display their anger at the federal response, and offered coverage when they did. Anderson Cooper reportedly asked a Parish President to bring an angry, unemployed offshore oil worker on his show. When the Parish President could not promise the worker would be "angry," both were disinvited.66
¶As the media coverage grew more frenzied, the pressure increased on federal, state, and local officials to take action and to avoid being seen as in league with BP. What Admiral Allen would later call "the social and political nullification" of the National Contingency Plan, which envisions "unity of effort" between the federal government, state governments, and the responsible party, was well underway.67
¶Spill Impacts and Efforts To Help Effects on the Gulf economy, environment, and way of life increased as the spill dragged on and oil crept closer to shorelines. Concerns about fisheries took hold immediately. The
140Gulf of Mexico is home to crab, shrimp, oyster, and finfish fisheries, all of which were affected by the oil. The Louisiana Department of Wildlife and Fisheries and the Department of Health and Hospitals began closing fisheries and oyster grounds in state waters— three miles or less from shore—on April 30. State fishery closures continued piece by piece, beginning on June 2 in Alabama, June 4 in Mississippi, and June 14 in Florida.68 NOAA's Office of Response and Restoration began conducting flyovers and modeling the movement of the oil beginning April 23.69 Responders used these daily trajectory forecasts to anticipate where oil would be over the next 24- and 48-hour periods. Based on the forecasts, as well as sampling in or near affected areas, the federal fishery closures began on May 2. Through an emergency rule, NOAA's National Marine Fisheries Service first closed an area spanning approximately 6,817 square miles, or 3 percent of the Gulf federal fishing zone.70 On May 7, NOAA increased the closed area to 4.5 percent of that zone.71 A week later, it extended the closures indefinitely.72 NOAA continued to close additional areas, and on June 2—at the peak of the closures—it prohibited all fishing in nearly 37 percent of the Gulf zone.73
Although unable to fish, many fishermen were not content to lay idle. As contractors and subcontractors set up camp in towns across the Gulf to carry out response activities, residents viewed them with suspicion. People in Lafourche Parish, for example, worried about the out-of-state oil-spill-response contractors who took over their shores bringing crime and taking away spill-related job opportunities.74 Parish Presidents pushed BP and Unified Command to give clean-up jobs to residents and, in the newly out-of-work fishermen, saw a fleet of experienced captains who were more familiar with the intricate shoreline than any out-of-state oil-spill responders.
The Vessels of Opportunity program was BP's answer, and a way for BP to provide some income to affected residents outside of the formal claims process. Through the program, BP employed private vessels to conduct response efforts such as skimming, booming, and transporting supplies. Vessels of opportunity made between $1,200 and $3,000 per day, depending on the size of the boat. Individual crew members made $200 for an eight-hour day.75 But the program had delays and problems. BP and the Coast Guard were slow to develop eligibility requirements (such as an operable VHF-FM radio) for boats.76 Initially, there was not enough work. Later, residents and Parish Presidents complained that BP was not sufficiently targeting out-of-work fishermen at whom the program was ostensibly directed, and that wealthy or non-local boat owners were taking advantage of poor oversight to gain spots in the program. Eventually, BP established a verification process that prioritized boats registered with the state before March 2010 and that accepted only one boat per owner.77 The group that may have lost out the most on the program was the large population of Vietnamese-American fishermen. Many had arrived in the region as refugees and struggled with the lack of Vietnamese-language training.78 (Chapter 6 discusses the impacts of the spill on minority fishing communities.)
141Angry that BP was deploying non-local boats in his parish waters, Craig Taffaro, President of St. Bernard Parish, started his own program using the commercial fishing fleet based there. He submitted invoices to BP, which it paid. The State of Louisiana also began its own program, as did Plaquemines and Jefferson Parishes.79 Unified Command struggled
¶to coordinate this floating militia of independent vessels and to give them useful response tasks. Having hundreds of vessels look for oil did not contribute significantly to the response, because aircraft were more effective at spotting oil.80 Placing boom requires skill and training, and responders differed in their judgments of how much the vessels contributed.
¶In addition to overseeing the Vessels of Opportunity program, Unified Command needed to ensure that all workers, whether on boats or on shore, were adequately trained and taking safety precautions. The Occupational Safety and Health Administration (OSHA) began working with Unified Command at the end of April; under the National Contingency Plan, all response actions must comply with OSHA's training and safety requirements.81 OSHA established rules regarding protective equipment and, because the response relied in part on untrained workers, a shortened training course.82 Residents were eager to take on cleanup jobs, but some worried that, notwithstanding OSHA's involvement, response-related work would affect their health.83 (Chapter 6 discusses the impacts of response activities on health.)
¶Health issues for non-workers were thornier. The Centers for Disease Control and Prevention represents the Department of Health and Human Services on the National Response Team and had participated in recent spill training exercises. The Centers for Disease Control, however, had not foreseen that an oil spill could affect the health of the broader population and had not fully considered the role health agencies might play in a spill response.84 Others in the Department, including the Assistant Secretary for Preparedness and Response, had not either.85 Consequently, the Department had to consider during the disaster how it would fund spill-related activities, because BP would have to pay only for those deemed response measures by Unified Command. The Department was concerned that neither the Oil Spill Liability Trust Fund nor BP would reimburse it for activities such as long-term health surveillance, and negotiations over what costs qualified for reimbursement took time.86 At the request of Unified Command, Health and Human Services eventually, in June, sent a Senior Health Policy Advisor to support the National Incident Commander on public health issues.87
¶The spill affected wildlife health as well. On April 30, the Times-Picayune reported the recovery of the first oiled bird.88 From then on, crude-covered animals were a fixture in the media coverage and public perceptions of the disaster. The U.S. Fish and Wildlife Service, NOAA's Fisheries Service, state wildlife agencies, and academic organizations oversaw animal response and rehabilitation efforts.89 Wildlife responders took recovered animals to one of several treatment centers, washing, monitoring, and then releasing them.90 According to the Audubon Society, more than 12,000 volunteers signed up to help with these efforts during a single week in early May.91 Not all offers of assistance were accepted. Some groups that could have provided skilled wildlife responders, such as the National Wildlife Federation, felt discouraged from helping; in their view, there was no effective process for integrating skilled volunteers into the response structure.92 Would-be volunteers worried that animal mortality was greater than it would have been had more rescuers been out looking for oiled animals.93 (Chapter 6 discusses impacts on wildlife in detail.)
142Free once more, a pair of pelicans test their wings in Aransas National Wildlife Refuge after being de-oiled and nursed back to health. Taking part in the release are veterinarian Sharon Taylor and Refuge manager Dan Alonso. Over a thousand birds affected by the spill were rehabilitated; thousands of others were not so fortunate.
¶U.S. Coast Guard photo/Petty Officer 3rd Class Robert Brazzell
Along with volunteering for wildlife rescue, members of the general public submitted to BP and the Coast Guard numerous ideas for how to clean up the oil or plug the well. For instance, movie star Kevin Costner argued for the use of his oil-water separator, and BP eventually purchased 32 units.94 Citizens without Costner's resources had more trouble getting their ideas reviewed. On June 4, the Coast Guard established the Interagency Alternative Technology Assessment Program to receive, acknowledge, and evaluate ideas.95 The program received about 4,000 submissions.96 Most of the proposals were not viable or required too much time for development into operational response tools.* As ideas came in, the Coast Guard screened them and sent the most promising to the Federal On-Scene Coordinator, who ended up testing about a dozen during the course of the spill. None was implemented on a large scale, but the Coast Guard plans to use some of the proposals in its spill-response research.97
143Foreign companies and countries also offered assistance in the form of response equipment and vessels. The Coast Guard and National Incident Command accepted some of these offers and rejected others.98 News reports and politicians alleged that the federal government turned away foreign offers of assistance because of the Jones Act, a law preventing foreign vessels from participating in trade between U.S. ports.99 While decisionmakers did decline to purchase some foreign equipment for operational reasons— * Although intellectual property concerns prohibit the Coast Guard from disclosing the proposals actually submitted, news outlets reported that individuals suggested ideas like dumping popcorn from airplanes; soaking up the oil with packing peanuts, sawdust, kitty litter, and air conditioning filters; and using liquid nitrogen to freeze the oil. Julie Schmit, "After BP Oil Spill, Thousands of Ideas Poured in for Cleanup," USA Today, November 15, 2010; John W. Schoen, "BP's Suggestion Box Is Spilling Over," MSNBC, May 14, 2010.
¶for example, Dutch vessels that would have taken weeks to outfit and sail to the region, and a Taiwanese super-skimmer that was expensive and highly inefficient in the Gulf— they did not reject foreign ships because of Jones Act restrictions.100 These restrictions did not even come into play for the vast majority of vessels operating at the wellhead, because the Act does not block foreign vessels from loading and then unloading oil more than three miles off the coast.101 When the Act did apply, the National Incident Commander appears to have granted waivers and exemptions when requested.102
¶In the end, the response technology that created the most controversy was not a mechanical tool like a skimmer or oil-water separator, but a chemical one.
¶Initial Dispersant Decisions (April 30–May 10) Even before they were certain that oil was spilling into the Gulf, responders had readied planes full of dispersants to use in a potential response. Dispersants include surfactants that break down oil into smaller droplets, which are more likely to dissolve into the water column.103 On April 24, once Unified Command knew a leak existed and coastal impacts were possible, Admiral Landry told reporters: "We have one-third of the world's dispersant resources on standby. . . . Our goal is to fight this oil spill as far away from the coastline as possible."104 Faced with what one Coast Guard captain called a "tradeoff of bad choices" between spraying chemicals on the water or watching more oil reach the shore,105 responders would wield dispersants in the battle against oil for the next 12 weeks, using novel methods and unprecedented volumes.
¶Dispersants do not remove oil from the water altogether. Energy from wind and waves naturally disperses oil, and dispersants accelerate this process by allowing oil to mix with water. Dispersed oil is diluted as it mixes vertically and horizontally in the water column.106 Using dispersants has several potential benefits. First, less oil will reach shorelines and fragile environments such as marshes.107 Second, animals and birds that float on or wade through the water surface may encounter less oil.108 Third, dispersants may accelerate the rate at which oil biodegrades.109 Finally, responders to an oil spill can use dispersants when bad weather prevents skimming or burning. But dispersants also pose potential threats. Less oil on the surface means more in the water column, spread over a wider area, potentially increasing exposure for marine life. Chemically dispersed oil can be toxic in both the short and long term. Moreover, some studies have found that dispersants do not increase biodegradation rates—or may even inhibit biodegradation.110
¶At the direction of the Federal On-Scene Coordinator, responders first sprayed dispersants on the surface oil slick on April 22.111 Long before the spill, interagency "Regional Response Teams" had evaluated and preauthorized the use of specific dispersants in the Gulf of Mexico, with limits as to geographic areas where the chemicals could be applied, but not on overall volume or duration of use.112 The teams included representatives from relevant state governments and from federal agencies with authority over oil spills, including the Coast Guard, EPA, the Department of the Interior, and NOAA. Preauthorization, requiring the concurrence of the Team, allows the Federal On-Scene Coordinator to employ dispersants immediately following a spill.113 Timing matters, because the chemicals
144are most effective when oil is fresh, before it has weathered and emulsified.114 Without preauthorization, responders can still use dispersants during a spill if EPA and state authorities approve.115 With the permission of the Federal On-Scene Coordinator, BP and its contractors applied 14,654 gallons of the dispersant Corexit on the surface during the week of April 20 to 26.116
Under the terms of the preauthorization, Corexit was a permissible dispersant because EPA listed it on the National Contingency Plan Product Schedule. EPA obtains toxicity data from the manufacturer before placing a dispersant on that schedule.117 Some toxicologists have questioned the reliability and comparability of the testing by manufacturers.118 Moreover, the required testing is limited to acute (short-term) toxicity studies on one fish species and one shrimp species;119 it does not consider issues such as persistence in the environment and long-term effects.
Dispersant use increased during the first weeks of the spill. From April 27 to May 3, responders applied 141,358 gallons to the surface. The following week, they applied 168,988 gallons. The Coast Guard and other responders had often deployed dispersants to respond to spills, but never in such volumes; during the Exxon Valdez spill, responders sprayed about 5,500 gallons, and that use was controversial.120
Faced with high-volume dispersant use, Gulf residents became concerned that the chemicals were just as bad as the spilled oil itself. Some workers reported nausea and headaches after coming into contact with dispersants.121 However, OSHA found no evidence of unsafe dispersant exposure among responders.122 Environmental groups pressured Nalco, the company that manufactures Corexit, to disclose its formula. Although it had given the formula to EPA during the pre-listing process, Nalco declined to make the formula public, citing intellectual property concerns.123 This decision did not reassure the citizens of the Gulf.
As the volume of dispersants sprayed on the surface grew, BP raised the idea of applying dispersants directly at the well, rather than waiting for the oil to reach the surface a mile above.124 Responders had never before applied dispersants in the deep sea. Within Unified Command, some scientists were cautiously optimistic. They hoped that, in addition to reducing shoreline impacts, subsea application would mean less dispersants used overall, because they would be more effective in the turbulent subsea environment. Responders would later conclude that subsea dispersant application also helped to protect worker health by lowering the concentrations of volatile organic compounds at the surface.125
145But responders were concerned about the absence of information on the effects of dispersants in the deepwater environment. No federal agency had studied subsea dispersant use and private studies had been extremely limited.126 BP's Hayward was less than helpful; he told a British newspaper, "The Gulf of Mexico is a very big ocean. The amount of volume of oil and dispersant we are putting into it is tiny in relation to the total water volume."127 While federal officials did not possess the scientific information they needed to guide their choices, they had to make choices nevertheless.
¶From April 30 to May 10, scientists within Unified Command worked intensively to create a monitoring protocol for subsea dispersant use that would detect adverse environmental effects and provide criteria for when the use was appropriate. It was unclear whether the preauthorizations by the Regional Response Teams covered subsea dispersant use. EPA believed they did not and wanted to make decisions about such use at a high level within the agency. But it had trouble establishing clear and rapid communication, both internally and outside the agency.128 This slowed creation and review of the testing protocols, while Coast Guard responders and NOAA scientists chafed at the delay.
¶On May 10, after several rounds of testing and revision, EPA adopted a testing protocol created by NOAA and BP scientists as its directive regarding subsea dispersant use. The directive, as later amended by EPA, limited subsea application to 15,000 gallons per day and required monitoring and compliance with environmental toxicity guidelines.129 Administrator Lisa Jackson ultimately gave EPA's approval for subsea dispersant use and would later call it the hardest decision she ever made.130 Observed toxicity levels never exceeded the guidelines in EPA's directive, and responders continued to apply dispersants at the source until BP capped the well.
¶Deploying the Containment Dome (May 6–8) While scientists tried to determine if subsea dispersant use was even possible, BP engineers simultaneously worked to contain and recover oil until they could kill the well. Within days of discovering the leaks from the broken riser on the sea floor, they began to consider use of a large containment dome. The idea was to place the dome, also known as a cofferdam, over the larger of the two leaks, with a pipe at the top channeling oil and gas to the Discoverer Enterprise, a ship on the surface. BP already had several cofferdams, which it had used to provide safe working space for divers repairing leaks from shallow-water wells following Hurricanes Katrina and Rita.131 By May 4, BP had finished modifying for deep-sea use and oil collection a preexisting dome that was 14 feet wide,24 Testimony of Jimmy Harrell, Hearing before the Deepwater Horizon Joint Investigation Team, May 27, 2010, 77; Internal Transocean document (TRN-HCDC 92). U.S. Geological Survey, Monthly Engineering Reports Vol. 128 (December 1958) and Monthly Engineering Reports Vol. 144 (February 1960), RG 57, Records of the U.S. Geological Survey, NARA. Richard J. Lazarus, The Making of Environmental Law, (Chicago: University of Chicago Press, 2004), 70. 25 42 U.S.C. § 4332(c). The Well Site Leaders—Bob Kaluza and Don Vidrine—would normally have been on the rig. Morel, a relatively junior BP engineer, had flown to the rig out of a professional interest in learning more about the cementing process. Guide, interview. feet long, and 40 feet tall.132 Following an MMS inspection of the Discoverer Enterprise, BP began to lower the 98-ton dome to the sea floor late in the evening of May 6.133
¶The likelihood of collecting oil with the cofferdam was uncertain. BP's Suttles publicly cautioned that previous successful uses had been in much shallower water.134 BP recognized that chief among potential problems was the risk that methane gas escaping from the well would come into contact with cold sea water and form slushy hydrates, essentially clogging the cofferdam with hydrocarbon ice.135 Notwithstanding the uncertainty, BP, in a presentation to the leadership of the Department of the Interior, described the probability of the containment dome's success as "Medium/High."136 Others in the oil and gas industry were not so optimistic: many experts believed the cofferdam effort was very likely to fail because of hydrates.137
¶The effort did fail, for that reason. Although BP had a plan to deal with hydrates once the cofferdam was in place, it had not planned to mitigate hydrate formation during installation.138 When crews started to maneuver the cofferdam into position on the evening of May 7, hydrates formed before they could place the dome over the leak, clogging the
146opening through which oil was to be funneled.139 According to Richard Lynch, a vice president overseeing the effort, BP never anticipated hydrates developing this early.140
Because hydrocarbons are lighter than water, the containment dome became buoyant as it filled with oil and gas while BP tried to lower it. BP engineers told Lynch that they had "lost the cofferdam" as the dome, full of flammable material, floated up toward the ships on the ocean surface. Averting a potential disaster, the engineers were able to regain control of the dome and move it to safety on the sea floor.141 In the wake of the cofferdam's failure, one high-level government official recalled Andy Inglis, BP's Chief Executive Officer of Exploration and Production, saying with disgust, "If we had tried to make a hydrate collection contraption, we couldn't have done a better job."142
Inaccurate estimates of the well's flow also affected the cofferdam effort. According to Suttles, during this time, no one at BP believed the flow was greater than 13,000 to 14,000 barrels per day.143 The government's then-current estimate of the flow was 5,000 barrels per day. The far larger volume of the actual flow—about 60,000 barrels per day, according to the government's now-current estimate—may be part of the reason hydrates formed more quickly than expected.144 Moreover, BP had publicly predicted that the cofferdam would remove about 85 percent of the oil spilling into the sea.145 But the ship it planned to connect to the cofferdam was capable of processing a maximum of 15,000 barrels per day.146 While BP may have misjudged the probability of success, its decision to deploy the dome instead of another containment device appears to have turned more on timing than on perceived effectiveness: the dome was largely off-the-shelf and therefore ready to use in early May, before other equipment.147
With the failure of the cofferdam highlighting the shortage of viable options to contain and control the well, somewhat outlandish suggestions filled the void. In mid-May, a Russian newspaper suggested detonating a nuclear weapon deep within the well to stop the flow of oil, as the former Soviet Union had done on a number of occasions.148 BP moved on: a little over a week after giving up on the cofferdam, on May 16, it was able to deploy a new collection device. Named the Riser Insertion Tube Tool, the device was a tube, four inches in diameter, that fit into the end of the riser and carried oil and gas up to the Discoverer Enterprise. This tool, BP's first effective means of containment, collected approximately 22,000 barrels of oil over its nine days of use.
147Flow-Rate Estimates Creep Up (May 27) After Unified Command announced its best estimate of the flow rate as 5,000 barrels per day on April 28, a number of independent scientists began to register their disagreement. BP had contacted scientists at the Woods Hole Oceanographic Institution on May 1 about undertaking diagnostic work on the BOP and measuring the flow using a remotely operated vehicle with sonar and acoustic sensors. But BP cancelled the Woods Hole project on May 6 to instead deploy the containment dome.149 Based on satellite imagery of the surface slick, other non-government scientists arrived at estimates in late April and early May ranging from 5,000 to 26,500 barrels of oil per day.150 Using the appearance of oil on the surface to assess flow from a source 5,000 feet below is inherently unreliable, but the outside scientists had no other data. That changed on May 12, when BP released
¶a 30-second video of oil and gas streaming from the end of the broken riser. Within 24 hours, independent scientists had seized on this information and published three new estimates of the combined flow of oil and gas that ranged from 20,000 to 100,000 barrels per day.151 On May 18, BP released another video, this time of the leak at the kink. Combining estimated flow from the two sources, a non-government scientist, Steve Wereley, testified before Congress that approximately 50,000 barrels of oil per day were flowing into the Gulf.152
¶BP dismissed these new estimates, with spokesman Bill Salvin stating, "We've said all along that there's no way to estimate the flow coming out of the pipe accurately."153 The government disagrees with Salvin's claim: according to Marcia McNutt, Director of the U.S. Geological Survey, if a similar blowout occurs in the future, the government will be able to quickly and reliably estimate the flow rate using the very oceanographic techniques that Woods Hole was prepared to use on May 6.154* At the time, the government responded to the independent estimates by devoting greater resources to the question of flow rate. On May 19, the National Incident Command created an interagency Flow Rate Technical Group and charged it with generating a preliminary flow rate as soon as possible and, within two months, a final estimate based on peer-reviewed methodologies. On May 23, at Secretary Salazar's recommendation, the National Incident Command appointed McNutt the leader.
¶The Group consisted of both government and non-government scientists, and included subgroups using different methodologies. It published its first estimate on May 27, stating: "The only range of flow rates that is consistent with all 3 of the methods considered by the [the Group] is 12,000 to 19,000 barrels per day. Higher flow rates [of up to 25,000 barrels per day] are consistent with the data considered by [one subgroup]."155 The Group released little additional information about its calculations. A few days later, it issued a two-page report stating that the 12,000 to 25,000 barrel range represented the "lower bound" of one subgroup's estimates, and that this subgroup had chosen not to release its "upper bound" estimates, deeming them speculative because of "unknown unknowns."156
¶Responders uniformly contended that they were responding to the oil as it appeared on the water's surface, and that the problems with quantifying the flow from the source did not affect their ability to respond. In response to a congressional inquiry later in the summer about dispersant use, however, Admiral Allen indicated that early dispersant decisions were based on the 5,000 barrels per day figure, and that the higher estimate from the Flow Rate Technical Group "spurred responders to consider reassessing the strategy for the use of dispersants as well as other oil recovery methods."157
¶Later studies would conclude that 12,000 to 25,000 barrels a day was still a significant underestimate of the amount of oil streaming into the Gulf.
-
¶
- At the behest of the Coast Guard, Woods Hole used its sonar and acoustic technology on May 31 to gather data that later yielded a flow-rate estimate of 58,000 barrels per day. On June 21, Woods Hole, again with the support of the Coast Guard, collected source samples, which initially demonstrated that 43.7 percent of the total flow was oil, while the remainder was gas. (Woods Hole has since revised this figure to 42.8 percent.)
Top government officials work on source control out of BP's Houston headquarters. At center is Secretary of Energy Steven Chu, flanked by Secretary of the Interior Ken Salazar (right) and Director of Sandia National Laboratories Tom Hunter.
¶Unified Area Command, Deepwater Horizon Response
The Top Kill and Junk Shot (May 26–28) Throughout May, the federal government increased its presence in Houston, the hub of the well-control effort. In early May, scientists and engineers from three Department of Energy national laboratories began to work on-site with BP on containment. On May 7, Secretary Salazar asked McNutt, who had traveled to the Gulf with him on May 4, to remain in Houston. Finally, on May 10, President Obama directed Secretary Chu to form a team of government officials and scientists to work with BP on source control.158 On May 11, Secretary Chu called several prominent scientists and asked them to join him the next morning for a meeting in Houston.159
The May 12 meeting signified the beginning of an oversight role for Secretary Chu and his team of science advisors. Secretary Chu is a Nobel Prize-winning physicist who had previously directed the Lawrence Berkeley National Laboratory, where he had led an effort to expand research into synthetic biofuels.160 Though well known for his wide-ranging intelligence, Secretary Chu was not an oil and gas or drilling expert. During the following weeks, he immersed himself in the finer points of petroleum engineering and became intimately involved in decisionmaking with respect to containment of the well.
149Although they were highly respected within their fields of study, the members of the advisory team had limited experience with well control and varying levels of experience with petroleum engineering generally. Secretary Chu assumed—correctly—that BP had
¶already hired a host of containment experts, and he wanted advisors known for creative thinking. His principal deputy on the team, Tom Hunter, was about to retire from his position as Director of Sandia National Laboratories. Along with McNutt, Hunter served as a link between the on-site government scientists and engineers and the rest of Secretary Chu's science advisors, who were for the most part based elsewhere. Another team member, Richard Garwin, helped design the world's first hydrogen bomb and had worked to extinguish oil fires in Kuwait following the first Gulf War. Alexander Slocum, an MIT professor who holds about 70 patents, had done some previous work on drilling design. George Cooper had been the head of the Petroleum Engineering Program at the University of California, Berkeley.
¶The role of both the national laboratories scientists and Secretary Chu's advisors took time to evolve from helping BP diagnose the situation—for instance, using gamma-ray imaging to show the position of the BOP's rams—to substantively overseeing BP's decisions on containment. In part, this was because the Secretary of Energy, his team of advisors, and the national laboratories personnel lacked a formal role within Unified Command. Their supervision was informally grafted onto the command framework.
¶In addition, the national laboratories team did not immediately integrate itself into the existing source-control structure, led by MMS and the Coast Guard. While MMS, the Coast Guard, and McNutt worked out of offices on the third floor of BP's Houston headquarters, the national laboratories team sat on the eighteenth floor.161 One MMS staff member who was in Houston from late April through early July said that he never interacted with the national laboratories team: they never reached out to him, and he had no idea what they were working on. Perhaps because the lines of authority were unclear, BP's sharing of data with the government science teams was uneven at first. BP gave information when asked, but not proactively, so government officials had to know what data they needed and ask for it specifically.162 Finally, both the national laboratories team and the science advisors had to educate themselves on the situation, and on deepwater petroleum engineering, before they knew enough to challenge BP and participate in high-level decisionmaking.163
¶With more substantive government oversight on the way but not yet in place, BP moved toward its first attempt to kill the well completely, via procedures called the "top kill" and "junk shot." Those names were fodder for late night comics: Jay Leno suggested that the top kill "sound[ed] like some bad Steven Seagal movie from the '80s."164 In fact, both procedures are standard industry techniques for stopping the flow from a blown-out well (though they had never been used in deepwater165). A top kill—also known as a momentum or dynamic kill—involves pumping heavy drilling mud into the top of the well through the BOP's choke and kill lines, at rates and pressures high enough to force escaping oil back down the well and into the reservoir. A junk shot complements a top kill. It involves pumping material (including pieces of tire rubber and golf balls) into the bottom of a BOP through the choke and kill lines. That material ideally gets caught on obstructions within the BOP and impedes the flow of oil and gas. By slowing or stopping the flow, a successful junk shot makes it easier to execute a top kill.
150BP's top-kill team began work in the immediate aftermath of the initial efforts to trigger the BOP.166 In planning the operation, both BP and federal engineers modeled different scenarios based on different rates at which oil might be flowing from the well. National laboratories engineers used the then-current flow-rate estimate of 5,000 barrels per day.167 Paul Tooms, BP's Vice President of Engineering, recalled that given the planned pumping rates, the top kill was unlikely to succeed with flow rates greater than 15,000 barrels of oil per day.168 A senior administration official similarly recalled being told by a BP engineer that the top kill would not work if the flow rate exceeded 13,000 barrels per day.169
With the approval of the Federal On-Scene Coordinator, the top kill began on the afternoon of May 26. Secretary Chu and some members of his science team were in the command center in Houston.170 During three separate attempts over three consecutive days, BP pumped mud at rates exceeding 100,000 barrels per day and fired numerous shots of junk into the BOP.171 During each effort, pressures within the well initially dropped, but then flattened, indicating that the top kill had stopped making progress.172 After the third unsuccessful attempt, BP and the government agreed to discontinue the strategy.173
As with the cofferdam, BP struggled with public communications surrounding the top kill. At the time, both industry and government officials were highly uncertain about the operation's probability of success. One MMS employee estimated that probability as less than 50 percent, while a BP contractor said that he only gave the top kill a "tiny" chance to succeed.174 But BP's Hayward told reporters, "We rate the probability of success between 60 and 70 percent."175 After the top kill failed, that prediction may have lessened public confidence in BP's management of the effort to control the well.
The Federal Role Increases (Late May) By late May, the competence and effectiveness of the federal response was under assault. Polls showed that 60 percent of adults thought the government was doing a poor job of handling the spill.176 News articles chronicled local anger that BP appeared in charge of clean-up efforts.177 The government's estimate of the flow rate was climbing and, with the failure of the top kill, no end to the spill was in sight.
On May 28, President Obama made his second trip to the region to see response efforts and meet with state and local leaders. Plaquemines Parish President Billy Nungesser would later claim, incorrectly, that he had not been invited to this important meeting.178 He told the Plaquemines Gazette that he had smuggled himself and another Parish President across bays and bayous and through an armada of state boats, gaining access only after threatening to call Anderson Cooper.179
151The meeting with the President occurred at the Coast Guard station in Grand Isle, Louisiana, and included, among others, Governor Jindal, Florida Governor Charlie Crist, Alabama Governor Bob Riley, Louisiana Senators David Vitter and Mary Landrieu, Louisiana Congressman Charlie Melancon, New Orleans Mayor Mitch Landrieu, Lafourche Parish President Charlotte Randolph, and Parish President Nungesser.180 President Obama emphasized the seriousness with which the government was treating the spill, announcing at a press conference after the meeting that he would triple the federal manpower and
¶equipment involved in the response.181 Though Coast Guard responders believed they were already dedicating every available resource to the spill, and did not see across-the-board "tripling" as the best use of resources, they dutifully attempted to triple the personnel engaged and boom deployed. They chronicled their progress in Louisiana in a report titled "Status on Tripling."182
Under fire, President Barack Obama meets with dissatisfied state and local officials in Grand Isle, Louisiana on May 28, during his second visit to the Gulf since the spill began. Visible clockwise from the President: Plaquemines
¶While in Grand Isle, President Parish President Billy Nungesser, Louisiana Governor Bobby Jindal, New
¶Orleans Mayor Mitch Landrieu, Grand Isle Mayor David Camardelle, and Florida Obama also received an "earful" Governor Charlie Crist. about Louisiana's proposal to build
¶David Grunfeld/The Times-Picayune. Photo © 2010 The Times-Picayune massive offshore sand berms as Publishing Co., all rights reserved. Used with permission of The Times-Picayune.
¶a physical obstacle to oil, which the National Incident Command had declined to approve in its entirety.183 Parish President Nungesser, seated immediately to the President's left, was the first attendee to speak at the meeting and was adamant about the need for the entire berms project. Governor Jindal echoed him. In line with the federal government's effort to be more responsive to local demands, President Obama turned to Admiral Allen and asked him, in front of the berms' strongest proponents, to figure out a solution.184
¶The "tripling" order and promise to promptly reevaluate the berms project were only two of many actions at the end of May by which the federal government attempted to demonstrate its focus on the Deepwater Horizon disaster and commitment to the communities in the Gulf. The President signed the Executive Order creating this Commission on May 21.185 On May 27, he announced a moratorium on offshore deepwater drilling and held a press conference about the administration response.186 The same day, Elizabeth Birnbaum, the head of MMS, resigned—"on her own terms and on her own volition," according to Secretary Salazar.187 Most symbolically, the federal government stopped holding joint press conferences with BP. From June 1 on, Admiral Allen gave his own daily press briefing.188 But local officials continued to attack the adequacy of the federal response and to assert that that BP was running the response effort.
¶The Battles over Boom and Berms (May to June) While the response had many dimensions, local communities fixated on the deployment of boom to prevent oil from washing ashore. Although not the most effective response tool, boom is a measurable, physical object that visibly stops oil. Residents could not see source-control efforts on the ocean floor or skimming far out in the Gulf, but they could see boats laying ribbons of bright orange or yellow floating boom to protect their shorelines. According to one Terrebonne Parish resident, boom was eye candy—seeing it gave him a sense of satisfaction (even if it did not do much).189
152The Moratorium On May 27, after a 30-day interagency examination of deepwater drilling operations, Secretary Salazar directed MMS to issue a six-month moratorium on all drilling at a water depth of more than 500 feet in the Gulf of Mexico and the Pacific Ocean. Department officials justified the moratorium as providing time for this Commission to do its work and for MMS to undertake needed safety reforms. The moratorium took effect on May 30 and halted work on 33 offshore deepwater rigs in the Gulf.
The oil and gas industry, local communities, and elected officials from the region immediately criticized the action. Senator Landrieu testified before this Commission in July that the moratorium was "unnecessary, ill-conceived and has actually created a second economic disaster for the Gulf Coast that has the potential to become greater than the first." On July 30, BP established a $100 million charitable fund to assist rig workers experiencing economic hardship because of the moratorium.
The federal government concluded that the moratorium's impact would be less severe. On September 16, a federal interagency report stated that the moratorium "may temporarily result in up to 8,000 to 12,000 fewer jobs in the Gulf Coast," with these losses attributed mostly to small businesses. Louisiana elected officials criticized the report's methodology and the decision to conduct this analysis after, instead of before, the moratorium began.
A group of companies that provide support services for deepwater drilling vessels challenged the moratorium in federal district court in Louisiana. On June 22, the court ruled that the moratorium violated the Administrative Procedure Act and enjoined its continued enforcement. The federal government asked the Fifth Circuit Court of Appeals to stay the district court's ruling, but the Fifth Circuit denied that request on July 8. The Department of the Interior then issued a revised moratorium on July 12, which limited drilling based on the equipment a rig used rather than the depth of the wellhead. Neither the first nor the second moratorium provided a company with the option of avoiding the bar on drilling by proving the safety of its rig operations to the government. A second group of offshore support companies challenged the revised moratorium. Before the district court could rule on this new lawsuit, the Department lifted the moratorium on October 12, seven weeks ahead of its scheduled November 30 expiration.
153On September 30, a few weeks before lifting the moratorium, the Department promulgated new regulations on topics such as well casing and cementing, blowout preventers, safety certification, emergency response, and worker training. Compliance with the new rules is a prerequisite for both shallow and deepwater drilling permits. Some companies called these new requirements a "de facto moratorium" because of the time needed to meet them and for the Department to verify compliance.
¶A vessel places containment boom in Louisiana's Barataria Bay. Hundreds of miles of boom were deployed along the Gulf coast, but politicians clamored for more of the highly visible barriers.
¶U.S. Coast Guard photo/Petty Officer 3rd Class Ann Marie Gorden
¶Boom became a symbol of federal responsiveness to local communities. NOAA scientists worked through the night, every night, to prepare oil trajectory forecasts for federal responders to review as they began their days.190 Responders used those forecasts to plan their actions, including where to place boom. Federal responders thought that officials and residents complaining about lack of boom did not understand their strategy for deployment; officials and residents thought that federal responders were inattentive to local needs.191 The National Incident Command was not deaf to these complaints and gave an unofficial order to "keep the parishes happy."192 Coast Guard responders distributed many miles of boom according to political, rather than operational, imperatives. They felt hamstrung by the outrage that resulted when a parish or state felt slighted by allocation decisions, so they placed boom wherever they could.193
¶Every Governor wanted more boom. When the oiling risk was highest in Louisiana, the Coast Guard directed boom there. Governor Riley of Alabama contended that this decision left his state's shoreline in danger.194 At a press conference in mid-May, Governor Jindal said that the containment boom provided to Louisiana by the Coast Guard and BP was inadequate, while local officials behind him held up pictures of oil-coated pelicans.195 Florida Department of Environmental Protection Secretary Mike Sole told reporters, "A lot of the decisions about Florida are being made in Mobile." He said he had warned the Federal On-Scene Coordinator, "Florida is important. We have 770 miles of shoreline to protect. I'm concerned that we're not getting enough focus on Florida."196
154The competition for boom occurred at the parish and town levels as well. St. Bernard Parish had its own contractor bring in boom; it then sought to make the Coast Guard purchase and deploy that boom locally.197 Some parishes reportedly ordered boom directly from suppliers and told them to "send the bill to BP."198 Lafourche Parish kept demanding more boom—until it realized that certain skimmers were more effective and began demanding those skimmers instead.199 Unified Command struggled to track how much boom was deployed and where.
Initially, responders made booming decisions based on their knowledge of the region's geography, the location of environmentally sensitive areas, and NOAA's oil trajectory forecasts. The oil-spill planning documents did not lay out a specific booming map, because the coastal ecosystem, particularly in the marshes, frequently changes. Unified Command eventually brought the Parish Presidents together to review boom plans that each parish had created. Some were infeasible—for instance, requesting that boom be placed in tidal passes where currents would drive oil under the boom or else damage it. In addition to worrying about useless or unnecessary boom, responders were concerned that storms could blow it into delicate marsh habitat. They deployed boom based on local pressures only to pull it away during bad weather.200
Once parishes had boom, they did not want to let it go. On July 22, Parish President Nungesser threatened to blow out the tires of trucks carrying away boom as the Coast Guard prepared for Tropical Storm Bonnie. Though he claimed that he was joking, the FBI called to reprimand him.201 Other Parish Presidents issued orders prohibiting the removal of response equipment from their parishes and threatened Coast Guard responders with arrest.202 Officials asked responders to measure "feet of boom deployed"—a statistic that was time-consuming to generate and had little value in assessing response efforts.203 All of these problems distracted responders from their focus on cleaning up the spill.
The boom wars never reached a resolution. Responders knew that in deploying boom they were often responding to the politics of the spill rather than the spill itself. And the miles of boom along the coastline still did not prevent oil from washing up on the shore.
The boom wars were relatively civil, however, compared to the struggle among the State of Louisiana, the Army Corps of Engineers, the National Incident Command, and, ultimately, the White House over berms. Reinforcing barrier islands had long been a component of Louisiana's and Plaquemines Parish's coastal restoration plans.204 But by early May, Governor Jindal and Parish President Nungesser had seized on an idea (originally proposed by Deltares, a Dutch independent research institute, together with Van Oord, a Dutch dredging and marine contractor) to construct massive, linear sand berms along Louisiana's barrier islands for spill response, to guard the coastline from oil.205 The berms project presented an opportunity for Louisiana to take the lead on a large-scale response measure—with BP footing the bill. Moreover, after the spill ended, the berms' purpose could "pivot" from response to coastal restoration.206
155On May 11, Louisiana's Office of Coastal Protection and Restoration applied to the Corps for an emergency permit to construct berms to "enhanc[e] the capability of the islands to
¶"If I was a mom, what would I do?"
Sheryl Lindsay, Orange Beach Weddings, Orange Beach AL
When Sheryl Lindsay picked up the April 21 Mobile Press-Register and read the headline, "At least 11 workers sought after gulf rig explosion," she recalled, "My heart went out to the workers on that rig, the victims and their families. I couldn't believe what had happened." The newspaper reported that six of the Deepwater Horizon survivors had been flown to a Mobile, Alabama, trauma unit.
¶Michelle Rolls-Thomas/Associated Press
¶For six years, Lindsay had been president of Orange Beach Weddings, which coordinated and arranged "The Wedding of Your Dreams" on Alabama's Gulf Coast near the Florida line. Her offices on Perdido Boulevard overlooked the pristine white sand beaches of Orange Beach, Alabama—one of her firm's specialties was elegant beach ceremonies and festivities. Her busy season was starting, with 73 weddings booked for 2010. She worked with numerous contractors, from wedding planners and caterers to ministers and photographers. She knew that BP's Macondo well was now spewing oil; "But I never thought it would affect us here."
¶On April 30, the day after the U.S. Coast Guard declared the Macondo blowout a "spill of national significance," Lindsay was in her office when the phone rang. It was her first cancellation. "When the bride called to cancel, she said it was because of the spill. She didn't want her guests coming down to find oil on the beaches. She didn't want to come if they couldn't swim or eat the seafood. That's when I knew."
¶In the wake of the oil spill, "Every time the phone rang, all we got was another cancellation—or someone asking how bad it was down here. I became a counselor for these brides. Orange Beach is a popular spot for destination weddings, and many of my brides come from out of state. But if girls' weddings were still a few months out, they still had time to change plans and move the wedding somewhere else. A lot of girls asked me what they should do—they were worried about the smell, whether the guests could swim and the quality of the seafood." She continued, "This was their big day. It was tough. And you think, 'If I was a mom, what would I do?'"
¶"What's funny," Lindsay said, "is we only had about three bad weeks where oil was washing on shore and BP was staging clean-up on the beach. That was in June. The rest of the summer the beaches were pretty much clean but folks still didn't come down." As the spill gushed on, Lindsay began to realize she had no idea what the next year would look like, but it didn't look good. She did not think she could afford to renew her office lease. In 2009, she had taken out a small business loan from the local bank for $55,000 to expand her firm, but now she began to fear she could not meet those payments as her business diminished.
156reduce the inland movement of oil from the BP Deepwater Horizon Oil Spill."207 Colonel Alvin Lee, two months shy of the end of his three-year tour as the Commander of the Corps for the District of New Orleans, cancelled a long-scheduled vacation, and the Corps immediately sought comments on the proposal from relevant federal and state agencies.208
The patience of Louisiana officials quickly wore thin. On May 17, Governor Jindal's office summoned Colonel Lee to the New Orleans airport for a meeting that included three Parish Presidents, the Chairman of the Office of Coastal Protection and Restoration, the Adjutant General for Louisiana, and the Governor himself. The group's message to Colonel Lee was clear: approve the berms project, and do it quickly.209 The entire Louisiana congressional delegation wrote Colonel Lee on May 20, to "implore [him] to immediately approve the emergency authorization request" for the Louisiana berms.210 In a May 21 letter to President Obama, Senator Vitter asked the President to stop the "tragic bureaucratic stranglehold" and to "make this happen now."211
The Corps reviewed agency comments, conducted its own evaluation of the project, and engaged in dialogue with state officials. On May 27—just 16 days after it had received Louisiana's application—the Corps approved the issuance of an emergency permit for a significantly scaled-back berms project: six "reaches" totaling 39.5 miles in length.212 During the review process, commenting agencies expressed skepticism that the berms could be constructed in time to be effective for spill response and concern that partially completed berms would do more environmental harm than good.213 The Corps' job, however, was to analyze the "feasibility and environmental impacts" of the berms. The National Incident Commander had the task of determining whether the berms would be "effective. . . in combating the oil spill."214 That determination was necessary to make BP pay for the project as a response measure.
The same day the Corps approved the six reaches, Admiral Allen authorized one of the six as a prototype oil-spill response mechanism.215 Earlier in May, an interagency task force had advised the National Incident Command that the project would not be an effective spill-response measure, in part because the berms could not be constructed in time to fight the spill.216 But public and political pressure had been unyielding. In an attempt to balance both sets of concerns, on May 22, Admiral Allen e-mailed an idea to his deputy: "What are the chances we could pick a couple of no brainer projects and call them prototypes to give us some trade space on the larger issue and give that to Jindal this weekend?"217 Five days later, the National Incident Command announced its approval of one prototype berm, to cost $16 million.218 The accompanying press release promised that additional berms could be constructed if the approved section proved effective. Building even one prototype segment would take months, however, and the segment would then need to be analyzed. Any further construction therefore would not begin until the fall.
157But because of the meeting in Grand Isle on May 28, where Parish President Nungesser and Governor Jindal urged President Obama to approve the entire project, the National Incident Command would change course. At the meeting, the President turned to Admiral Allen and, in front of the assembled Governors and other leaders, asked him to assemble a group of experts to examine the merits of Louisiana's proposal as a spill-response measure.
¶Admiral Allen replied that this might take some time. It was the Friday afternoon before Memorial Day weekend. But the President pushed, asking, "Can you do it next week?" Admiral Allen, put on the spot, pledged to do his best.219
¶After the meeting, Governor Jindal immediately announced that the President had "agreed that work on the first segment must begin immediately" and that the federal government would decide "within two to three days" whether the additional five segments should proceed.220 Parish President Nungesser told a similar story to Anderson Cooper on CNN that evening, saying "The President committed by early next week, we will have an answer and I believe that he's going to task BP."221
¶On June 1, Admiral Allen convened a summit in New Orleans "which included members of academia [one from Louisiana State University and a second from the University of New Orleans], federal trustees, fish and wildlife service and NOAA," as well as Governor Jindal and Parish President Nungesser. Although some experts at the summit expressed concern about causing harm to the environment, the discussion focused on the berms' potential to protect marshlands.222 The politics of the project remained close at hand: Parish President Nungesser walked out, calling the meeting a "Dog and Pony Show,"223 only to return in time to speak at the end. Governor Jindal continued to express his frustration and pressed for approval of all six reaches covered by the Corps permit.224 In the face of the spill and in front of the Louisiana politicians, no one directly opposed the berms, and a "preponderance of opinion" at the summit suggested the berms would be an effective response measure.225
¶That evening, following the summit, Admiral Allen and BP's Hayward had dinner together in New Orleans to discuss the berms.226 The following afternoon, Admiral Allen gave the go-ahead to all six reaches approved by the Corps, to be funded by BP.227 BP estimated the cost to be $360 million, double the entire amount it had spent as of early June in "helping the region respond to the oil spill."228 The Corps pegged the cost at $424 million.229
¶Louisiana awarded contracts for the project to Shaw Group, a Baton Rouge-based engineering, construction, and environmental services firm, and C.F. Bean LLC, a dredging contractor based in Plaquemines Parish.230 Shaw estimated that five of the six berm reaches would be completed by November 1, and that the sixth would be completed by the end of November.231 The National Incident Command estimated that the construction time for all six reaches would be six to nine months.232 Even if those estimates had been correct, the project would have been nowhere close to complete by the time the government expected BP to kill the Macondo well with a relief well. As it happened, all of the estimates were far too rosy. Only a fraction of the planned reaches would be finished before the spill ended, and very little oil would be captured.
¶From Containment to Collection (Late May to Early July) Following the unsuccessful top kill, BP teams in Houston met through the night of May 28 to assess the operation.233 Some meetings occurred behind closed doors, without government participation. At one point, Herbst of MMS and Admiral Kevin Cook, who had been dispatched by Admiral Allen to be his representative in Houston, entered a meeting and stated that they had a right to be present. Apparently, government officials
158had not previously insisted on joining these types of meetings, and BP personnel were surprised by the interruption.234 The failure of the top kill marked a turning point for the government science teams, with the government significantly increasing its oversight of the containment effort.
The next morning, BP presented its analysis of why the top kill failed to stop the flow of oil. The analysis focused on the well's 16-inch casing, the outermost barrier between the well and the surrounding rock for more than 1,000 vertical feet. That casing was purposely fabricated with three sets of weak points, called rupture disks. During the well's production phase, the hot oil coursing through the production casing, which is inside the 16-inch casing, would lead to a buildup of pressure in the well. If the pressure buildup was too high, it could cause the collapse of one of the two casings. The disks were designed to rupture and relieve this potential buildup of pressure before a casing collapsed.
The disks could rupture in two ways. If pressure between the 16-inch casing and the production casing were too high, the rupture disks would burst outward before the production casing collapsed. If pressure outside the 16-inch casing were too high, the rupture disks would collapse inward before the casing itself collapsed.235 Once ruptured, the disks would create small holes in the 16-inch casing, bleeding built-up pressure off into the rock. According to BP's top-kill analysis, pressures created by the initial blowout could have caused the rupture disks to collapse inward, compromising the well's integrity.236 BP believed that the mud it had pumped down the well during the top kill could have gone out into the rock through the rupture disks, instead of staying within the well and pushing oil back down into the reservoir as intended.237
Collapse of the rupture disks was only one of BP's possible explanations for the unsuccessful top kill.238 But the company presented it to the government as the most likely scenario.239 Although the government science teams did not fully accept BP's analysis of what happened to the mud, they agreed that the rupture disks could have collapsed during the blowout, and that the integrity of the well had to be considered in future containment efforts.240 In retrospect, government officials have suggested that the top kill likely failed because the rate at which oil was flowing from the well was many times greater than the then-current 5,000 barrels-per-day estimate. Because BP did not pump mud into the well at a rate high enough to counter the actual flow, oil and gas from the well pushed mud back up the BOP and out of the riser.241
159BP had previously said that, if the top kill failed, its next step might be to install a second BOP on top of the existing one to shut in the well.242 But now, the company engineers viewed the possibility that the rupture disks had collapsed as a reason to discard capping the well as an option.243 If BP shut the well in, oil and gas could flow out the rupture disks and into the rock surrounding the well in a "broach" or "underground blowout." From there, the hydrocarbons could rise through the layers of rock and flow into the ocean from many points on the sea floor. This would make containment nearly impossible, at least until the completion of a relief well. Thus, in the aftermath of the top kill, BP and the government focused on trying to collect the oil, with the relief wells still providing the most likely avenue for killing the well altogether.244
¶Transocean's huge drill ship the Discoverer Enterprise, its derrick towering 400 feet above the sea, and Helix's Q4000 (foreground) sit over the gushing wellhead. Together the vessels were able to recover up to 25,000 barrels of oil per day.
¶Julie Dermansky ©2010
¶BP had a team ready to proceed with new collection tools almost immediately.245 On May 29, the company and the government announced that BP would attempt to cut off the portion of the riser still attached to the top of the BOP and install a collection device—the "top hat"—which would then be connected via a new riser to the Discoverer Enterprise above.246 BP began installing the device on June 1, and had the top hat in place and functioning by 11:30 p.m. on June 3. Having learned from its cofferdam experience, BP injected methanol to prevent formation of hydrates. By June 8, the Discoverer Enterprise was collecting nearly 15,000 barrels of oil per day.
¶BP also developed a system to bring oil and gas to the surface through the choke line on the BOP. BP outfitted the Q4000, a vessel involved in the top-kill effort, with collection equipment, including an oil and gas burner imported from France. After it became operational on June 16, the Q4000 system was able to process and burn up to 10,000 barrels of oil per day.*
¶On occasion, BP was overly optimistic about the percentage of the oil it could remove or collect. On June 1, Suttles said that he expected the top hat, when connected to the Discoverer Enterprise, to be able to collect the "vast majority" of the oil.247 Within days, it became apparent that the top hat and Discoverer Enterprise were inadequate. On June 6, Hayward told the BBC that, with the Q4000 in place, "we would very much hope to be containing the vast majority of the oil."248 But when the Q4000 came online in mid-June, the two vessels' joint capacity of 25,000 barrels per day was still insufficient.
¶Over the course of June and early July, BP worked on further expanding its containment system, which it asserted would eventually be able to collect up to 90,000 barrels of oil per day. BP never used the complete system, based around two freestanding risers connected to the choke and kill lines on the BOP, because it succeeded in capping the well on July 15.
160It is unclear whether BP could have increased its collection capacity more rapidly than it did. BP's Lynch said that the speed at which the company brought capacity online was limited solely by the availability of dynamically positioned production vessels.* One senior Coast Guard official challenged BP's definition of availability: he suggested that BP did not consider options such as procuring ships on charter with other companies until the government pushed it to do so. Obtaining another production vessel might have enabled BP to collect oil through the BOP's kill line at a rate comparable to that of the Q4000.249
Continued Conflict about Dispersant Use (May 10–July 14) Because of the insufficient collection capacity, oil continued to flow into the Gulf. Though the subsea use of dispersants proved helpful in preventing huge surface slicks, it did not initially have the predicted effect of reducing the total volume of dispersants applied. At a May 24 press conference, EPA Administrator Jackson announced that the government was instructing BP to "take immediate steps to significantly scale back the overall use of dispersants" and expressed EPA's belief that "we can reduce the amount of dispersant applied by as much as half, and I think probably 75 percent, maybe more."250 A Coast Guard–EPA letter and joint directive issued two days later instructed BP to "eliminate the surface application of dispersants," except in "rare cases when there may have to be an exemption."251
Despite this directive, surface use of dispersants continued. When surveillance aircraft spotted oil and no other method of cleaning it up was available in the area, BP would ask for an exemption from the Federal On-Scene Coordinator, who would then seek EPA's approval. The Coast Guard could not unilaterally allow the exemption; EPA had the final vote.
EPA expressed frustration that BP sought regular exemptions, and it repeatedly asked for more robust explanations of why BP could not use mechanical recovery methods, such as skimming and burning, instead of dispersants.252 Coast Guard responders, who viewed dispersants as a powerful tool to protect the coastline, wondered why EPA wanted to cast aside the advance planning that went into the preauthorization of surface dispersant use.253
These different perspectives on dispersants led to conflicts between EPA and the Coast Guard. For example, on June 7, BP requested permission to spray dispersants on several large slicks. Despite Federal-On Scene Coordinator Rear Admiral James Watson's statement that he had "determined aerial dispersant the best and only way to mitigate the pending landfall effect of the oil spotted," EPA would not approve the exemption.254 The Coast Guard captain leading the majority of front-line operations was furious. "It would be a travesty," he wrote, "if the oil hits the beach because we did not use the tools available to fight this offshore. This responsibility needs to be placed squarely in EPA's court if it does hit the shoreline."255 Later that day, without having received responses to its requests for additional data, EPA threatened to issue a directive "to stop the use of all dispersants."256
161Dynamically positioned vessels have computer-controlled systems that maintain the vessel's exact position and direction, despite external factors such as wind, waves, and current.
¶The working relationship between the agencies improved over time, with more complete justifications for dispersant use included in the daily requests for exemptions.257 But disagreements came to a boil again in mid-July. By this point, EPA had finally installed a senior official, Assistant Administrator for Solid Waste and Emergency Response Mathy Stanislaus, on the ground at Unified Area Command.258 On July 13, BP's head of dispersant operations made a request to apply 10,000 gallons to slicks.259 The request ultimately went to Stanislaus, who denied it, noting that skimming in particular had been extremely effective over the past few days.260 The Federal On-Scene Coordinator (by this time Rear Admiral Paul Zukunft) replied that he could not "take the dispersant tool out of my kit when" oil threatened to hit environmentally sensitive areas in Louisiana. "We spent over a month cleaning Barataria Bay with over 1500 people and 600 vessels," he added, "and still incurred significant wildlife kills while exposing these clean-up crews to extreme heat conditions. That is the trade-off option where dispersants come into play. . . ."261 The back-and-forth continued, with BP ultimately prohibited from using dispersants on July 14.262 The capping of the well the next day tabled the conflict.
¶Months later, Admiral Allen and Administrator Jackson would say that they had cooperated closely, nearly attained the goal of a 75 percent reduction in dispersant use, and were satisfied with the use of dispersants to mitigate the spill.263
¶The Well Is Finally Capped (Late June to July 15—and Beyond) Meanwhile, in Houston, the government continued to develop a more effective structure for oversight of well control. The basic elements of the structure were in place by mid- May, and the roles of the different government teams were better defined by mid-June. MMS and the Coast Guard continued to focus on identifying hazards in BP's technical procedures; personnel from the national laboratories and the U.S. Geological Survey provided information and analyses to the science advisors and BP; and the science advisors conducted their own independent analyses and helped inform the government's ultimate decisionmakers, including Secretary Chu, Secretary Salazar, McNutt, Hunter, Carol Browner (Director of the White House Office of Energy and Climate Change Policy), and Admiral Allen.264
¶Following the failure of the top kill, BP began presenting its source-control plans for review by these government teams. The science advisors would question BP's assumptions, forcing it to evaluate worst-case scenarios and explain how it was mitigating risks.265 The government saw its pushback as essential because BP would not, on its own, consider the full range of possibilities.266 According to one senior government official, before the increased supervision, BP "hoped for the best, planned for the best, expected the best."267 BP often found the supervision frustrating. Tooms, BP's Vice President of Engineering, believed that the government science advisors unnecessarily slowed the containment effort, arguing that scientists consider risk differently than engineers and that BP had expertise in managing risk.268 BP, however, was not in the best position to tout that expertise: its well had just blown out.
¶In mid- to late June, the government teams also began to seek more frequent input from other oil companies, primarily through large conference calls of 30 or more people.
162Although BP had previously turned to others in industry for advice, it had generally asked discrete questions about aspects of source control. The government teams, by contrast, asked other companies to comment on BP's overall plans and to help force BP to consider contingencies. BP, which believed its competitors suffered from a conflict of interest, did not appreciate the increased industry involvement. After one meeting in which BP's competitors aggressively challenged its plans, BP refused to meet with them again, forcing the government teams to schedule separate meetings.269
The conference calls were somewhat disorganized, with no agenda and participants sometimes not knowing who was speaking. One industry participant recalled an instance when he was chagrined to learn he had been talking to Secretary Chu without realizing it.270 A senior government official noted that some colleagues viewed BP's conflict-of- interest concerns as valid and took the competitors' advice "with a grain of salt."271 But government personnel generally found the industry participation helpful.
The science advisors' oversight increased substantially during June. On June 18, Secretary Chu sent an e-mail to the advisory team as well as some national laboratories scientists, describing their expanded role. The e-mail cited a scene from the classic World War II movie The Guns of Navarone, and quoted the character played by Gregory Peck: "[Y]our bystanding days are over! You're in it now, up to your neck! They told me that you're a genius with explosives. Start proving it!" Recognizing that there were "[p]robably no shaped charges to be used on this mission," Secretary Chu wrote that "the rest rings true." He enclosed a directive that Admiral Watson, the Federal On-Scene Coordinator, would issue the next day, formally requiring BP to submit any "pending decision" on containment to the government "for review."272
The role of the science advisors and the on-site scientists increased just as the source-control effort approached a critical phase. By late June, BP was well on its way toward deploying a "capping stack," which, once installed on top of the BOP, would enable BP to shut in the well. The capping stack was essentially a smaller version of a BOP, similarly designed to stop the flow of oil and gas. BP had internally discussed installing a tight- sealing cap within a week of the blowout.273 Following the top kill, however, BP and the government had shelved the idea of shutting in the well, in part because of concerns that the rupture disks in the well's 16-inch casing had collapsed, potentially allowing oil to flow out of the well into the rock. The government and BP had to take these concerns into account when planning for use of the capping stack.
163Secretary Chu and Hunter briefed the President on the capping stack in late June or early July, and he approved its use. The government appears to have delayed installation for a few days, however, to continue analyzing the significant risks of shutting in the well.274 One critical analysis involved the geology surrounding the Macondo well. The government's scientific Well Integrity Team concluded that it would take a total of approximately 100,000 barrels of oil flowing through the rupture disks into the surrounding rock for oil to create paths through the rock to the sea floor. The Team further concluded that such paths were likely to close or "heal" if BP and the government detected oil flow into the rock and reopened the capping stack with sufficient speed. To spot any
¶"This unnatural, unnatural catastrophe. . . ."
Al & Sal Sunseri, P&J Oyster Company, New Orleans, LA
Al and Sal Sunseri are co-owners of P&J Oyster Company, their family's 134-year-old business in the French Quarter of New Orleans. P&J processes and sells some 60,000 Louisiana oysters to the city's best restaurants and local oyster bars on a typical day. When Al first heard about the Deepwater Horizon rig accident, he recalled thinking, "'What a terrible thing for those people.'" He added, "I didn't think more about it because the Coast Guard and everyone said it would be limited."
¶The Louisiana Seafood Marketing and Promotion Board
¶Al's routine remained unchanged in the days after the Deepwater Horizon blowout and fire: early mornings bustling with deliveries, the din of his skilled shuckers pounding and prying open oysters, preparing orders. Then, on Saturday, April 24, the Sunseris and the rest of America heard that oil was leaking from the rig's broken riser. With each passing day, the news only got worse.
¶P&J oysters are an institution in New Orleans, a celebrated brand proudly listed on local menus as a promise of taste and quality. P&J specializes in Louisiana oysters; most of their suppliers farm in the Barataria Basin, west of the Mississippi River. P&J had survived floods, the Great Depression, and even Hurricane Katrina. But now, the Sunseri family and the staff were all at the mercy of a runaway oil spill, with no end in sight.
¶Throughout May, the Macondo well gushed on unchecked, and by early June, the government had closed Louisiana oyster beds. The Sunseris had taken over from their father 25 years earlier. Now, for the first time, they had to lay off 11 skilled shuckers. "These ladies here, those guys—I grew up with them," Al said. "We were in our twenties when we started." Longtime employee Wayne Gordon, 42, had been shucking at P&J since he was 18: "Twenty-four years. I cannot imagine not being here." As the shuckers worked their way through what was to be the final pile of succulent Louisiana shellfish, the owner of a nearby restaurant appeared with a breakfast buffet of scrambled eggs, fried ham, grits, and biscuits. "After a funeral, we bring food," said the restaurateur, a longtime customer.
¶Al's son Blake, 24, has spent the past three years learning the business, intent on becoming the sixth family generation to run it. "This is a real devastating event for me," he said. "This is my home, it feels like I don't really have a say in what's going on around me." He could have been speaking for millions of his fellow Americans, all along the Gulf of Mexico coast, who suddenly found themselves and their worlds facing ruin from what his uncle, Sal, called "this unnatural, unnatural catastrophe."
164problem quickly enough to avoid lasting damage, the Team recommended monitoring shut-in pressure at the BOP as well as visual, seismic, sonar, and acoustic data.275 Because shutting the capping stack would increase the pressure inside the well, the government was also concerned about bursting either the rupture disks (if they had not already collapsed) or another weak point in the casings. One industry executive recalled discussing this issue on a conference call with the science advisors; he expressed his view that allowing the pressure to climb above the level recorded during the top kill would be traveling into uncharted territory, with uncertain risks.
On July 9, as analysis of these risks continued, Admiral Allen authorized BP to install the capping stack, but not to close it.276 The extremely complicated operation began the next day. After removing the top hat from the top of the riser, remotely operated vehicles had to unbolt the stub of riser connected to the top of the Deepwater Horizon BOP stack, remove this stub, look for any pieces of drill pipe sticking up through the top of the BOP stack, slide the capping stack into place, and bolt it to the BOP stack. The process went smoothly, and BP finished installing the capping stack without incident by July 12. Suttles described this installation as the best operation of the entire source-control effort.277
BP next prepared to temporarily close the capping stack in a planned "well integrity test," to determine whether the well had been compromised and oil could flow into the rock formation. In a July 12 letter, Admiral Allen formally authorized the test to begin.278 But it did not. About two hours before the test was supposed to start, the government teams met with BP and industry representatives, including from Exxon (in person) and Shell (by phone). Secretary Chu and Admiral Allen were both present in person. BP faced significant criticism of the wisdom of attempting the test, with Exxon and Shell raising concerns associated with shutting in the well that had yet to be considered by BP or the government.279 In the most extreme scenario, one industry expert suggested that an underground blowout could cause the sands around the wellhead to liquefy and the entire BOP to disappear into the sea floor.280 Because Secretary Chu and the science advisors believed that these risks required further study, Admiral Allen delayed the test to allow for 24 hours of additional analysis.281
Overnight, the government science teams reached out to industry and academia for help. By 10:00 the next morning, experts had reassured the government that catching a leak early enough would prevent catastrophic consequences.282 With the government teams satisfied, Admiral Allen reauthorized the well integrity test. The test was to last from 6 to 48 hours, and BP had to monitor pressure, sonar, acoustic, and visual data continuously, as recommended by the Well Integrity Team.283 Secretary Chu required BP to dedicate two remotely operated vehicles to visually monitor for leaks at the wellhead.
165Although the Well Integrity Team had calculated that it would take a leak of approximately 100,000 barrels for oil and gas to reach the sea floor, the government was prepared to permit a leak of only 20,000 barrels before requiring the capping stack to be reopened.284 Using an estimate for the expected pressure at shut-in derived from BP's modeling of the reservoir, the Team developed guidelines for the length of the test.285 If the pressure at shut-in was less than 6,000 pounds per square inch, major well damage was likely—BP would
¶FIGURE 5.1: Protocol for Well Integrity Test have to terminate the test within six hours and reopen the well. If the shut-in pressure was greater than 7,500 pounds per square inch, the risk of a leak was low, and the test could proceed for the full 48 hours. Finally, if the shut-in pressure was between 6,000 and 7,500 pounds per square inch, the risk of a leak was uncertain—either there was a medium-sized leak or the reservoir was highly depleted. Under this scenario, the test could proceed for 24 hours. (See Figure 5.1.) If the pressure was too high, there was also the risk of causing a new rupture.
¶After a 24-hour delay to repair a minor leak, BP shut the stack and began the well integrity test at about 2:25 p.m. on July 15.286 For the first time in 87 days, no oil flowed into the Gulf of Mexico. Initial wellhead pressure readings were just over 6,600 pounds per square inch—in an uncertain middle range that one senior administration official termed "purgatory"—and rising slowly.287 Later that afternoon, the science advisors, including McNutt and Hunter, met with Secretaries Salazar and Chu to determine whether to keep the well shut in. Based on the early pressure data, the group appears to have been firmly in favor of reopening the well. Garwin, who had opposed even undertaking the well integrity test, voiced the strongest opinion, arguing BP ought to stop the test immediately and wondering whether it was already too late. No one at the meeting appears to have argued in favor of keeping the well closed.288
¶Following the science team meeting, Admirals Allen and Cook, Browner, Secretaries Chu and Salazar, and McNutt had a series of conversations to determine how to proceed. Keeping the capping stack shut could cause an underground blowout and, in the worst case, loss of a significant portion of the 110-million-barrel reservoir into the Gulf.289 This risk had to be balanced against the benefit of stopping the spill, a continuing
166environmental disaster. The government decisionmakers recognized that the public wanted the well plugged and the flow of oil into the Gulf stopped, but the risk of causing greater harm was real.
Admiral Cook made the argument that eventually prevailed. He reminded the others that, before the test began, BP and the government had considered the possibility of pressure measurements like those being observed. Both had agreed that, in such a case, the test should last 24 hours, with consultation between the parties before reopening the well.290 The government leaders decided that they should follow this protocol: the stack would stay closed overnight.
This additional time proved critical. Using a single cell-phone photograph of the plot of initial pressure readings, Paul Hsieh, a U.S. Geological Survey scientist then in Menlo Park, California, worked overnight to develop an explanation of the results of the test, including the lower-than-expected shut-in pressure. Pre-test expectations had been based on an incomplete understanding of the reservoir's geometry and on pressure readings from a single gauge at the bottom of the BOP, which was only accurate to plus or minus 400 pounds per square inch and functioning sporadically. At the government's behest, BP had equipped the capping stack with pressure gauges.291 Following the shut-in of the well, those gauges provided accurate pressure data for the first time. Using that data along with a flow-rate estimate of 55,000 barrels per day and BP's estimate that the reservoir contained 110 million barrels of oil, Hsieh was able to generate a model that predicted the observed shut-in pressure without having to assume a significant oil and gas leak into the rock formation.292
The next morning, the government principals and the science advisors—who had been convinced that reopening the stack was necessary—hosted a meeting. Both BP and Hsieh made presentations explaining the observed pressures at shut-in, with BP arguing that the well should remain capped.293 Participants had different recollections as to whether Hsieh's or BP's presentation carried more weight. But the outcome of the meeting was clear: the stack would stay shut, with the government reevaluating that decision every six hours.
While it went unrealized at the time, a critical point had passed. As intense monitoring of the area around the wellhead continued over the next several days, Hsieh's model continued to predict the behavior of the well, and a leak into the formation became progressively less likely.294 Although the well integrity test had originally been scheduled to last a maximum of 48 hours, Admiral Allen began to extend it in 24-hour increments beginning on July 17. At his July 24 press briefing, he stated what was by then plain: "our confidence [in the capping stack] is increasing and we have better integrity in the well than we may have guessed."295
167Meanwhile, on July 19, BP publicly raised the possibility of killing the well before completing a relief well, through a procedure called a "static kill."296 Like the top kill, the static kill involved pumping heavy drilling mud into the well in an effort to push oil and gas back into the reservoir. But because the oil and gas were already static, the pumping rates required for the static kill to succeed were far lower than for the top kill.
¶The primary concern with the static kill was the pressure it would put on the well. On July 28, BP received an unsolicited letter from Pat Campbell, a Vice President at Superior Energy Services, which owned BP contractor Wild Well Control, recommending in no uncertain terms that the static kill not proceed. Campbell, who had worked with legendary well-control expert Red Adair, reiterated a point already raised by others in the industry: that the only pressure the well could withstand for certain was the current shut-in pressure (approximately 6,920 pounds per square inch at the time he wrote).297
¶Despite these issues, after some delays caused by weather and work on the first relief well, the government approved the plan for the static kill on August 2.298 A mud injection test began on August 3, and pressure at the wellhead increased only slightly before beginning to drop.299 Based on the positive results of the test, BP began slowly pumping more drilling mud into the well later that same day. By 11:00 p.m., the static kill had succeeded.300 The following evening, Admiral Allen authorized BP to follow the mud with cement.301 BP finished cementing the next day. On August 8, Admiral Allen reported that the cement had been pressure-tested and was holding.302
¶The Fate of the Oil (August 4) On August 4, the same day it announced the static kill's success, the federal government released a 5-page report titled BP Deepwater Horizon Oil Budget: What Happened to the Oil?, as well as a 10-page supporting document titled Deepwater Horizon MC252 Gulf Incident Oil Budget.303 The "Oil Budget" provided the government's first public estimate of the total volume of oil discharged during the spill—roughly 4.9 million barrels. The government arrived at this number using its current flow-rate estimate, which ranges from 62,200 barrels per day on April 22 to 52,700 barrels per day on July 14, just before the capping stack stopped the flow.304 * The Oil Budget also described the efficacy of different response methods.
¶The Oil Budget was originally an operational tool, intended as a guide for responders, not as the basis for a scientific report on what happened to the oil. Nonetheless, in late July, the White House decided to publicly release the Oil Budget and asked NOAA to take the lead on drafting a short report to introduce the tool.305 The Budget cleared the interagency review process in time for its August 4 release.†
¶The White House's Browner appeared on six morning newscasts on August 4 to discuss both the successful static kill and the Oil Budget report. On NBC, MSNBC, and ABC, she told viewers that, according to the report, "the vast majority," or approximately three-quarters, of the oil "is gone" or "appears to be gone."‡ The Budget, however, did not *
¶The government's estimate, which is current as this report goes to press, has an uncertainty factor of ±10 percent. It is the Commission's understanding that the government's Flow Rate Technical Group will issue a final report in January 2011. In a peer-reviewed paper published in Science Express on September 23, 2010, Timothy Crone and Maya Tolstoy of Columbia University's Lamont-Doherty Earth Observatory estimated that the total release was roughly 5.2 million barrels—slightly higher than the government's estimate. While BP has not released its own flow-rate figures, it has suggested that the government's estimate of the total amount of oil released from the Macondo well is 20 to 50 percent too high. †
¶During the review process, EPA expressed concerns about the pie chart's potential to obscure the uncertainty of the government's estimates. Lisa Jackson, e-mail to Jane Lubchenco, July 31, 2010. For example, EPA recommended that NOAA combine chemically and naturally dispersed oil into a single category because there was not enough information to accurately distinguish between the two mechanisms. Bob Perciasepe, e-mail to Jane Lubchenco and others, July 31, 2010; Bob Perciasepe, e-mail to Stephen Hammond and others, August 1, 2010. NOAA disagreed. Administrator Jane Lubchenco asserted that combining the two categories would not decrease any uncertainty and that "'[c]hemically dispersed' is part of the federal response and 'naturally dispersed' is not, and there is interest in being able to sum up the federal response efforts." Jane Lubchenco, e-mail to Bob Perciasepe and others, August 1, 2010. ‡
¶On the other three shows, Browner similarly stated that "what the scientists are telling us is that the vast majority of the oil has been cleaned, it's been captured, it's been skimmed, it's been burned, mother nature has done its part" (Fox News); "our scientists are telling us that the vast majority of the oil has been contained, it's been burned, it's been cleaned" (CBS); and "our scientists and external scientists believe that the vast majority of the oil has now been contained, it's been skimmed, mother nature has done its part, it's been evaporated" (CNN).
168¶FIGURE 5.2: August 4 Oil Budget
Deepwater Horizon Oil Budget Based on estimated release of 4.9m barrels of oil
Unified Residual includes oil Command that is on or just below the surface as light Response Direct Recovery sheen and weathered from Operations Residual* Wellhead tar balls, has washed Burned 26% 17% 5% ashore or been collected from the Skimmed shore, or is buried in 3% sand and sediments. Evaporated or Chemically Dissolved Naturally Dispersed* 25% 8% Dispersed* 16% * Oil in these three categories is currently being degraded naturally.
show that most of the oil was gone. The three-quarters of the oil not in the "remaining" category included "dissolved" and "dispersed" oil that was potentially biodegrading, but not necessarily gone. By 9:00 a.m., NOAA Administrator Jane Lubchenco e-mailed Browner's deputy and other officials to express her concern "that the oil budget is being portrayed as saying that 75% of the oil is gone": "It's not accurate to say that 75% of the oil is gone. 50% of it is gone—either evaporated or burned, skimmed or recovered from the wellhead." Lubchenco asked the officials to "help make sure" the error was corrected.306* She had made the same point to the White House before the Budget rollout; a July 30 e-mail to Browner's deputy had emphasized that Lubchenco opposed grouping dispersed oil with recovered oil because the former was "still out there or [was] being degraded."307
At a press briefing that afternoon, Browner said that the report had "been subjected to a scientific protocol, which means you peer review, peer review, and peer review." Earlier in the same briefing, Lubchenco had said "[t]he report was produced by scientific experts from a number of different agencies, federal agencies, with peer review of the calculations that went into this by both other federal and non-federal scientists."308 The Budget, however, was not "peer-reviewed" as the scientific community uses that term. Many of the outside scientists listed as reviewers had not even seen the final report.
The rollout of the Oil Budget drew immediate criticism, with scientists pointing out that Browner's optimism about the percentage of the oil that was gone was unsupported, especially because of the uncertain rate of biodegradation.309 Moreover, after a summer of ever-increasing official estimates of the spill's size, the public was dubious of the government's conclusions. As aTimes-Picayune editorial noted, "From the start of the
169
- The U.S. Geological Survey, which had also been involved in developing the Oil Budget tool and editing the report, expressed similar misgivings about the portrayal of the report. At 11:00 a.m., U.S. Geological Survey scientist Mark Sogge told a colleague, "We need to keep in mind, and make it clear to others, that this is NOT a [U.S. Geological Survey] product." Mark Sogge, e-mail to Stephen Hammond, August 4, 2010.
¶disaster. . . the government has badly underestimated the amount of oil spewing from the runaway well. That poor track record makes people understandably skeptical of [the Oil Budget] report."310 Lubchenco has since acknowledged that she was "in error" when claiming that the Oil Budget had been peer-reviewed.311 NOAA has emphasized that the report's "purpose was to describe the short-term fate of the oil and to guide immediate efforts to respond to the emergency" rather than to "provide information about the impact of the oil" or "indicate where the oil is now."312
¶NOAA supplied these explanations on November 23, when it released a new version of the Oil Budget: Oil Budget Calculator Technical Documentation, a peer-reviewed report of over 200 pages that gave the formulas used and updated the percentages in the original budget.313 The new version's biggest change was its estimate of the amount of oil chemically dispersed, which doubled from 8 percent to 16 percent. Of this additional 8 percent,3 Testimony of Nathaniel Chaisson, 411; U.S. Department of Energy, Well Configuration (BP document made public by the Department of Energy), http://www.energy.gov/open/documents/3.1_Item_2_Macondo_Well_07_Jun_1900.pdf; Testimony of Natalie Roshto, Hearing before the Deepwater Horizon Joint Investigation Team, July 22, 2010, 15. Daniel Yergin, The Prize: The Epic Quest for Oil, Money, and Power (New York: Simon and Schuster, 1992), 409. Internal BP document (BP-HZN-MBI 126338). Campbell Robertson, "11 Remain Missing After Oil Rig Explodes Off Louisiana," New York Times, April 22, 2010. EPA, Government Response to the BP Oil Spill: Odors from the BP Spill (June 2010), http://www.epa.gov/bpspill/ reports/odorfactsheet.pdf (announcing help line for residents experiencing oil-related odors); Press Release, NOAA, Administration Launches Dockside Chats to Promote Gulf Seafood Safety Awareness, August 25, 2010, http://www. restorethegulf.gov/release/2010/08/25/administration-launches-dockside-chats-promote-gulf-seafood-safety- awareness; BP, Claims and Government Payments Gulf of Mexico Oil Spill Public Report (November 18, 2010). Health and Safety Executive, Major Incident Investigation Report, BP Grangemouth Scotland (29th May – 10th June 2000) (August 18, 2003), 7, http://www.hse.gov.uk/comah/bpgrange/images/bprgrangemouth.pdf. These terms are taken directly from the Council on Environmental Quality (CEQ) NEPA implementing regulations. 40 C.F.R. § 1508.28. 4 40 C.F.R. §1508.4. percent came from the "naturally dispersed" category,2 Internal BP document (BP, presentation to Commission, August 9, 2010, slides 5 & 12). Quoted in Tom Zoellner, "Oil and Water: The Adventure of Getting One from Deep Beneath the Other," Invention and Technology (Fall 2000): 48. Internal Transocean document (TRN-HEC 90686). Internal documents are identified by their document production serial numbers when available, which were assigned by the entity that provided them. Neil MacFarquhar, "Routine Flights Become Overland Odysseys, Minus Clean Socks," New York Times, April 22, 2010. Campbell Robertson and Clifford Krauss, "Gulf Spill Is the Largest of Its Kind, Scientists Say," New York Times, August 2, 2010. BP, Sustainability Review (2009), 20–21. http://www.bp.com/assets/bp_internet/globalbp/STAGING/global_assets/ e_s_assets/e_s_assets_2009/downloads_pdfs/bp_sustainability_review_2009.pdf. See 43 U.S.C. § 1337(b)(6) ("An oil and gas lease issued pursuant to this section shall . . . contain such rental and other provisions as the Secretary may prescribe at the time of offering the area for lease."). percent from the "evaporated or dissolved" category, and 3 percent from the "residual" category. (These changes brought the total amount of "residual" oil down from 26 to 23 percent.)
¶As a tool for responders, the Oil Budget indicated that response and containment operations collected, eliminated, or dispersed about 41 percent of the oil, with containment ("direct recovery from wellhead") the most effective method, and chemical dispersants breaking down a substantial fraction. Response technology (skimming or burning) removed—as opposed to dispersed—only 8 percent of the oil. Dispersion of the oil before it reached the surface limited the amount that responders could skim, burn, or disperse at the surface. Nevertheless, responders considered burning an important success: it had never before been attempted on this scale, and burning techniques advanced during the spill.314 Skimming was less of a success: despite the participation of hundreds of ships and thousands of people, it collected only 3 percent of the oil.
¶The least effective response technology was the berms, which the Oil Budget documents do not even mention. By the time BP capped the well on July 15—day 44 of the berm construction project—Louisiana's contractor estimated that 10 percent of one reach—6 percent of the total project—had been completed.315 In late May, Governor Jindal had asserted that "[w]e could have built 10 miles of sand [berms] already if [the Corps] would have approved our permit when we originally requested it."316 In fact, it took five months to build roughly 10 miles of berms, at a cost of about $220 million.317 Estimates of how much oil the berms collected vary, but none is much more than 1,000 total barrels.318 On November 1, Governor Jindal announced plans to convert the berms into part of a long-term coastal restoration project, which BP would continue to fund. In his recently released book, the Governor maintained that the berms were "one of the most effective protection measures" against oil reaching the Louisiana coast.319
¶The End of the Well, but Not the End of the Response In mid-September, the first relief well—which BP had begun drilling in early May—finally intercepted the Macondo well, allowing BP to pump in cement and permanently seal the reservoir. On September 19,152 Ibid. Testimony of Charlie Williams, 46–53. Lee Gard, e-mail message to Commission Staff, December 13, 2010. days after the blowout, Admiral Allen announced: "the Macondo 252 well is effectively dead."320
170But fears about health and safety did not die with the well. Some Gulf residents continued to believe that BP had used dispersants onshore, nearshore, at night, and without government approval, and that it had continued using them after it capped the well. The Commission has not seen credible evidence supporting these claims. NOAA reopened one-third of the area closed to fishing on July 22 and continued to reopen additional sections based on a testing and sampling protocol developed and implemented with the Food and Drug Administration.321 But some scientists questioned the protocol, while some fishermen were hesitant to give up income from the Vessels of Opportunity program and return to their regular jobs in the midst of public concern about Gulf seafood.322 (Chapter 6 discusses seafood safety.)
Residents also had to cope with the miles of used boom and other debris. Despite the typical spill-responder uniform of rubber gloves and protective coveralls, BP planned to send the thousands of tons of oily debris generated over the summer to ordinary municipal landfills.323 Wastes from oil exploration and production are classified as non-hazardous by law and do not require specialized disposal.324 Although the federal government generally does not supervise the disposal of non-hazardous waste, on June 29, the Coast Guard and EPA issued a directive requiring BP to test its waste for hazardous elements, publicize the results, and consult with the communities where the waste was to be stored.325 In addition, EPA announced it would conduct its own twice-monthly testing of the debris and would post the results online.326 BP was initially slow to release its testing data. After receiving a sternly-worded letter from Federal On-Scene Coordinator Admiral Zukunft on July 24, however, it started regularly posting the results on its website.327 EPA began sampling the waste and posting the test data as well, after some criticism and delay.328 As of November 17, EPA's tests had not shown any of the waste to be hazardous.329
As BP and EPA implemented the waste directives, environmental justice activists argued that BP was dumping the debris disproportionately in poor and non-white communities.330 Residents of Harrison County, Mississippi fiercely opposed the disposal of oiled waste in their Pecan Grove landfill, and BP agreed not to use it.331 Environmental justice advocate and scholar Robert Bullard contended that the racial makeup of Harrison County was a factor, and EPA objected to BP's decision.332 The Federal On-Scene Coordinator instructed BP to follow the approved waste plan, noting that "[a]llowing one community to reject acceptance of waste. . . may complicate remaining waste disposal efforts." BP began to use the site for waste staging, though not for disposal.333
171With the well sealed, the number of responders in the Gulf decreased. The National Incident Command officially stood down on October 1.334 Admiral Allen turned over the remaining tasks to Federal On-Scene Coordinator Admiral Zukunft and finally retired. BP started to shut down some of its programs, and Coast Guard responders started to head to their next posts. The spill and the emergency response had ended. Figuring out the extent of the damage, and how to repair it, had begun.
¶"I don't know what to do with myself."
Dean Blanchard, Dean Blanchard Seafood Inc., Grand Isle, LA
Dean Blanchard runs Louisiana's biggest shrimp business, on Grand Isle—a Mississippi River Delta barrier island 50 miles south of New Orleans, fully exposed to the Gulf of Mexico. During the warm months of a typical shrimp season, Blanchard Seafood and its extensive network of bayside wharves are a frenetic cacophony of languages and accents—Spanish, Vietnamese, a smattering of Cajun French, and the various Deep South dialects—as more than a thousand
¶Susan Poag/The Times-Picayune. Photo © 2010 The fishermen offload the catch from their shrimping vessels. Times-Picayune Publishing Co., all rights reserved. The shrimp are sorted by size and dispatched into the Used with permission of The Times-Picayune.
¶world.
¶During 30 years in business, Blanchard had become one of the nation's principal suppliers—and a multi-millionaire. In season, he bought as much as 500,000 pounds of shrimp daily from more than a thousand fishermen. The cold 2009-2010 winter had raised high hopes: "Every 10 years, when you get a cold winter, you get a really good shrimp crop," he explained. "We were licking our chops."
¶But with the Macondo well gushing more than 50,000 barrels of oil a day, and no end in sight, the brown shrimp season had been canceled just as it was about to start. By mid-May, tar balls and oil had started washing up onto Grand Isle's wetlands and beaches. By mid-June, Blanchard figured, "I've lost $15 million of sales in the last 50 days. That would have been $1 million in my pocket." The usually busy docks were quiet, the only activity the occasional coming and going of boats and crews working for BP cleaning and containing the oil."I don't know what to do with myself," Blanchard explained. "I built all this over the last 30 years, and now for what?" "We've got 1,400 vessels that go and catch shrimp, come to our facility." Now, he continued, "basically we've lost all our customers because we can't supply them."
¶For decades, oil and seafood had mixed comfortably in Louisiana's coastal culture. Each year Morgan City hosted the annual Shrimp and Petroleum Festival, a rollicking celebration of the state's two high-profile economic mainstays. Oil has long provided the region's best-paying jobs, and the revenue to finance everything from state roads to free school books. The maritime world of seafood has deeper cultural roots, and provides a living and a way of life along the gulf coast, one of the nation's most productive fishing waters. Many families had members in both worlds. Indeed, Blanchard's own grandfather had made a fortune servicing the offshore oil industry.
¶But now those two worlds had collided—and everything seemed at risk.
173¶Chapter Six "The worst environmental disaster America has ever faced." Oiling a Rich Environment: Impacts and Assessment When President Barack Obama addressed the nation from the Oval Office on June 15—nearly two months after the Macondo well began gushing crude oil and one month before engineers subdued it—he said:
¶Already, this oil spill is the worst environmental disaster America has ever faced. And unlike an earthquake or a hurricane, it's not a single event that does its damage in a matter of minutes or days. The millions of gallons of oil that have spilled into the Gulf of Mexico are more like an epidemic, one that we will be fighting for months and even years.1
¶The Deepwater Horizon blowout produced the largest accidental marine oil spill in U.S. history,2 an acute human and environmental tragedy. Worse still, as discussed in Chapter 7, it occurred in the midst of environmental disasters related to land-based pollution and massive destruction of coastal wetlands—chronic crises that proceed insidiously and will require not months but decades of national effort to address and repair.
¶A lone beachgoer encounters bands of oil along Alabama's Orange Beach. Though wind and currents helped keep most of the spilled oil offshore, all told some 650 miles of Gulf Coast habitat were oiled to one degree or another— Louisiana was hardest hit—impacting ecosystems, the economy, and human health.
¶< Tyrone Turner/Photo courtesy of National Geographic
174Laws guide resolution of damages from the spill itself. There is a suite of policies and programs aimed at improving discrete environmental issues within the Gulf and along its coast. The law also provides compensation for direct economic impacts. This chapter analyzes these immediate impacts, not only on the natural environment but also on the economy and on human health in the affected region. Unfortunately, the human-health effects are the least-recognized fallout from the spill, and those least-well addressed in existing law and policies.
The Impact on Nature The Deepwater Horizon oil spill immediately threatened a rich, productive marine ecosystem. To mitigate both direct and indirect adverse environmental impacts, BP and the federal government took proactive measures in response to the unprecedented magnitude of the spill.3 Unfortunately, comprehensive data on conditions before the spill—the natural "status quo ante" from the shoreline to the deepwater Gulf—were generally lacking.4 Even now, information on the nature of the damage associated with the released oil is being realized in bits and pieces: reports of visibly oiled and dead wildlife, polluted marshes, and lifeless deepwater corals. Moreover, scientific knowledge of deepwater marine communities is limited, and it is there that a significant volume of oil was dispersed from the wellhead, naturally and chemically, into small droplets.5 Scientists simply do not yet know how to predict the ecological consequences and effects on key species that might result from oil exposure in the water column, both far below and near the surface.6
Much more oil might have made landfall, but currents and winds kept most of the oil offshore, and a large circulating eddy kept oil from riding the Loop Current toward the Florida Keys.7 Oil-eating microbes probably broke down a substantial volume of the spilled crude, and the warm temperatures aided degradation and evaporation8—favorable conditions not present in colder offshore energy regions.9 (Oil-degrading microbes are still active in cold water, but less so than in warmer water.) However widespread (and in many cases severe) the natural resource damages are, those observed so far have fallen short of some of the worst expectations and reported conjectures during the early stages of the spill.10 So much remains unknown that will only become clearer after long-term monitoring of the marine ecosystem. Government scientists (funded by the responsible party) are undertaking a massive effort to assess the damages to the public's natural resources. Additionally, despite significant delays in funding and lack of timely access to the response zone, independent scientific research of coastal and marine impacts is proceeding as well.
175A rich marine ecosystem. Particularly along the Louisiana coast, the Gulf of Mexico is no stranger to oil spills.11 But unlike past insults, this one spewed from the depths of the ocean, the bathypelagic zone (3,300–13,000 feet deep). Despite the cold, constant darkness and high pressure (over 150 atmospheres), scientists know that the region has abundant and diverse marine life. There are cold-water corals, fish, and worms that produce light like fireflies to compensate for the perpetual night. Bacteria, mussels, and tubeworms have adapted to life in an environment where oil, natural gas, and methane seep from cracks in the seafloor. Endangered sperm whales dive to this depth and beyond to feed on giant squid and other prey.12
¶Elmer's Island in Grand Isle, La.
¶A dark tongue of oil invaded sensitive wetlands last May near Grand Isle, Louisiana, despite the presence of booms deployed to stop it. In a hopeful development over the summer, scientists found new plant growth in similarly oiled marshes, indicating that oil had not penetrated into root systems.
¶Patrick Semansky/Associated Press
¶Higher up the water column, light and temperature gradually increase and the ascending sperm whales—and Macondo well oil—encounter sharks, hundreds of fish species, shrimp, jellyfish, sea turtles, and dolphins. As the sperm whales surface for air at the bright and balmy Gulf surface, they pass through multitudes of plankton, floating seaweed beds, and schools of fish. Some of these fish species spend their early lives in the coastal waters and estuaries; others travel along annual migration routes from the Atlantic Ocean to the Gulf. The floating seaweed beds (sargassum), fish larvae, and plankton drift with the surface currents and are driven by the wind—as is the oil rising from below. The critical sargassum habitats lure sea turtles, tuna, dolphins, and numerous game fish to feed on the snails, shrimp, crabs, and juvenile species that seek shelter and food in the seaweed.13
¶Overhead are multitudes of seabirds—among them brown pelicans, northern gannets, and laughing gulls—that in turn feed in the ocean and coastal estuaries.14 Dozens of bird species fly the Mississippi migration route each year, a major attraction for bird watchers, who flock to coastal Louisiana and Texas to catch a glimpse of migrating and resident shorebirds and nesting seabirds. Some of these birds feed on estuarine shrimp, fish, and crabs; others depend on shellfish and other small organisms that populate the expansive mudflats. Larger wading birds stalk their prey in the shallow water of mangroves, marshes, and other habitats that shelter fish and frogs. Raptors, including ospreys, bald eagles, and peregrine falcons, also pluck their prey from any of these environments and carry it to their perches.
¶As the unprecedented volume of oil gushing from the Macondo blowout reached the surface, it had the potential to affect all of these marine and coastal organisms and to wash into the salt marshes, mudflats, mangroves, and sandy beaches—each in its way an
176¶Oiled Sargassum
Wildlife biologist Mark Dodd surveys a raft of oil-soaked sargassum, also known as gulfweed. The floating beds are home to snails, shrimp, crabs, and other small creatures that—oiled or not—are ingested by turtles, dolphins, tuna, and game fish.
¶Blair Witherington/FWC
essential habitat at one or more stages of many species' lifecycles.15 And these marine and coastal species are so interdependent that a significant effect on any one has the potential to disturb several existing populations in this complex food web.16
Encountering oil. Organisms are exposed to oil through ingestion, filtration, inhalation, absorption, and fouling.17 Predators may ingest oil while eating other oiled organisms or mistaking oil globules for food. Filter feeders—including some fish, oysters, shrimp, krill, jellyfish, corals, sponges, and whale sharks—will ingest minute oil particles suspended in the water column. Surface-breathing mammals and reptiles surrounded by an oil slick may inhale oily water or its fumes. Birds are highly vulnerable to having their feathers oiled, reducing their ability to properly regulate body temperature.18 Moderate to heavy external oiling of animals can inhibit their ability to walk, fly, swim, and eat. Similarly, oiling of plants can impede their ability to transpire and conduct photosynthesis, and oiling of coastal sediments can smother the plants they anchor and the many organisms that live below.
Americans watched as the oil eventually came to rest along intermittent stretches of the Gulf coast. Before it arrived, scientists rushed to collect crucial baseline data on coastal and water-column conditions. Some of the oil propelled up from the wellhead was dispersed by natural and chemical means (as described in Chapter 5), creating a deep-ocean plume of oil droplets and dissolved hydrocarbons.19 A portion of the oil that rose to the surface was also naturally and chemically dispersed in the shallow water column.20
177The oil that made landfall was fairly "weathered," consisting of emulsions of crude oil and depleted of its more volatile components. More than 650 miles of Gulf coastal habitats—
¶salt marsh, mudflat, mangroves, and sand beaches—were oiled; more than 130 miles have been designated as moderately to heavily oiled. Louisiana's fragile delta habitats bore the brunt of the damage, with approximately 20 additional miles of Mississippi, Alabama, and Florida shorelines moderately to heavily oiled.21 Light oiling and tar balls extended east to Panama City, Florida. Except for occasional tarballs, Deepwater Horizon oil never reached Texas or the tourism centers along the southwest Florida coast.22
¶Assessing the mixture of oil and life at the water's edge. The most biologically productive area along a sandy beach occurs where seaweed and other organic materials wash up just above the high tide line in the "wrack zone." Here, shorebirds forage for insects and other small organisms. As oil moves onto a beach with the rising tide, it is deposited in the wrack zone. Removing oiled wrack is the most prudent means of removing the oil—but doing so removes the living community, too. As the response to the spill proceeded, the Audubon Society evaluated wrack density along shorelines; it found that the wrack density on beaches east of the Mississippi River, where cleanup activities occurred, was "nearly absent," indicating "diminished habitat quality."23
¶Few beachgoers realize that millions of microscopic organisms live in the Gulf 's soggy sands between high and low tide. By comparing samples taken before and after beaches were oiled, Holly Bik of the University of New Hampshire's Hubbard Center for Genome Studies, together with scientists at Auburn University and the University of Texas, hopes to determine the impact on this understudied community of sediment-dwelling microfauna.24
¶Tidal mudflats, generally devoid of vegetation and exposed at low tide, are more sensitive to pollutants than beaches.25 The Louisiana delta and the estuarine bays of Mississippi and Alabama have large expanses of tidal mudflats, which support dense populations of burrowing species (vulnerable to smothering), foraging birds, crabs, and other organisms.26 As oil settles on the flats, crabs and other burrowing animals help mix the oil into the sediment layer (an ecological process called bioturbation), extending the potential damage below the surface.27
¶Salt marsh and mangroves are both highly productive and sensitive habitats. Marsh grasses tolerate surface coating by weathered oil fairly well, but they will die if oil penetrates the saturated sediments and is absorbed by the root system.28 When that happens, the plants' root systems degrade, making the marsh much more susceptible to erosion and threatening the habitat on which a wide variety of animals depend. People and equipment deployed in response to the spill can themselves damage the marsh; for example, summer storms pushed boom (used to corral waterborne oil) deep into the marshes, from which it could only be removed by intrusive methods that caused additional harm to the marsh topography.29 Scientists working in oiled marshes observed new plant growth during the summer of 2010—a positive sign that oil had not penetrated into the rich, organic soils and inhibited root systems.30 Professor Eugene Turner of Louisiana State University's Coastal Ecology Institute plans to study the effects of oil on the local salt marshes for at least the next year. His preliminary observations, through the fall of 2010, indicate some stress resulting in loss of marsh along its edge, but the estimated loss "pales
178in comparison" to the annual loss associated with dredging and flood protection (described in Chapter 7).31
The marine impacts. When water temperatures warm in the late spring, female oysters release millions of eggs into the water column. The timing of the Macondo oil spill may have been detrimental to oyster reproduction and the spawning of many other species.32 Submerged oil floating in the nearshore water column poses potential threats to diverse shellfish and fish species. Although the impacts are not yet known, the presence of oil in the nearshore environment has been documented. Oil that reached the Gulf 's estuarine waters forced closures of and likely damaged substantial tracts of Louisiana oyster beds.33 Oyster mortality observed in the highly productive areas of Barataria Bay and Breton Sound, estuaries that flank the lower Mississippi River, appear to be due, in large part, to the flood of fresh water introduced through river diversions in what many believe was a futile attempt to keep oil from entering the estuarine areas.34
Beyond their commercial import, oysters are a keystone species—an organism that exerts a shaping, disproportionate influence on its habitat and community.35 A single adult oyster can filter more than one gallon of water per hour, effectively removing impurities— including oil—from the water column.36 Oyster reefs established on an estuary's muddy bottom can increase the surface area fifty-fold, creating intricate habitats for crabs, small fish, and other animals, which in turn sustain larger species.37
Harriet Perry, Director of the Center for Fisheries Research and Development at the University of Southern Mississippi, and scientists at Tulane University are studying the potential effects of oil on larvae of blue crabs, another keystone species. The slick from the Macondo oil spill ultimately covered about 40 percent of the offshore area used by larvae of the northern Gulf 's estuarine-dependent species.38 The Gulf coast's blue crab population had already declined considerably during the past 8 to 10 years as a result of a regional drought.39 Perry and other scientists raced to take samples before the oil arrived and then after, hoping to be able to separate the oil-related impacts on wildlife from climate-related changes.40
Many large fish species are dependent on the health of the estuarine and marine habitats and resources. The National Oceanic and Atmospheric Administration (NOAA) noted that species with "essential fish habitat"41 near the oil spill include scalloped hammerhead, shortfin mako, silky, whale, bigeye thresher, longfin mako, and oceanic whitetip sharks; and swordfish, white marlin, blue marlin, yellowfin tuna, bluefin tuna, longbill spearfish, and sailfish. Other important Gulf fish include red snapper, gag grouper, gray triggerfish, red drum, vermilion snapper, greater amberjack, black drum, cobia and dolphin (mahi- mahi); coastal migratory open-water species, such as king and Spanish mackerel; and open-water sharks.42
179Oil in the water column affects fish and other marine organisms through dermal contact, filtration, or ingestion. How much oil they accumulate depends on its concentration in food, water, and sediments they encounter, time and exposure, and the characteristics of each species—particularly the extent of their fatty tissue. Although oil is not very soluble
¶"I have to make house payments and boat payments."
Ve Van Nguyen, Oysterman, Buras, LA
Ve Van Nguyen was an oystermen working for one of the suppliers to P&J Oyster Company. A Vietnamese refugee who fled his homeland with his wife and young family in a boat in 1978, Van Nguyen had made it to the United States. He eventually settled in Buras, located in Plaquemines Parish in 1983, joining a large
¶Claire Luby
Vietnamese and Cambodian community that found limited
¶English skills no impediment to earning a living fishing and shrimping. He had been a fisherman in Vietnam, and as he explained in his native language, "I grew up near the sea and I'm used to eating seafood. I wanted to live where there's lots of seafood." He and his wife had both worked on the water, and in recent years they had purchased two specially outfitted oystering boats, in addition to two other boats used for gill fishing. They had loans to repay. In 2009, when they had $80,000 in income from harvesting oysters, that was not a problem. Their four children were grown, with one still at home.
¶When Van Nguyen heard on television about the oil spill, he recalls, "I felt that I was going crazy and was really worried that I can't work anymore. I was afraid that the oil would spread and people can't eat what we catch so I wouldn't be able to work. So I was going through a mental crisis." Louisiana has about 25,000 Vietnamese Americans.
¶All through May, the Macondo well gushed oil as the government was closing Louisiana oyster beds. Ve Van Nguyen and his wife both found interim work using their boats to install booms against the spreading oil slicks, as part of BP's clean up. But he made nowhere near as much money as he would have harvesting oysters. Like so many others around the Gulf, he said, "I worry about myself and my wife. I don't know how we can make it." He had received some BP payments, but wondered how long those would go on? "I have to make house payments and boat payments." At age 60, he was no longer young, but certainly expected to continue oystering. But now, if BP does not compensate him for an amount similar to the lost income, "I can't do anything except for applying for welfare and food stamps." He had had his four boats towed back to his house. The future? "Everyone is worried and scared about that. They are scared of poisoning so we have to rely on the government to take care of it. I don't know what will happen."
180¶Turtle in East Grande Terre Island, LA
Sad testament to the spill, a sea turtle lies dead beside the black tide that took its life along East Grand Terre Island in Louisiana. As of November 2010, the carcasses of more than 600 of the endangered reptiles had been collected. Countless others undoubtedly perished.
¶Benjamin Lowy/Edit by Getty Images
in water, oil and lipids do mix very well, so high concentrations of petroleum can be found in the fat-rich tissues of the liver, brain, kidneys, and ovaries. Muscle generally has the lowest lipid concentrations, but fish with fatty flesh can accumulate more oil than leaner species.43 Oil constituents can be transferred through the food chain: heavier hydrocarbons can be passed from water to phytoplankton and then to zooplankton, or from sediments to polychaete worms and eventually to fish.44 Because animals that are several steps up the food chain, like small fish, have the capability to metabolize hydrocarbons fairly rapidly, their predators will actually not accumulate much from eating them. Accordingly, bioaccumulation of toxic oil components does occur in fish, but biomagnification, with increasingly higher concentrations in animals at each level, does not occur.45
181It would be impossible to sample and assess each of the thousands of marine fish and other species inhabiting the open-ocean water column. But scientists monitoring the spill along the shorelines and aboard research vessels have sampled plankton, shellfish, fish, water, sediment, and other environmental media to better understand the potential impacts on all terrestrial and marine organisms.46 Tens of thousands of samples have been collected. They will likely analyze the samples to determine concentrations of oil and dispersants, and combine that information with existing data on species populations and distributions to model the potential impact of contamination in the water column on different species. In addition, large fish—like bluefin tuna and whale sharks (the world's largest fish)— mammals, and turtles are being tagged with tracking devices so scientists can follow
¶their movements in the hope of learning how they have been affected by the spill.47 By overlaying maps of the extent of the oil spill, derived from satellite images from the European Space Agency, with simulations of bluefin tuna spawning grounds and models of larval development, the Ocean Foundation estimated that the spill could have affected 20 percent of the 2010 season's population of bluefin tuna larvae, further placing at risk an already severely overfished species.48
¶Birds, mammals, turtles. Oiled birds are often the most visually disturbing and widely disseminated images associated with a major oil spill—as in the landmark Santa Barbara accident of 1969.49 Through November 1, 2010, wildlife responders had collected 8,183 birds, 1,144 sea turtles, and 109 marine mammals affected by the spill—alive or dead, visibly oiled or not.50 Given the effects of hiding, scavenging, sinking, decomposition, and the sheer size of the search area, many more specimens were not intercepted.51 Therefore, scientists will assess the estimated total damage by applying a multiplier to the final observed number of casualties, and will likely issue separate estimates of sub-lethal effects and the impact of the spill on future populations.
¶In September 28 testimony before the Commission, Jane Lyder, Deputy Assistant Secretary of the Department of the Interior for Fish and Wildlife and Parks, said that "With more than 60 percent of the data verified, the three most affected [bird] species appear to be Brown Pelicans, Northern Gannets, and Laughing Gulls." She added that "The fall migration is underway. Songbirds and shorebirds began their migration to the Gulf coast in July. Waterfowl began arriving in late August and early September. We know there are significant impacts to marsh and coastal wetland habitats along sections of the Louisiana coast, particularly near Grand Isle, Louisiana. We are continuing to monitor what the full impact will be to migratory birds and other wildlife."52
¶The potential impact on marine mammals and sea turtles is harder to assess. Tim Ragen, Executive Director of the federal Marine Mammal Commission, testifying before a House of Representatives subcommittee on June 10, 2010, could only conclude, "Unfortunately, the scientific foundation for evaluating the potential effects of the Deepwater Horizon spill on many marine mammals inhabiting the Gulf is weak."53
¶According to NOAA, "Of the 28 species of marine mammals known to live in the Gulf of Mexico, all are protected, and six (sperm, sei, fin, blue, humpback and North Atlantic right whales) are listed as endangered under the Endangered Species Act." Also of note, "At least four species of threatened/endangered sea turtles (Kemp's ridley, green, leatherback, and loggerhead) are residents of the northern Gulf of Mexico and are represented by all life stages. A fifth species, the hawksbill turtle, can be found in the southern Gulf. The only nesting beaches in the world for Kemp's ridley turtles are in the western Gulf of Mexico."54 As of November 1, the Unified Area Command reported that nine marine mammals had been collected alive (and three were released).55 One hundred mammals were collected dead, though only four of those were visibly oiled. Most of the marine mammal mortalities were bottlenose dolphins.56 Also among the dead was one juvenile sperm whale; it was found floating more than 70 miles from the source of the spill, reportedly unoiled.57 More than 600 dead sea turtles were collected.58
182Deepwater plumes of dispersed oil. The highly visible damage to wildlife aside, public and scientific concern about the Deepwater Horizon spill—at unprecedented water depths— has for some time focused on the impacts of an invisible subsurface "plume," or more accurately "clouds" of minute oil droplets moving slowly over the seabed. As of November 2010, three independent, peer-reviewed studies59 confirmed the presence of a deepwater plume of highly dispersed oil droplets and dissolved gases at between 3,200 and 4,200 feet deep and extending for many miles, primarily to the southwest of the wellhead.
How will such substances affect the deepwater environment? One concern centered on decomposition and the resulting depletion of the oxygen supply on which aquatic species depend. Bacterial decomposition begins quickly for the light hydrocarbon gases, propane and ethane, but more slowly for the heavier hydrocarbons typically present in a liquid form and for the predominant gas, methane. The blooms of bacteria stimulated by lighter hydrocarbons prime the populations for degradation of other hydrocarbons. The degradation rates are sufficient to reduce the dissolved oxygen concentrations in the plume, but not to harmfully low levels associated with dead zones, where aquatic species cannot survive.60 Subsequent mixing with adjacent, uncontaminated waters by slow-flowing currents appears to have been sufficient to prevent any further depletion of dissolved oxygen in the aging plumes.61 These findings do not rule out potential impacts of deepwater oil and dispersant concentrations on individual species.62 Chemical analyses of water samples taken from the established deepwater plume in May 2010 suggest that hydrocarbon concentrations were high enough at the time to cause acute toxicity to exposed organisms,63 although concentrations declined over several miles from the well as the plume mixed with the surrounding water.
Federal scientists have estimated that about 15 percent of the oil escaping the wellhead was physically dispersed by the fluid turbulence around the flow of oil and gas. The deepwater plume would have formed even if chemical dispersants had not been injected at the wellhead. But the addition of 18,379 barrels of dispersants to the discharging oil and gas stream may have increased the volume of oil in the deepwater plumes to a degree comparable to that from physical dispersion alone.64 As of late 2010, there have been unconfirmed reports of oil deposited on the seafloor in the vicinity of the Macondo well.65 If confirmed by chemical analyses, this would not be particularly surprising because oil droplets can become entrained in denser particulate matter, including the flocks of organic matter (referred to by scientists as "marine snow") that characterize open-ocean waters, and settle on the ocean floor. There have also been recent reports of dead or dying deepwater corals living on rock outcrops that could have been impinged by the deep plumes.66
183Because the Deepwater Horizon spill was unprecedented in size, location, and duration,67 deepwater ecosystems were exposed to large volumes of oil for an extended period. It will take further investigation and more time to assess the impacts on these ecosystems, their extent and duration. Unfortunately, except for studies that have focused on rare and specialized communities associated with rocky outcrops or seeps, scientific understanding of the deepwater Gulf ecosystem has not advanced with the industrial development of deepwater drilling and production.68
¶Figure 6.1: Assessment Categories for Natural Resource Damage Assessment
SHORELINES TERRESTRIAL AND
¶TURTLES AND • Aerial surveys
MARINE MAMMALS AQUATIC SPECIES
¶• Ground surveys HUMAN USE
¶WATER COLUMN • Aerial surveys • Observations of the • Ground surveys
¶AND SEDIMENTS • Tissue sampling quality of habitat • Observations of the • Aerial surveys
¶• Acoustic • Measurements of quality of habitat • Ground surveys
¶• Water quality surveys monitoring subsurface oil near the
¶• Transect surveys to • Satellite tagging shore detect submerged oil
¶• Oil plume modeling
¶• Sediment sampling
¶Wellhead